Question

The following info is available for drawing a PERT network using AOA. *(More than one answer...

The following info is available for drawing a PERT network using AOA.

*(More than one answer may be selected)*

Activity

Immediate Predecessors

Activity Duration (days)

A

--

10

B

--

13

C

A

12

D

B

15

E

A

13

F

C

16

G

D,E

10

H

G,F

5

a.

the critical path includes: B, D, G, and H.

b.

the slack on activity G is not 11 days.

c.

there is one critical path.

d.

the total duration to complete the project is 40 days.

e.

the critical path includes: A, C, F, and H.

f.

the slack on activity D is 5 days.

g.

the slack on activity H is less than 1 day.

h.

the slack on activity C is not 5 days.

i.

the slack on activity E is more than 5 day.

j.

the total duration to complete the project is more than 40 days.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

from the given data, the network diagram becomes :- ACM) (12) (13 F(16) OH(3) to ulios BIB) O AEGH - 38 Path Time 0 AlfH 43 –

Add a comment
Know the answer?
Add Answer to:
The following info is available for drawing a PERT network using AOA. *(More than one answer...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Use a PERT network to establish the expected duration for the project described in the table...

    Use a PERT network to establish the expected duration for the project described in the table below:    (SHOW the PERT NETWORK) Activity Predecessors Duration a        m       b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400         600 D B, C 4 6 8 200                             600 E B, C 6 9 12 400 300 F C 4 6 14...

  • Problem 5: For the given activity network, if there are 35 days required to complete the...

    Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...

  • Reliable Garage is completing production of the J2000 kit car. The following data are available for...

    Reliable Garage is completing production of the J2000 kit car. The following data are available for the​ project:                                                                                      Activity Activity Time ​(day​s) Immediate​ Predecessor(s) A 3 − B 4 A C 5 B D 7 C E 6 C F 2 C G 4 F H 4 ​D, E, G Determine the​ project's critical path and duration. The critical path is A-B-C-D-H and the project duration is 23 day​(s). ​(Enter your response as a whole​ number.) c. What is...

  • For the activities given in the table: Draw the AOA network diagram Find the critical activities...

    For the activities given in the table: Draw the AOA network diagram Find the critical activities Find the critical path Find the project completion time Time (days) Predecessors Activity Description Initial Paperwork A 3 Build Body B A 3 C Build Frame A 2 Finish Body 3 D E Finish Frame C Final Paperwork B,C 3 G Mount Body to Frame D,E 6 Install Skirt on Frame C 2 H A FLO For the activities given in the table: Draw...

  • B. Determine the project’s critical path and duration.(this is number b wuestion) please answer t...

    b. Determine the project’s critical path and duration.(this is number b wuestion) please answer this two b and c questions Reliable Garage is completing production of the J2000 kit car. The following data are available for the project Activity Activity Time (days) Immediate Predecessor(s 10 D, E,G A-B-C-D-H 4 4 A-B-C-F-G-H b. Determine the pr A-B-C-E-H The critical path isand the project duration is I duration. day(s). (Enter your response as a whole number.) c. Calculate the slack for each...

  • Q1. a) Draw a project network using (AOA) method, b) and calculate (EST, EFT, LFT, LST)...

    Q1. a) Draw a project network using (AOA) method, b) and calculate (EST, EFT, LFT, LST) for each activity, c) and define the critical path. Activity Symbol A B C Predecessor Activity D E F G Duration (Weeks) Nil Nil Nil 5 9 4 B 7 AC C 8 7 D F

  • Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A...

    Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 10 B - 12 C A 4 D A, B 8 E A, B 9 F C 10 G D, F 12 H E, G 15 Answer the following: What is the critical path? How long will it take to complete this project? Can activity E be delayed without delaying the completion of the project? If so, how many days?

  • A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity...

    A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity Duration Time (In DAYS ) Early Start (ES) (In DAYS ) Early Finish (EF) (In DAYS ) Late Start (LS) (In DAYS ) Late Finish (LF) (In DAYS ) SLACK (In DAYS ) A - 14 B - 13 C A 11 D A 15 E B 14 F B 11 G D, E 13 H F 15 J C 12 K G,H 11...

  • Network Diagrams & PERT Question: We are remodeling the da Vinci Lounge in the Spencer Engineering...

    Network Diagrams & PERT Question: We are remodeling the da Vinci Lounge in the Spencer Engineering Building. A. Identify the critical path B. Identify the slack for each element C. Identify the most and least sensitive element D. Identify the predicted project duration (TE) E. Z is the number of standard deviations from the mean found in the statistical table below, and defined by the relationship: Z = (Ts - TE) / SQRT(Σσte2 ) where only critical path σte are...

  • MANG471-002-24185 Operations Management Homework: Chapter 7 Score: 0.89 of 1 pt 2 of 5 (5 complete)...

    MANG471-002-24185 Operations Management Homework: Chapter 7 Score: 0.89 of 1 pt 2 of 5 (5 complete) % Problem 1 SA b. Calculate the critical path for this project. The critical path is A-C-F-H-J and the project duration is 26 days. (Enter your response as a whole number.) c. How much slack is in each of the activities G, H, and I? Activity Activity Time (days) On critical path? Slack (days) Enter your answer in the edit fields and then click...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT