Question
Question i: Calculate the dates PI and PT for each activity. Identify the Project Critical Path. Is it posible to finish the Project in 42 weeks? [Explain your answer in slide 3]

Question ii: Imagine that Activity A actually ends in 3 weeks, the B in 12 weeks and the C in 13 weeks. Recalcula la fecha de terminación del proyecto. In what activities would you focus on to readjust the Project so that it is completed in less than 42 weeks?


3.1 Critical Path : Explain your answer
Question iii: Explain which are some of the benefits of the CPM method for Project management.

Key: Earliest Beggining G n E a 3.1 Slide: Critical Path Question i: Critical Path: [A>B>E>G>H] Question i: Calculate the dat
Key: Earliest Beggining 0 0 Earliest Terminatio 3.1 Slide: Critical Path Question ii: Termination: (41 weeks] Question ii: Im


Key: Earliest Beggining 0 G E arliest termination 3.1 Slide: Critical Path Question i: Critical Path: [A>B>E>G>H] Question i:
Key: Earliest Beggining 0 0 Earliest Terminatio 3.1 Slide: Critical Path Question ii: Termination: (41 weeks] Question ii: Im
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Question i) Explanation of critical path.

Critical path is the sum of all those activities that add up to the longest duration in a project. For a project to complete all its activities must be completed. The shortest time possible to complete the project will be the critical path. In this case the critical path identified is A>B>E>G>H, which takes a total duration of 41 weeks. All other paths of dependent activists are: A>D>G>H takes 34 weeks and path A>C>F>H takes 35 weeks.

Since the path A>B>E>G>H has the longest duration of 41 weeks when added up, it is the critical path. The project can be completed within 42 weeks.

Question ii) If the duration for activities A, B and C are altered, the project network will have the following paths with dependant activities:

A>B>E>G>H will take 39 weeks

A>D>G>H will take 35 weeks

A>C>F>H will take 41 weeks

Since path A>C>F>H has the longest duration of 41 weeks, it is critical path. Any extension of duration in these activities could delay the project and may miss the 42 weeks deadline. Activities that are not on this critical path (B, E, D and G) can however be adjusted for any lag/ float.

P.S: The Earliest termination for Activity F should be 36, not 38 as displayed in the network diagram.

Question iii) Some if the benefits of Critical Path Method in project management are:

  • CPM identifies the most important activities in a project that have dependencies.
  • Gives a graphical form and helps the project manager visualise the activities of the project.
  • Helps in identifying tasks that are nin-critical, wherein adjustments can be made without affecting the overall project completion date.
  • CPM is a controlling technique that can be used for monitoring the activities during the implementation phase of the project. Activities missing their deadline can be flagged and reported.
  • Project managers can determine the expected project completion dates and communicate the same with sponsors and other project stakeholders.
  • For projects with a hard deadline, the network diagram can be plotted backward using late start and late finish dates.
  • CPM can be used as an input for further project planning like resource allocation and budgeting.
Add a comment
Know the answer?
Add Answer to:
Question i: Calculate the dates PI and PT for each activity. Identify the Project Critical Path....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statisti...

    for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statistics 1. A project is shown by the following network. The durations of activities (in weeks) are indicated on the arrows. a. Identify all of the paths, compute the length of each, identify the critical path and the b. Determine...

  • D Question 6 5 pts Project B: What is/are the critical path(s) for this project? Activity...

    D Question 6 5 pts Project B: What is/are the critical path(s) for this project? Activity Immediate Predecessor Activity Duration 6 A,B D,E G,F BDFH BEGH and CGH BEFH BEGH

  • NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the...

    NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the total project duration. Feel free to verify your answer using MS Project or a similar tool. Activity Dependency Activity Duration (weeks) A B None None AB B F G H 8 9 DE F, G, HI 7 8 5 Draw the Network Diagram using the convention discussed in the class. (If challenged with drawing tools, you can hand draw, take a picture, and paste...

  • Mauritius Pharmaceuticals Ltd was undertaking a project for reviewing the packaging of its saline drips. The...

    Mauritius Pharmaceuticals Ltd was undertaking a project for reviewing the packaging of its saline drips. The activities and the duration of each activity are shown in the table below. Activity Completion time (weeks) ACTIVITY Completion time (weeks) A 6 B 9 C 8 D 5 E 10 F 6 G 14 H 11 I 9 The immediate precedence relationships are:  Activities D and E follow activity B.  Activities A and D follow activity C.  Activities G and...

  • 11. In CPM/PERT, an activity that is on the critical path A. has equal values for...

    11. In CPM/PERT, an activity that is on the critical path A. has equal values for "Latest Start" and "Earliest Start" ( LS = ES ) B. has equal values for "Latest Finish" and "Earliest Finish" ( LF = EF ) C. is used in calculating total project duration D. has slack equal to zero E. all of the above 12. In CPM/PERT, the critical path through the network A. will require the most time of any path B. will...

  • Activity on arrow construction

    QUESTION 1 The following table provides information about a particular project:ActivityDuration (Days)PrecedingActivityA5_B6_C4AD3AE1AF4EG14D,EH12B,CI2G,H (a)   Represent the project by means of a simple network diagram.        (b)   Prepare in tabular form, an activity schedule showing the following details: Earliest-start, earliest-finish, latest-start, latest-finish and slack times.         (c)   Identify the critical path.                                                               ...

  • Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity...

    Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. Calculate the slack for each activity. Identify all activities on the Critical Path. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score). Activity A 8 с D E...

  • B. Determine the project’s critical path and duration.(this is number b wuestion) please answer t...

    b. Determine the project’s critical path and duration.(this is number b wuestion) please answer this two b and c questions Reliable Garage is completing production of the J2000 kit car. The following data are available for the project Activity Activity Time (days) Immediate Predecessor(s 10 D, E,G A-B-C-D-H 4 4 A-B-C-F-G-H b. Determine the pr A-B-C-E-H The critical path isand the project duration is I duration. day(s). (Enter your response as a whole number.) c. Calculate the slack for each...

  • QUESTION 17 The critical path of the projected below as been determine what they Activity Time...

    QUESTION 17 The critical path of the projected below as been determine what they Activity Time Immediate Predecessor A 7 8 C 2 A D A E F 5 G CE 8 D. QUESTION 17 A B The critical path of the project outlined below has been mined of B-F-H. What is the slack time for activity F? Time Immediate Activity (wks) Predecessor(s) 7 8 с 2 А A E B F G 9 CE H 8 DF D 2...

  • Activity Duration Precedence Problem# 3 For the project information given below (wecks) information a) Draw the...

    Activity Duration Precedence Problem# 3 For the project information given below (wecks) information a) Draw the network diagram to accurately B must be after C represent the information given C must be after A 10 15 b) Determine the earliest start, earliest D must be after B E must be after C F must be after D and E G must be after F H must be after G 1 must be after F finished, latest start, latest finish for...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT