Slack time for Activity E = 1 week
The following table provides a list of activities in a project, along with their respective durations...
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...
Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...
6. A project has been defined to contain the following list of activities, along with their precedence relations and time and cost estimates for the activity durations. Time estimates (weeks L Cost estimates ($) Activity Predecessor(s) Normal time Crashed time Normal cost Crashed cost 10 9 $6000 $8000 - 85 $1100 $2000 A 7 5 $3000 $3800 B 12 4 $4000 $6000 B 4 2 $5000 $6500 AD 6 3 $2500 $4000 CE $2800 $$3000 a. Draw the Activity-on-node (AON)...
QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...
5. (4 points) The Figure shows the project network with normal durations of the activities (in weeks). The following table shows the normal durations, shortest possible durations, achieved at extra cost, & the acceleration cost per time unit. Activity Immediate predecessor(s) Normal duration Shortest possible duration Unit cost of acceleration ($ in Thousands) 40 C 5 4 50 80 DA 5 1 50 (6,5, 40) (5, 4, 50) Start End D (5, 1, 50) (4, 3, 80) Develop all possible...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity A (start) B с E F(end) Duration (weeks) 3 8 3 4 Precedes B, C F E F 2 This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-F c) The total project completion time for Rafay Ishfaq's software firm is 13 weeks. (Enter your...
The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project. Table 1: The time-cost information for the activities Activity Normal Completion Time (weeks) Immediate Predecessor Crash Time (weeks) Normal cost for activities Crash cost for activities/week A 2 - 1 1200 400 B 3 - 1 1400 500 C...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration(Weeks) Activity Precedes 3 A(start) В.С В 2 5 C F E 2 F F(end) b- The activites on the critical path are: A C- F c- The total project completion time for Rafay Ishfaq's software firm is weeks. d- Determine the slack time for each of the activities. e- What is the total...
PLEASE ANSWER IN 30 MINUTES PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: Activity Duration (weeks) Immediate Predecessor(s) A 20 - B 12 - C 15 A D 5 B E 6 D F 14 A,E G 5 F H 3 C,G What is the duration of the project? weeks What is the latest start week for activity C? What is the slack time for...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity Duration (weeks) Precedes A (start) 2 B, C B 2 E C 6 F E 3 F F (end) 4 — This exercise contains only parts b, c, and d. b) Define the critical path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...