Question

Here is an Activity on Arrow (AOA) network diagram for a project. The lettered A through F represents an activity, as shown in the accompanying precedence diagram.

A D E LL


image?w=54&h=23&rev=1&ac=1&parent=1NKCIp

The probabilistic time for each activity is as follows

Activity

Time

Activity

Time

A

4-5-6

D

4-5-6

B

2-5-6

E

2-5-6

C

3-4-5

F

3-4-6

What is the expected time and standard deviation of path A-C-D?

What percentage will path A-C-D finish within 13 weeks?

Please type your answer and the steps of computation

A D E LL
0 0
Add a comment Improve this question Transcribed image text
Answer #1

To find the expected time, we will use the following formula.

T = (a + 4m + b) / 6

A. (4 + (4 * 5 ) + 6) / 6 = 5

B. (2 + (4 * 5 ) + 6) / 6 = 5

C. (3 + (4 * 4 ) + 5) / 6 = 4

D. (4 + (4 * 5 ) + 6) / 6 = 5

E. (2 + (4 * 5 ) + 6) / 6 = 5

F. (3 + (4 * 4 ) + 6) / 6 = 4


To find the variance, we will use the following formula.

Variance = [(b - a) / 6] ^2

A. [(6 -4) / 6 ] ^ 2 = 0.11

B. [(6 -2) / 6 ] ^ 2 = 0.44

C. [(5 -3) / 6 ] ^ 2 = 0.11

D. [(6 -4) / 6 ] ^ 2 = 0.11

E. [(6 -2) / 6 ] ^ 2 = 0.44

F. [(6 -3) / 6 ] ^ 2 = 0.25



ACTIVITY

OPTIMISTIC

MOST LIKELY

PESSIMISTIC

EXPECTED TIME

VARIANCE

a

m

b

t = (a + 4 m + b) / 6

[(b - a) / 6] ^2

A

4

5

6

5

0.11

B

2

5

6

5

0.44

C

3

4

5

4

0.11

D

4

5

6

5

0.11

E

2

5

6

5

0.44

F

3

4

6

4

0.25

CPM

The ES, EF values are calculated using a forward pass where the ES of the next activity is the maximum EF of all the predecessor activities.

The LS, LF values are calculated using a backward pass where the LS of the next activity is the minimum LF of all the Predecessor activities.

The critical path represents all the activities in a particular chain which have the largest duration and 0 slack for all activities, and due to this fact, any delay in the critical activities can cause a delay for the entire project.




ACTIVITY

DURATION

PRE 1

PRE 2

ES

EF

LS

LF

SLACK

A

5

0

5

0

5

0

B

5

0

5

4

9

4

C

4

A

5

9

5

9

0

D

5

C

9

14

9

14

0

E

5

B

5

10

9

14

4

F

4

B

5

9

10

14

5

CRITICAL PATH & DURATION:

A - C - D = 14


PROBABILITY

CRITICAL VARIANCE = A - C - D = 0.11 + 0.11 + 0.11 = 0.33

STANDARD DEVIATION = SQRT(CRITICAL VARIANCE) = SQRT(0.33) = 0.57

EXPECTED = 13 DAYS

Z = DUE - EXPECTED / STANDARD DEVIATION

Z = 14 - 13 / 0.57 = 1.754

THE Z VALUE OF 1.754 GIVES 0.9603 OR 96.03% PROBABILITY OF COMPLETION.



Add a comment
Know the answer?
Add Answer to:
Here is an Activity on Arrow (AOA) network diagram for a project. The lettered A through...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT