The AON diagram is:
The calculations are:
Data | Normal time | 26 | Minimum crash cost to meet project goal | $ 1,700 | ||||||||
Project goal | 20 | Minimum time | 17 | Project time | 20 | |||||||
Immediate Predecessors (1 per column) | Intermediate Computations | |||||||||||
Activity | Normal Time (weeks) | Crash Time (weeks) | Normal Cost | Total Cost with Crashing | Pred 1 | Pred 2 | Pred 3 | Pred 4 | Crash days | Crash cost/day | Crash limit | |
A | 10 | 9 | $6,000 | $8,000 | 0 | 2000 | 1 | |||||
B | 8 | 5 | $1,100 | $2,000 | 0 | 300 | 3 | |||||
C | 7 | 5 | $3,000 | $3,800 | A | 0 | 400 | 2 | ||||
D | 12 | 4 | $4,000 | $6,000 | B | 6 | 250 | 8 | ||||
E | 4 | 2 | $5,000 | $6,500 | B | 0 | 750 | 2 | ||||
F | 6 | 3 | $2,500 | $4,000 | A | D | 0 | 500 | 3 | |||
G | 5 | 3 | $2,800 | $3,000 | C | E | 2 | 100 | 2 |
6. A project has been defined to contain the following list of activities, along with their...
1) Based on the given information regarding the activities for the project, the project length= ___ weeks. 2) The total cost required for completing this project on normal time= $____ 3) For reducing the duration of the project by one week, the activity that should be crashed first is activity ___. 4) The cost of the project based on the first activity selected for crashing will increase by $___. 5) The maximum weeks by which the project can be reduced...
The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 3 2 B с D E F 4 A B B с DE E 1 3 G 2 Determine the amount of slack time for Activity E Ola. O weeks b. 1 week c. 2 weeks d. 3 weeks
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...
Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...
I just need the last two parts of the question answered. PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) $1,050 $2,000 $2,560 $2,600 $1,300 $2,600 $2,200 $1,800 $2,400 4 $4,200 $5,540 $2,050 4...
QUESTION 9 Consider the following project; for which activities is it possible that the slack can be greater than zero? Activity Immediate Predecessors B, E a. Only activities B or E could have slack, but they could not both have slack. Ob. Only activities B or C could have slack, but they could not both have slack. Oc. It is possible for any or all activities in this project to have slack. Od. It is possible for either all three...
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) Activity A (start) Precedes B, C Crash Cost/Week $400 $100 $200 $300 $400 F F (end) 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to...
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? A)By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) B) The total cost of crashing the project by 4 days is $. (Enter your response as a whole number.) Normal Crash Time Normal Total Cost Activity Time (days) (days)...
Question 16 4 points Save Answe The following provides information about a project, including a list of activities and precedence relationships, activity durations (normal and "crash" times), direct activity costs (normal and "crash"), indirect costs for the project, as well as calculated crash costs/day and the maximum amount that each activity can be shortened (crashed) by. There are no penalty costs for this project. Total project cost (using normal times), a network diagram, and the four paths and durations have...