Pik-Fast, a chain of convenience stores, is planning to open a new store. The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below.
Activity | Description | Immediate Predecessors | Optimistic Time (days) | Most Likely Time (days) | Pessimistic Time (days) | TE | ES | EF | LF | LS | Slack | Standard Dev | Variance |
A | Select manager | -- | 10 | 12 | 20 | 13 | 0 | 1.67 | |||||
B | Select site | -- | 8 | 15 | 22 | 15 | 0 | 2.33 | |||||
C | Hire workers | A | 17 | 21 | 31 | 22 | 0 | 2.33 | |||||
D | Basic training | C | 3 | 4 | 5 | 4 | 0 | 0.33 | |||||
E | Secure permits | B | 12 | 18 | 30 | 19 | 0 | 3.00 | |||||
F | Construct building | E | 26 | 30 | 40 | 31 | 0 | 2.33 | |||||
G | Purchase equipment | -- | 30 | 45 | 60 | 45 | 0 | 5.00 | |||||
H | Install equipment | F,G | 4 | 6 | 8 | 6 | 0 | 0.67 | |||||
I | Advertise opening | B | 15 | 55 | 89 | 54 | 0 | 12.33 | |||||
J | Final training | D,H | 2 | 3 | 4 | 3 | 0 | 0.33 | |||||
K | Stock store | H,I | 4 | 6 | 8 | 6 | 0 | 0.67 | |||||
L | Open store | J,K | 1 | 1 | 1 | 1 | 0 | 0.00 |
b) Identify the critical path and projected project completion time using the expected completion times.
c) Calculate the expected slack times for any two paths not including the critical path. For the path slack time, compute this compared to the critical path and that also considers the slack time for each activity on that path.
d) Find the probability that the critical path will be completed within 80 working days.
e) Illustrate or explain why the probability that the critical path will be finished in 80 days or less is not necessarily the probability that the project will be finished in 80 days or less. Assume that times for each activity will not change from what is provided below and no new activities are added nor are the predecessor relationships changed.
b)
Critical path is the longest path. It can be identified in the following table. All the activities having Slack time of 0 constitute the critical path.
So, critical path is: B-E-F-H-K-L
Expected completion time = LF time of the last activity of critical path = 78 days
c)
The expected slack times are shown in the right-most last column of the above table
d)
Expected time of critical path = 78 days
Variance of time of critical path = 5.44+9+5.44+0.44+0.44+0 = 20.78
Standard deviation of time of critical path = sqrt(20.78) = 4.56
Expected time of z value = (80-78)/4.56 = 0.4388
F(z) = NORMSDIST(0.4388) = 0.6696
Probability of completion of critical path within 80 working days = 0.6696 ~ 67 %
e) Probability of that the critical path will be finished within 80 days is 0.6696, whereas probability that all the paths will be finished within 80 days is 0.5796. Both are different.
Pik-Fast, a chain of convenience stores, is planning to open a new store. The activities required, their...
Pik-Fast, a chain of convenience stores, is planning to open a new store. The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...
1. Sid Orland is involved in planning a scientific research project. The activities are displayed in the following diagram. Optimistic, most likely, and pessimistic time estimates are displayed in the following table. Figure for Problem 1. r e 14 16 E 4 H 4 7 11 7 11 16 20 G 5 0 33 611 16 11 16 D 3 Most Likely Pessimistic Activity Optimistic 4 4 (a) Determine the expected times and variances for each activity along the critical...
Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...
The estimated times and immediate predecessors for the activities in a project at Caesar Douglas’s screening company are given in the following table. Assume that the activity times are independent. All times are in weeks. Activity Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) A -- 9 10 11 B -- 4 10 16 C A 9 10 11 D B 5 8 11 What is the critical path based on expected times? You may use any...
2. You are in charge of planning and coordinating next fall's sales management training program ur company. You have never done this before, but you decided to use the lessons from for yo your BUS 190 class to develop a table of tasks to be done, their immediate predecessors, and the most pessimistic, optimistic, and frequent times for each task. The table you developed is below: Task completion time estimate (weeks) Most Immediate Variance Task Predecessor Optimistic probable Pessimistic Mean...
HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects Howard Urinalarning company are given in the following assume that the activity times are independent Question Help Activity . Immediate Predecessor) А 8 Time (weeksi . Predecessors Activity b 8 10 С 7 19 13 4 10 18 D 6 10 14 This exercise contains only parts , bedande a) Based on the activity time estimate the expected times and variance for each of...
1. A sporting goods store is planning to open an outlet in a college town. The activities consist of the hiring of the manager of the outlet and his/her employees. Also it is necessary to coordinate the renovation of a building that previously was a fast food restaurant. To schedule this project using PERT, the following time estimates (in weeks) are gathered: What is the critical path and expected completion time for this project? (15 pts) Which activity has the...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning Company are given in the following table. Assume that the activity times are independent. Activity Immediate Predecessor a (time weeks) m (time weeks) b (time weeks) A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 Calculate the expected time (mean) and variance for each activity, then answer the following: a. What is the...
please help!! The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assu that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity a bPredecessor(s)Activitya bPredecessor(s) 12 10 12 8 17 This exercise contains only parts a, b, c, d, and e a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response...