Question 92 In CPM, the duration of the project o a. is determined by managers o b.is determined by a supervising governmentQuestion 90 Slack for activity I is computed as oa. EST; - LST; o b. EFT; - LFT; oc. LFT; - EST; od. LST; - EST;Question 88 A project plan is established o a. before project activities begin o b. before project activities begin and is mo

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Q.92

c)In CPM, the duration of the project is equal to the duration of the critical path.

CPM consist of an algorithm for scheduling a set of project activities.it predicts the time required to complete the project. The critical path is the longest period path through the network diagram.

Q.90

a) Slack for the activity I is computed as ESTi - LSTi

Slack time for an activity is the time between the earliest and latest start time or earliest and latest finish time.it is the amount of time a task can be delayed without affecting the deadlines.

Q.88

b)a project plan is established before project activities begin and is modified as time goes on and conditions change

The project plan is an important aspect of the project life cycle.project plan helps to manage time, quality, changes etc.project plan is not created all at once.it is progressively elaborated.

Add a comment
Know the answer?
Add Answer to:
Question 92 In CPM, the duration of the project o a. is determined by managers o...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Given the major activities and their duration for a building project as follows: Activity DurationSuccessors...

    1. Given the major activities and their duration for a building project as follows: Activity DurationSuccessors B,C D,E,F HI,J K,L L,M K,L 10 4 (a) Draw the precedence network. (b) Calculate the EST, EFT, LST and LFT of each activity using the forward pass and backward pass methods entire project about a delay of the activity D by 3 days? (Remark: please redraw the diagram to verify (c) Highlight/identify the critical path in the precedence network and find the duration...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Immediate Predecessor Activity A B С D E...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Activity A B C D E F G...

  • Question 1 3 pts Winston Corporation is evaluating a new project that will require an increase...

    Question 1 3 pts Winston Corporation is evaluating a new project that will require an increase in accounts receivable of $80,000, an increase in inventory of $250,000, and an increase in accounts payable of $160,000. The change in networking capital for this project will be: $330,000 $170,000 +$170,000 -$490,000 MACRS Depreciation Allowances Property Class Year 3-Year 5-Year 7-Year 33.33% 20.00% 14.29% 44.45 32.00 24.49 14.81 19.20 17.49 11.52 12.49 11.52 8.93 5.76 8.92 7.41 8.93 4.46 Question 2 3 pts...

  • Hi, Kindly assist with my project management assignment below using the attached case study Question 1 Update the project charter for the remainder of the project in response to Adams’ memo (lines 241...

    Hi, Kindly assist with my project management assignment below using the attached case study Question 1 Update the project charter for the remainder of the project in response to Adams’ memo (lines 241 through 246). Question 2 Prepare a plan for the remainder of the project in response to Adams’ memo (lines 241 through 246). Your answers to the above will be assessed in terms of the level of communication displayed, the insights and inferences drawn, and your ability to...

  • Show instructions Questions 1-60 of 60 | Page 1 of 1 Question 1 Which statement by...

    Show instructions Questions 1-60 of 60 | Page 1 of 1 Question 1 Which statement by a patient receiving high-dose melphalan indicates an understanding of the teaching O a "Blood counts are not routinely monitored during therapy. 9 b "tis important to take the tablet with food. Owill put honey in my tea daily. O d will suck on ice chips while the drug is being administered Question2 Prior to beginning treatment with daunorubicin, the patient should inform the nurse...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

  • there are 5 pictures attached to this question. The first picture which talk about P-R-O strategy...

    there are 5 pictures attached to this question. The first picture which talk about P-R-O strategy is the question itslef which I want to know thw aswer. the next 4 pictures are useful information that may help you to get the answer. please answer to this question. I need to know ASAP Increase in hominin brain size Task: Use the P-R-O strategy to construct a theory-based explanation for a puzzling problem. Refer to the handout you received in lecture to...

  • Refer to the following financial statements and answer the following questions hints:- 13. cash provided (used)...

    Refer to the following financial statements and answer the following questions hints:- 13. cash provided (used) by operating activities, investing activities, and financing activities. 14. cash-based net income. 15. estimate of uncollectible accounts receivable. 16. calculate and interpret accounts receivable ratio (most recent and prior period). hints:- 2:12 PM Wed Apr 15 39%). A 51.04cdn.com PART II NIKE, Inc. Consolidated Statements of Income in mWors, except per share data) Revenues Cost of sales Gross profit Demand creation expense Operating overhead...

  • JOHNSON & JOHNSON AND SUBSIDIARIES CONSOLIDATED STATEMENTS OF EARNINGS (Dollars and Shares in Millions Except Per...

    JOHNSON & JOHNSON AND SUBSIDIARIES CONSOLIDATED STATEMENTS OF EARNINGS (Dollars and Shares in Millions Except Per Share Amounts) (Note 1)* 2016 71,890 21,789 50.101 20,067 9.143 29 Sales to customers Cost of products sold Gross profit Selling, marketing and administrative expenses Research and development expense In-process research and development Interest income Interest expense, net of portion capitalized (Note 4) Other (income) expense, net Restructuring (Note 22) Eamings before provision for taxes on income Provision for taxes on income (Note 8)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT