Question

Q1. a) Draw a project network using (AOA) method, b) and calculate (EST, EFT, LFT, LST) for each activity, c) and define the
0 0
Add a comment Improve this question Transcribed image text
Answer #1

From given data of activity and its duration, AOA (Activity On Aerrow) network is drawn as shown below.

m A/co 0 G A → 3 5 5

EFT = EST + Duration

LST = LFT - Duration

Total Float= LFT - EFT

Activity Duration EST EFT LST LFT Total Float Comment
A 5 0 5 8 13 8
B 9 0 9 0 9 0 Critical
C 4 0 4 5 9 5
D 7 9 16 9 16 0 Critical
E 8 5 13 13 21 8
F 7 4 11 9 16 5
G 5 16 21 16 21 0 Critical

here in activity B, D and G total float is zero thus these are critical activities.

Critical path is B-D-G and the critical duration of the project is 9+7+5= 21 days.

Add a comment
Know the answer?
Add Answer to:
Q1. a) Draw a project network using (AOA) method, b) and calculate (EST, EFT, LFT, LST)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT