The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede:
Activity |
Duration (weeks) |
Precedes |
A (start) |
2 |
B, C |
B |
2 |
E |
C |
6 |
F |
E |
3 |
F |
F (end) |
4 |
— |
This exercise contains only parts b, c, and d.
b) Define the critical path, listing all critical activities in chronological order.
Critical path activities are the activities that lie on the longest time path (in terms of time). The critical path follows the activities with slack = 0.
For A -C- E - F, the length is ____ weeks. (Enter your response as a whole number.)
For A -B- F, the length is ____ weeks. (Enter your response as a whole number.)
The activities on the critical path are _____
c) What is the project duration (in weeks)?
The total project completion time corresponds to the longest path in the network, which is ___ weeks. (Enter your response as a whole number.)
Determine the slack time for each of the activities.
(Enter your responses as whole numbers.)
Activity |
Slack Time (weeks) |
A |
B |
C |
E |
F |
What is the total slack for the non critical path(s) in the project?
There is only one noncritical path through the network. Thus, the slack (in weeks) associated with any and all noncritical paths through the project is
1111minus−1010equals=nothing
week(s)
(Enter your response as a whole number.)
Network Diagram -
Possible Network Path and their Duration are -
ABEF --> 2+2+3+4 = 11 weeks
ACF --> 2+6+4 = 12 weeks
Critical path is the path with longest duration
Critical path = A-C-F
Project Duration = 12 weeks
Earliest Start (ES) = the earliest time when the activity can begin
Earliest Finish (EF) = ES + Activity Duration
Latest Finish (LF) = the latest time by whenthe activity can be finished without changing the project completion duration
Latest Start (LS) = LF - Activity Duration
Slack = LS-ES = LF-EF
Computing using the above gives us the below -
Activity | Precedes | Duration | ES | EF | LS | LF | Slack |
A | B, C | 2 | 0 | 2 | 0 | 2 | 0 |
B | E | 2 | 2 | 4 | 3 | 5 | 1 |
C | F | 6 | 2 | 8 | 2 | 8 | 0 |
E | F | 3 | 4 | 7 | 5 | 8 | 1 |
F | - | 4 | 8 | 12 | 8 | 12 | 0 |
Total slack for non critical activities = 1 + 1 = 2 weeks
The following is a table of activities associated with a project at Rafay Ishfaq's software firm...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity A (start) B с E F(end) Duration (weeks) 3 8 3 4 Precedes B, C F E F 2 This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-F c) The total project completion time for Rafay Ishfaq's software firm is 13 weeks. (Enter your...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what adivities each must precede Activity Duration (weeks) Precedes A (start) Fendi This exercise contains only parts and d. b) The activities on the critical path are c) The total project completion time for Rafay Ishlad's software firm is weeks. (Enter your response as a whole number) d) Determine the slack time for each of the activities. (Enter your...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration(Weeks) Activity Precedes 3 A(start) В.С В 2 5 C F E 2 F F(end) b- The activites on the critical path are: A C- F c- The total project completion time for Rafay Ishfaq's software firm is weeks. d- Determine the slack time for each of the activities. e- What is the total...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) Activity A (start) Precedes B, C Crash Cost/Week $400 $100 $200 $300 $400 F F (end) 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity Duration (weeks) Precedes Crash Cost/Week A (start) 2 B, C $ 370 B 2 E $ 130 C 4 F $ 200 E 1 F $ 150 F (end) 2 — $ 420 Suppose that Rafay is only given 5 weeks (instead of 8) to...
Suppose that Rafay is only given 7 weeks (instead of 10) to complete the project . By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity Each Activity Should be Reduced BY (weeks) A (weeks)- ? B (weeks)- ? C (weeks)- ? D (weeks)- ? E (weeks)- ? F (weeks)- ? What is the total crashing cost ? The following is a...
The following activities of a hospital expansion project has been identified in the following table. First, all activities of the project are listed. Next, the immediate predecessor(s) of each activity is identified (activity relationships). Please plot the activity network diagram and answer the following questions. Hospital Expansion Project Activity Description Immediate predecessor(s) Activity Time (Weeks) A Select administrative and medical staff - 12 B Select site and do site survey - 9 C Select equipment A 10 D Prepare final...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 6 6 N/A B none 5 2 $500 C A 3 2 $1000 D A, B 4 2 $2000 E C, D 5 2 $1250 F D 6 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
A project manager discovers that his team has neglected to complete the network diagram for the project. the network diagram is shown below. however the project manager has some information available, specifically that each activity a-g, has a different duration between one and seven weeks. also the slack time for each of the activity is known as shown belowDuration (weeks): 1,2,3,4,5,6,7 Slack time (weeks): 0,0,0,1,1,3,7 A D E G B FINISH START C F Using the clues provided below, determine...
QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...