Question

Job Saint has laid out the major steps and eight activities to complete the wing assembly...

Job Saint has laid out the major steps and eight activities to complete the wing assembly for an experimental air craft. These activities have been labeled A to H in the following table, which also shows their estimated completion time (in weeks) and immediate predecessors.

                       

                        Activity   Immediate Predecessors        a              m             b                                                   

             A                  ---------                         1              2              3

                 B                   --------                         2              3              4

                 C                     A                               4              5              6

                  D                    B                               8              9             10

                  E                    C                                2              5             8

                  F                     C, G                          4              5              6

                  G                   D, E                            1              2             3

(a) Determine expected time and the variance for all the activities.

(b) Determine the earliest start and finish, latest start and finish time and also find slack time for each activities and the project completion time.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Immdiate Pxdecesser.s rm 2 2. C, G, D E EExpected ime

Add a comment
Know the answer?
Add Answer to:
Job Saint has laid out the major steps and eight activities to complete the wing assembly...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and...

    Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity...

    also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...

  • Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b....

    Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b. A-B-C-F C. A-B-E-F Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) c. Which of these activities should the project manager track most closely? A. A-B-E-F b. A-D-E-F c. A-B-C-F Problem 15.6 Task Duration Estimate (in Days) Immediate Predecessors None А B A B and D E and C Earliest...

  • The table below defines the activities and the normal time duration for each activities within a...

    The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project. Table 1: The time-cost information for the activities Activity Normal Completion Time (weeks) Immediate Predecessor Crash Time (weeks) Normal cost for activities Crash cost for activities/week A 2 - 1 1200 400 B 3 - 1 1400 500 C...

  • Problem 5: For the given activity network, if there are 35 days required to complete the...

    Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...

  • A small software development project has eight major activities. The times are estimated and prov...

    A small software development project has eight major activities. The times are estimated and provided in the table below: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 5 -- B 5 7 9 -- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6 10 F Answer the following questions based on above table 1-2...

  • Question 8-10, CHAPTER 18: A home-remodeling project consists of eight activities. The immediate predecessors and activity...

    Question 8-10, CHAPTER 18: A home-remodeling project consists of eight activities. The immediate predecessors and activity times in weeks are shown below. Activity Predecessor(s) Normal Time Crash Time Normal Cost $400 Crash Cost $700 1600 2000 800 1100 1000 NNW 600 1200 1450 800 800 500 650 400 600 900 1300 F G H1 1000 650 8. Draw the network for this project. (10 points) 9. Please indicate the Earliest Start, Earliest Finish, Latest Start, and Latest Finish on the...

  • Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Pred...

    Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Predecessor ACTIVITY TIME EARLIEST START EARLIEST FINISH LATEST START LATEST FINISH SLACK A None 2 0 0 2 0 B A 1 2 3 3 4 1 C A 3 2 5 2 5 0 D B 7 3 10 4 11 E B, C 3 5 8 11 F C 5 11 5 11 0 G D ,E, F 4...

  • 6. Draw the network corresponding to the following information. Also, complete the table, identify the critical...

    6. Draw the network corresponding to the following information. Also, complete the table, identify the critical path, and specify project completion time. (Show calculations) (4 Points) Immediate ActivityPredecessor(s) (Weeks) Time 4 C, D D, E G, F EarliestEarlest Latest Latest ActivityStart Finish Start Finish Slack

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT