From given data of activity and its duration, AOA (Activity On Aerrow) network is drawn as shown below.
EFT = EST + Duration
LST = LFT - Duration
Total Float= LFT - EFT
Activity | Duration | EST | EFT | LST | LFT | Total Float | Comment |
A | 5 | 0 | 5 | 8 | 13 | 8 | |
B | 9 | 0 | 9 | 0 | 9 | 0 | Critical |
C | 4 | 0 | 4 | 5 | 9 | 5 | |
D | 7 | 9 | 16 | 9 | 16 | 0 | Critical |
E | 8 | 5 | 13 | 13 | 21 | 8 | |
F | 7 | 4 | 11 | 9 | 16 | 5 | |
G | 5 | 16 | 21 | 16 | 21 | 0 | Critical |
here in activity B, D and G total float is zero thus these are critical activities.
Critical path is B-D-G and the critical duration of the project is 9+7+5= 21 days.
Q1. a) Draw a project network using (AOA) method, b) and calculate (EST, EFT, LFT, LST)...
3. Draw a project network for this project. Calculate EST,EFT,LFT,LST Activity A:train workers B:purchase raw materials C:produce product 1 D:produce product 2 E:test product 2 PredecessorsDuration (days) ty A, B 8 A, B 10 C, E 12
1. Given the major activities and their duration for a building project as follows: Activity DurationSuccessors B,C D,E,F HI,J K,L L,M K,L 10 4 (a) Draw the precedence network. (b) Calculate the EST, EFT, LST and LFT of each activity using the forward pass and backward pass methods entire project about a delay of the activity D by 3 days? (Remark: please redraw the diagram to verify (c) Highlight/identify the critical path in the precedence network and find the duration...
For each of the following predecessor tables (Tables A-C): 1. 2. 3. 4. 5. Draw a corresponding AON network. Compute EST and EFT for each activity and complete the table. Compute LST and LFT for each activity and complete the table. Find and mark the critical path. Determine the total float and free float and complete the table. Table B Activity Duration Preceding Activity ES EF LSLF TF FF 0 60600 4 A, B 10 D, E C,F.G C, G...
Question 92 In CPM, the duration of the project o a. is determined by managers o b.is determined by a supervising government agency oc. is equal to the duration of the critical path o d. is determined by investors Question 90 Slack for activity I is computed as oa. EST; - LST; o b. EFT; - LFT; oc. LFT; - EST; od. LST; - EST; Question 88 A project plan is established o a. before project activities begin o b....
Module 5 Assisted Problems M5_A1. A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table IMMEDIATE TIME ACTIVITY ACTIVITY DESCRIPTION (WEEKS) PREDECESSORS A Excavate 2 Erect building Install generator A 6 C A 4 Install tank A 2 Install maintenance equipment B 4 E Connect generator and tank to building Paint finish В, С, D P 5 3 Check...
NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the total project duration. Feel free to verify your answer using MS Project or a similar tool. Activity Dependency Activity Duration (weeks) A B None None AB B F G H 8 9 DE F, G, HI 7 8 5 Draw the Network Diagram using the convention discussed in the class. (If challenged with drawing tools, you can hand draw, take a picture, and paste...
The following info is available for drawing a PERT network using AOA. *(More than one answer may be selected)* Activity Immediate Predecessors Activity Duration (days) A -- 10 B -- 13 C A 12 D B 15 E A 13 F C 16 G D,E 10 H G,F 5 a. the critical path includes: B, D, G, and H. b. the slack on activity G is not 11 days. c. there is one critical path. d. the total duration to...
Draw an activity on the arrow network for the activities of a project as shown in table, indicate the critical path and calculate the total float Activity description immediate predecessor Expected time (Weeks) A - 5 B - 4 C A 7 D B 7 E B 8 F B 5 G C,D 8 H E,I 11 I F 2 J F 12 K H,I 11 2.convert the above into activity on the node
Draw the AON and AOA network for a given problem. Activity Predecessor B B C DE DE F, G, H
For the activities given in the table: Draw the AOA network diagram Find the critical activities Find the critical path Find the project completion time Time (days) Predecessors Activity Description Initial Paperwork A 3 Build Body B A 3 C Build Frame A 2 Finish Body 3 D E Finish Frame C Final Paperwork B,C 3 G Mount Body to Frame D,E 6 Install Skirt on Frame C 2 H A FLO For the activities given in the table: Draw...