1. Given the major activities and their duration for a building project as follows: Activity DurationSuccessors...
Question 92 In CPM, the duration of the project o a. is determined by managers o b.is determined by a supervising government agency oc. is equal to the duration of the critical path o d. is determined by investors Question 90 Slack for activity I is computed as oa. EST; - LST; o b. EFT; - LFT; oc. LFT; - EST; od. LST; - EST; Question 88 A project plan is established o a. before project activities begin o b....
3. Draw a project network for this project. Calculate EST,EFT,LFT,LST Activity A:train workers B:purchase raw materials C:produce product 1 D:produce product 2 E:test product 2 PredecessorsDuration (days) ty A, B 8 A, B 10 C, E 12
Q1. a) Draw a project network using (AOA) method, b) and calculate (EST, EFT, LFT, LST) for each activity, c) and define the critical path. Activity Symbol A B C Predecessor Activity D E F G Duration (Weeks) Nil Nil Nil 5 9 4 B 7 AC C 8 7 D F
For each of the following predecessor tables (Tables A-C): 1. 2. 3. 4. 5. Draw a corresponding AON network. Compute EST and EFT for each activity and complete the table. Compute LST and LFT for each activity and complete the table. Find and mark the critical path. Determine the total float and free float and complete the table. Table B Activity Duration Preceding Activity ES EF LSLF TF FF 0 60600 4 A, B 10 D, E C,F.G C, G...
Module 5 Assisted Problems M5_A1. A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table IMMEDIATE TIME ACTIVITY ACTIVITY DESCRIPTION (WEEKS) PREDECESSORS A Excavate 2 Erect building Install generator A 6 C A 4 Install tank A 2 Install maintenance equipment B 4 E Connect generator and tank to building Paint finish В, С, D P 5 3 Check...
Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...
The following table illustrates the activities of a small project Duration Days) Activity Depends orn 7 7 9 2 419 A a. Calculate the mean Project duration; b. Write and Highlight the Critical Path; c. Find the probability to finish this project at 15 days; d. Find the probability to finish this project at 19 days; e. Find the project duration that satisfies probability equal to 8 %; f. Find the project duration that satisfies probability equal to 92 %.
Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as shown in the following table. Draw the project network diagram, find the critical path and calculate the corresponding project completion time. Also, find the total float as well as the free float for each activity and the non- critical activities. (10 Marks) ТРА Duration (Weeks) Activity A B نما 4 с 14 D A 10 E F A BD BD с F.H 5 4...
A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity Duration Time (In DAYS ) Early Start (ES) (In DAYS ) Early Finish (EF) (In DAYS ) Late Start (LS) (In DAYS ) Late Finish (LF) (In DAYS ) SLACK (In DAYS ) A - 14 B - 13 C A 11 D A 15 E B 14 F B 11 G D, E 13 H F 15 J C 12 K G,H 11...
Construct an Activity-on-branch network from the precedence relationships of activities shown Activity Predecessors Duration 6 7 A A A B с D E F 1 14 5 8 9 3 5 3 B C D C, D D H F E, J F GI G, I L, N H I J K L M 12 6