Question

Network Diagrams & PERT Question:


We are remodeling the da Vinci Lounge in the Spencer Engineering Building.

A. Identify the critical path
B. Identify the slack for each element
C. Identify the most and least sensitive element
D. Identify the predicted project duration (TE)
E. Z is the number of standard deviations from the mean found in the statistical table below, and
defined by the relationship:
Z = (Ts - TE) / SQRT(Σσte2 ) where only critical path σte are included in the summation.
If the company’s scheduled time to complete the work (Ts) is 70 days, then what is the likelihood
that we finish the remodeling project on time? Express your probability response as a
percentage rounded to the nearest integer.

Variance Likely Worst Time est. (days) M B TE =(A+(4M)+B)/6 St. Dev Ote =(B-A)/6 Ote^2 4 6 Activity Preceding Best activity A

z Value Probability z Value Probability -2 0.02 2 0.98 -1.5 0.07 1.5 0.93 -1 0.16 1 0.84 -0.7 0.24 0.7 0.76 -0.5 0.31 0.5 0.6

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Task O M P Te Var^0.5 Variance
A 3 4 6 4.166667 0.5 0.25
B 4 6 11 6.5 1.166667 1.361111
C 12 15 30 17 3 9
D 12 15 20 15.33333 1.333333 1.777778
E 7 12 22 12.83333 2.5 6.25
F 2 17 19 14.83333 2.833333 8.027778
G 13 17 19 16.66667 1 1
H 5 10 15 10 1.666667 2.777778
I 11 13 20 13.83333 1.5 2.25
J 12 13 16 13.33333 0.666667 0.444444
K 8 12 22 13 2.333333 5.444444

11-819-%9 (6 9 4:16 (332 (เ“66 (0) 1965 17 137 38) (0) 17

Activity ES EF LS LF Slack
A 0 4.16 0.5 4.66 0.5
B 4.16 10.66 10.5 17 6.34
C 0 17 0 17 0
D 17 32.33 17 32.33 0
E 4.16 17 4.66 17.5 0.5
F 17 31.83 17.5 32.33 0.5
G 32.33 49 32.33 49 0
H 31.83 41.83 39 49 7.16
I 49 62.83 49 62.83 0
J 49 62.33 49.5 62.83 0.5
K 62.83 75.83 62.83 75.83 0

Critical path = CDGIK

Slack has been given in table

The tasks with highest SD ( or variance)  are most sensitive, i.e. C,F,E,K,H while tasks like H,I and D are less sensitive as they have low variance.

Ptoject duration is 75.83

Note: As per policies, I cana answer first 4 parts of a question, Inconvenience is regretted.

Add a comment
Know the answer?
Add Answer to:
Network Diagrams & PERT Question: We are remodeling the da Vinci Lounge in the Spencer Engineering...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • Given: In a network the critical path is determined by six activities B, D, F, K,...

    Given: In a network the critical path is determined by six activities B, D, F, K, S, and T. The standard deviation (0) values for each activity are given in the table below. B D F R S T Activit y σ 51 6 11 51 21 6 6 6 11 51 66 Req'd: If the early finish for the network is calculated to be 15 days, calculate the probability of completing the project in 12 days. Value (z) 1.0...

  • Use a PERT network to establish the expected duration for the project described in the table...

    Use a PERT network to establish the expected duration for the project described in the table below:    (SHOW the PERT NETWORK) Activity Predecessors Duration a        m       b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400         600 D B, C 4 6 8 200                             600 E B, C 6 9 12 400 300 F C 4 6 14...

  • 9. How many females represented in the Venn diagram below are right-handed? (1 poimt) 200 females...

    9. How many females represented in the Venn diagram below are right-handed? (1 poimt) 200 females ight-handed 103 32 wear glasses O 103 71 144 135 10. Two events, 4 and B, are disjoint. What is the probability that both A and B will occur at the same time? o 0.5 0 1 11. Which event below is independent of event A? (1 point) A: You get to work on time. O There are no accidents on the road It's...

  • Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic...

    Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic                         Time                Time                Time A                     7                      10                    12 B                     6                      8                      14 C                     5                      9                      12 D                     12                    14                    21 E                      10                    12                    15 F                      4                      5                      8 G                     1                      3                      8 H                     12                    15                    17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...

  • Lecture Exercise #12 Critical Path Method Determine the early start, early finish, late start, late finish...

    Lecture Exercise #12 Critical Path Method Determine the early start, early finish, late start, late finish times for each activity Identify the critical path . Activity А Time (days) 6 7 3 Predecessor(s) None None B с A 2 A E 4 B F 6 B 10 C. E D. F H 7 Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 2 1 А B None None None с 1 1 Cost Normal Crash 1000...

  • (7) The events A and B are mutually exclusive (disjoint). If P(A) = 0.7 and P(B)...

    (7) The events A and B are mutually exclusive (disjoint). If P(A) = 0.7 and P(B) = 0.2, what is P(A or B)? A) 0.14 B) 0 C) 0.9 D) 0.5 (8) The events A and B are mutually exclusive (disjoint). If P(A) = 0.2 and P(B) = 0.1, what is P(A and B)? A) 0.02 B) 0 C) 0.5 D) 0.3 (9) A probability experiment is conducted in which the sample space of the experiment is S = {1,...

  • CHAPTER 13 / Developing and implementing Effective Accounting Information Systems 431 14 FIGURE 13-11 PERT network...

    CHAPTER 13 / Developing and implementing Effective Accounting Information Systems 431 14 FIGURE 13-11 PERT network diagram for a systems implementation project. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 Activity Prepare the Physical site 3958 Determine functional changes Select and assign personnel Train personnel Acquire and install computer equipment Establish...

  • Question i: Calculate the dates PI and PT for each activity. Identify the Project Critical Path....

    Question i: Calculate the dates PI and PT for each activity. Identify the Project Critical Path. Is it posible to finish the Project in 42 weeks? [Explain your answer in slide 3] Question ii: Imagine that Activity A actually ends in 3 weeks, the B in 12 weeks and the C in 13 weeks. Recalcula la fecha de terminación del proyecto. In what activities would you focus on to readjust the Project so that it is completed in less than...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT