For the activities given in the table: Draw the AOA network diagram Find the critical activities...
Activity Duration (week) Predecessors C,E,D a) Draw AOA network diagram (grading will be done only for AOA, not AON] (12 pts) a) When will the project be available (completion of project)? (2 pts) b) What is the effect on the project if activity E takes an extra week? (3 pts)
Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...
The following info is available for drawing a PERT network using AOA. *(More than one answer may be selected)* Activity Immediate Predecessors Activity Duration (days) A -- 10 B -- 13 C A 12 D B 15 E A 13 F C 16 G D,E 10 H G,F 5 a. the critical path includes: B, D, G, and H. b. the slack on activity G is not 11 days. c. there is one critical path. d. the total duration to...
W4A2: Tasks: See above to view the network diagram. Using the diagram, find: -The critical path. -How long it will take to complete the project? -How does simulation determine the probabilities of various project completion times? -What is "slack" and why is it important? -Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? -How is the uncertainty in project scheduling dealt with? -Should the critical path activities be managed differently from noncritical path activities? Explain....
Must use AOA PERT/CPM Manual Calculations and show Networks. 10. A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table: Activity Activity Activity Activity Description Predecessor Time Excavate Erect building Install generator Install tank Install maintenance equipment Connect generator and tank to building b.c,d Paint finish Η Check out facility Construct the network for this project and calculate the...
Here is an Activity on Arrow (AOA) network diagram for a project. The lettered A through F represents an activity, as shown in the accompanying precedence diagram. The probabilistic time for each activity is as follows Activity Time Activity Time A 4-5-6 D 4-5-6 B 2-5-6 E 2-5-6 C 3-4-5 F 3-4-6 What is the expected time and standard deviation of path A-C-D? What percentage will path A-C-D finish within 13 weeks? Please type your answer and the steps of...
Given the following table, construct the network diagram, either AOA or AON. Times are in days a. Determine the expected duration of the project. b.Compute the probability that the project will take at least 18 days. Path Activity Time Estimates 4-5-6 7-8-10 3-6-9 7-8-10 2-3-4 1-4-6 Top Bottom E Path Activity Time Estimates 4-5-6 7-8-10 3-6-9 7-8-10 2-3-4 1-4-6 Top Bottom E
The critical path for the network activities shown below is __ with duration ___ Activity Duration Immediate Predecessors A 2 - B 4 - C 1 A,B D 6 A,B E 3 B,C,D
question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in hours) Predecesur Planning Find location determine resource requirements Purchasing Requisition of lumber and sand Excavation Planning Dig and grade Sawing Planning Saw lumber inte appropriate sizes Placement Purchasing Position lumber in comect locations Sawing. c om Assembly Nail lamber together Placement Tafill Put sand in and under the equipment Ambly Outfill Put dirt a nd the equipment Assembly Decoration Put grass all over the...
Operations Research 4- Consider the (simplified) list of activities and predecessors that are involved in building a house: Description Predecessors Duration (Days) Build foundation Activity Walls and ceilings A Roof Electrical wiring B Put in windows B Put in siding Paint house 10 6 C,F Construct the network for this project, identify the critical path using the (IC,TC,IL,TL, and H) method. 4- Consider the (simplified) list of activities and predecessors that are involved in building a house: Description Predecessors Duration...