1. A sporting goods store is planning to open an outlet in a college town. The activities consist of the hiring of the manager of the outlet and his/her employees. Also it is necessary to coordinate the renovation of a building that previously was a fast food restaurant. To schedule this project using PERT, the following time estimates (in weeks) are gathered:

  1. What is the critical path and expected completion time for this project?   (15 pts)
  1. Which activity has the largest slack, and how large is that slack? (5 pts)
  1. What is the probability that the project is completed in 26 weeks and 24 weeks? (15 pts)

Activity

Description

Opt.

time

Likely

time

Pess.

time

Predecessors

A

Interview at college for new manager

4

10

16

None

B

Renovate building

4

6

20

None

C

Purchase new equipment for new outlet

1

4

7

B

D

Check references for new manager and make final selection

2

4

6

A

E

Place ad for new employees & interview applicants

3

3

3

D

F

Install new equipment

2

4

6

C

G

Make final selection for employees

3

3

3

E

H

Hold orientation meetings for employees

2

2

2

F,G

0 0
Add a comment Improve this question Transcribed image text
Answer #1

We first calculate the expected time using the formula

Expected time = (opt + 4*likely + pess)/6

And then calculate the variance using the formula

Variance = [(pess – opt)/6]^2

Then we calculate the early start, early finish, late start, late finish and slack based on the expected time.

The calculated table is shown below

Opt. Likely Pess. Predecessors Expected Variance time LS 0 Slack 0 1 Activity Description time ES time time 16 20 time 10 12

a.

The critical path is A-D-E-G-H and the expected completion time is 22 weeks

b.

The activities B,C, and F has the largest slack of 4 each.

c.

The project variance (along the critical path) is 4.44. The standard deviation is sqrt(4.44) = 2.1

26 weeks:

For 26 weeks, the z value is (26 – 22)/2.1 = 1.90

The probability at z = 1.90 is 0.9712 or 97.12%

24 weeks:

For 24 weeks the z value is (24-22)/2.1 = 0.95

The probability at z = 0.95 is 0.8289 or 82.89%

Add a comment
Know the answer?
Add Answer to:
1. A sporting goods store is planning to open an outlet in a college town. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • Module 5 Assisted Problems M5_A1. A farm owner is going to erect a maintenance building with a connecting electrical ge...

    Module 5 Assisted Problems M5_A1. A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table IMMEDIATE TIME ACTIVITY ACTIVITY DESCRIPTION (WEEKS) PREDECESSORS A Excavate 2 Erect building Install generator A 6 C A 4 Install tank A 2 Install maintenance equipment B 4 E Connect generator and tank to building Paint finish В, С, D P 5 3 Check...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • Use a PERT network to establish the expected duration for the project described in the table...

    Use a PERT network to establish the expected duration for the project described in the table below:    (SHOW the PERT NETWORK) Activity Predecessors Duration a        m       b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400         600 D B, C 4 6 8 200                             600 E B, C 6 9 12 400 300 F C 4 6 14...

  • Operation management

    The following activities are part of a project to be scheduled using CPM.Activity Immediate predecessors Time(Weeks)A - 6B A 3C A 7D C 2E B,D 4F D 3G E,F 7i) Draw the networkii) What is the critical path?iii) How many weeks will it take to complete the project?iv) How much slack does activity B have?

  • QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are s...

    QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...

  • Show step by step solutions. (a) Complete the expected duration, standard deviation and variance for activities...

    Show step by step solutions. (a) Complete the expected duration, standard deviation and variance for activities A and B and enter them into the table (provided above). (b) Draw the Activity-on-node (AON) including the Start & Finish diagram and use the expected activity durations to complete a forward and backward pass (show calculations for ES,EF,LS,LF), create a table and show your work. Maritime Shipbuilding is set to start building the first of six ships and to finish this ship within...

  • Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m...

    Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...

  • Job Saint has laid out the major steps and eight activities to complete the wing assembly...

    Job Saint has laid out the major steps and eight activities to complete the wing assembly for an experimental air craft. These activities have been labeled A to H in the following table, which also shows their estimated completion time (in weeks) and immediate predecessors.                                                 Activity   Immediate Predecessors        a              m             b                                                                 A                  ---------                         1              2              3                  B                   --------                         2              3              4                  C                     A                               4              5              6                   D                    B                               8              9             10                   E                    C                               ...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT