Question

Draw the Network Diagram (PDM) Identify All the Paths Through the Network

1) Draw the network diagram (PDM)

2) Identify all the paths through the network

3) select the critical path and explain why 

4) calculate the standard deviation of the critical path 


ActivityPrecedenceDurationSD
ANA62
BNA10
CNA82
DNA41
EA, B62
FC, D62
GE62
HE, F20
JH10
KH92
LG113
MG113
NK, L51
PM31
QK41


0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 9 more requests to produce the answer.

1 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Draw the Network Diagram (PDM) Identify All the Paths Through the Network
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the...

    NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the total project duration. Feel free to verify your answer using MS Project or a similar tool. Activity Dependency Activity Duration (weeks) A B None None AB B F G H 8 9 DE F, G, HI 7 8 5 Draw the Network Diagram using the convention discussed in the class. (If challenged with drawing tools, you can hand draw, take a picture, and paste...

  • Draw the PDM network showing lag factors

    The Planning Manager of ABC (Pvt.) Limited wants you to develop a network plan (a precedence diagram) for a development project which is required to begin In June 2019. Your Supervisor has gathered information from previous projects and formed the Table below (Hint: draw the Finish to Start relationships first) d) (1) Draw the PDM network showing lag factors (2) Calculate the earliest and latest event times (3) Calculate the total float times of each activity (4)Define the critical path State the overall project time

  • Given the following information, Construct the PDM network and use the information given in the following...

    Given the following information, Construct the PDM network and use the information given in the following table, calculate ES, EF, LS, LF and the critical activities. Project Data: 1-U and R can be performed concurrently and both begin on the start of the project. 2-Activity X is independent of both activities Q and K 3-E must start before work on activity K can begin. 4-Neither activity F nor activity G can start before activity R start. However, activities F and...

  • Given the following Project Activities and Precedence Relations table; determine the Critical Path, and the minimum...

    Given the following Project Activities and Precedence Relations table; determine the Critical Path, and the minimum Project Duration. Create the Gantt Chart for the project represented in the table. Project Activities and Precedence Relations ACTIVITY DURATION PRECEDED BY: A 3 B 2 A C 2 D 1 E 1 B F G 2 1 D D H 4 BD 2 J J 1 4 K F L 3 G M N 3 3 IJ H 0 4 HKL MNO Р...

  • Given the following Project Activities and Precedence Relations table; determine the Critical Path, and the minimum...

    Given the following Project Activities and Precedence Relations table; determine the Critical Path, and the minimum Project Duration. Create the Gantt Chart for the project represented in the table. Project Activities and Precedence Relations ACTIVITY DURATION PRECEDED BY: А 3 B 2 A C 2 1 D E 1 B F 2 1 D D G H 4 2 BD E J 1 E F 4 K L 3 G M N 3 3 H 0 4 HKL P MNO...

  • CME403/603 Scheduling and Project Control (10 pts PDM) For the following PDM schedule, manually perform CPM...

    CME403/603 Scheduling and Project Control (10 pts PDM) For the following PDM schedule, manually perform CPM calculation to show items as on legend (key) node - ES, EF, LS, LF, TF, SF and FNF. Highlight critical path(s). 2. 25 8 8 D 11 | 42 46 34 42 3 8 1 3 B 10 C T 16 10 18 29 40 37 Start Finis h 2 0 0 9 12 37 G 24 10 12 4 Legend ES Activity N...

  • Construct an Activity-on-branch network from the precedence relationships of activities shown Activity Predecessors Duration 6 7...

    Construct an Activity-on-branch network from the precedence relationships of activities shown Activity Predecessors Duration 6 7 A A A B с D E F 1 14 5 8 9 3 5 3 B C D C, D D H F E, J F GI G, I L, N H I J K L M 12 6

  • For the project outlined on the following table, (a) draw a network diagram (arrow or PDM,...

    For the project outlined on the following table, (a) draw a network diagram (arrow or PDM, as you prefer), and (b) identify the critical path and duration. (c) Identify the task(s) you would crash and the incremental cost to reduce project duration by (i) one week; (ii) a second week; (iii) a third week. Duration (Weeks) Cost (Dollars) Task Follows Task(s) Normal Crash Normal Crash (Start) (Start) A, B B C D uun $500 400 600 $600 450 750 550...

  • 1. For the following schedule, Draw the AON network diagram for the project and calculate the...

    1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...

  • 17-11) Use this network diagram for questions 11 through 17. 1. What is the expected duration...

    17-11) Use this network diagram for questions 11 through 17. 1. What is the expected duration of the project? (enter a whole number) 2. What is the critical path for this project? 3. What is the early finish time for activity E? 4. What is the early start time for activity D? 5. What is the late finish time for activity C? 6. What is the late start time for activity B? 7. What is the slack time for activity...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT