Question


home /study / business/operations management/operations management questions and answers/c) the planning manager of abc (p Qu

The Planning Manager of ABC (Pvt.) Limited wants you to develop a network plan (a precedence diagram) for a development project which is required to begin In June 2019. Your Supervisor has gathered information from previous projects and formed the Table below (Hint: draw the Finish to Start relationships first) 


d) 

(1) Draw the PDM network showing lag factors 

(2) Calculate the earliest and latest event times 

(3) Calculate the total float times of each activity 

(4)Define the critical path State the overall project time

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Fadw Ae dingem ue hae netriore he D18, 337 T13. 10 I3,231 32,427 Gresi ATas as,3 3342) 13,2] we bae dirgiom nehiore the akoree ged Hint 7he khets time 31-* hich He cay be sauted K) slatert time Aintid Time The can he finis had AM & atot staot time Th

Add a comment
Know the answer?
Add Answer to:
Draw the PDM network showing lag factors
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the...

    NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the total project duration. Feel free to verify your answer using MS Project or a similar tool. Activity Dependency Activity Duration (weeks) A B None None AB B F G H 8 9 DE F, G, HI 7 8 5 Draw the Network Diagram using the convention discussed in the class. (If challenged with drawing tools, you can hand draw, take a picture, and paste...

  • Draw the Network Diagram (PDM) Identify All the Paths Through the Network

    1) Draw the network diagram (PDM)2) Identify all the paths through the network3) select the critical path and explain why 4) calculate the standard deviation of the critical path ActivityPrecedenceDurationSDANA62BNA10CNA82DNA41EA, B62FC, D62GE62HE, F20JH10KH92LG113MG113NK, L51PM31QK41

  • Activity Duration Precedence Problem# 3 For the project information given below (wecks) information a) Draw the...

    Activity Duration Precedence Problem# 3 For the project information given below (wecks) information a) Draw the network diagram to accurately B must be after C represent the information given C must be after A 10 15 b) Determine the earliest start, earliest D must be after B E must be after C F must be after D and E G must be after F H must be after G 1 must be after F finished, latest start, latest finish for...

  • 1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 20...

    1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...

  • Mauritius Pharmaceuticals Ltd was undertaking a project for reviewing the packaging of its saline drips. The...

    Mauritius Pharmaceuticals Ltd was undertaking a project for reviewing the packaging of its saline drips. The activities and the duration of each activity are shown in the table below. Activity Completion time (weeks) ACTIVITY Completion time (weeks) A 6 B 9 C 8 D 5 E 10 F 6 G 14 H 11 I 9 The immediate precedence relationships are:  Activities D and E follow activity B.  Activities A and D follow activity C.  Activities G and...

  • Assignment for week 5 Given the following information, draw the project network

    Assignment for week 5Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?ID duration finish to start finish to start additional lag lag predecessor lag Relationship A 2 none 0 none 0B 4 A 0 none 0C 6 A 0 finish-finish C to F 7D 8 A 0 none 0E 18...

  • Given the following information, Construct the PDM network and use the information given in the following...

    Given the following information, Construct the PDM network and use the information given in the following table, calculate ES, EF, LS, LF and the critical activities. Project Data: 1-U and R can be performed concurrently and both begin on the start of the project. 2-Activity X is independent of both activities Q and K 3-E must start before work on activity K can begin. 4-Neither activity F nor activity G can start before activity R start. However, activities F and...

  • 2. You are in charge of planning and coordinating next fall's sales management training program ur company. You have never done this before, but you decided to use the lessons from for yo yo...

    2. You are in charge of planning and coordinating next fall's sales management training program ur company. You have never done this before, but you decided to use the lessons from for yo your BUS 190 class to develop a table of tasks to be done, their immediate predecessors, and the most pessimistic, optimistic, and frequent times for each task. The table you developed is below: Task completion time estimate (weeks) Most Immediate Variance Task Predecessor Optimistic probable Pessimistic Mean...

  • Please use the information below to draw and solve the network on a piece of paper...

    Please use the information below to draw and solve the network on a piece of paper by: • Complete the forward and backward pass • Identify the critical path Fill in the requested information (Example: ESA - Early Start of Activity A; LFA - Late Finish of Activity A, etc) Duration 3 Predecessor Relationship N 2 - Activity Activity ID Contract sign A Survey Target market C Data collection Presentation Analyze results Demographics G Closing H FS Lag 3 N...

  • 6. Urban Construction Company specializes in constructing bridges. Recently they have got the contract to construct...

    6. Urban Construction Company specializes in constructing bridges. Recently they have got the contract to construct a bridge over a small body of water. It is very important to finish the construction timely as the lack of bridge is hindering the movement of people and vehicles. The management of the company determined the activates required to complete the project, the precedence relationships of the activities and the activity time estimates are as follows: Task time (weeks) Activity Activity Predecessor 10...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT