6. Urban Construction Company specializes in constructing bridges. Recently they have got the contract to construct a bridge
0 0
Add a comment Improve this question Transcribed image text
Answer #1

3 15 1 LO 4 7 8 5 6 2 7 6 12

Activity Predecessor Task Time Early Start Early Finish Late Start Late Finish Float
1 - 10 0 10 0 10 0
2 - 7 0 7 6 13 6
3 1 15 10 25 10 25 0
4 1 4 10 14 14 18 4
5 2 6 7 13 12 18 5
6 2 12 7 19 13 25 6
7 4,5 7 14 21 18 25 4
8 3,7,6 9 25 34 25 34 0

The total duration of project is the duration of critical path which is 1->3->8 of duration 34 weeks

The tasks that have float can be delayed by the amoount of float. Calculated in below table and hghlighted in yellow

Add a comment
Know the answer?
Add Answer to:
6. Urban Construction Company specializes in constructing bridges. Recently they have got the contract to construct...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 13 The following table provides a list of activities in a project, along with their...

    Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...

  • Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing...

    Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing plant. The client expects the plant to be functional within a year. You are assigned as the Project Manager to ensure that the whole project stays on schedule. The two important conditions as per the client contract are:- ABC construction group will incur a penalty if the work is not completed by the deadline of 47 weeks from now. ABC construction group will be...

  • (30%Juana Pueblo is the owner ofJPPR Construction, a Activity Description company that specializes in the construction of single-family residences and small office buildings. She wants to apply p...

    (30%Juana Pueblo is the owner ofJPPR Construction, a Activity Description company that specializes in the construction of single-family residences and small office buildings. She wants to apply project scheduling techniques to one of the homebuilding project she will be undertaking in the near future, Juana hasRough plur identified each of the major activities required for this projectD Frame and has estimated how much time each activity will require Finis The table at the right summarizes this information along withInstall HVAC...

  • QUESTION 1 Your company is planning to implement a construction project in a nearby town. You...

    QUESTION 1 Your company is planning to implement a construction project in a nearby town. You have identified ten (10) activities and their relationship to be carried out in order to complete the project. Table 1 and Figure 1 below show the relationship and the critical path diagram for the project. The duration to complete each activity (days) is stated below the activity. The relationship between activities is 'finish-start with no lag except for the following activities. Table 1: Relationship...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity...

    A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity Duration Time (In DAYS ) Early Start (ES) (In DAYS ) Early Finish (EF) (In DAYS ) Late Start (LS) (In DAYS ) Late Finish (LF) (In DAYS ) SLACK (In DAYS ) A - 14 B - 13 C A 11 D A 15 E B 14 F B 11 G D, E 13 H F 15 J C 12 K G,H 11...

  • Orleans Construction Company Case (adapted from Meredith and Mantel) The Orleans Construction Company, a small construction...

    Orleans Construction Company Case (adapted from Meredith and Mantel) The Orleans Construction Company, a small construction company in North Carolina, has been awarded a contract for the construction of a new 25,000 soccer stadium at Greensboro. The City is hoping to use this facility to attract a new soccer franchise. The construction cannot start earlier than March 2, 2020 (because of the availability of bond funds) and must be completed within 1 year (52 weeks). A penalty clause of $13,000...

  • Recently, you were assigned to manage a project for your company. You have constructed a network...

    Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: ơ Time Estimates (days) Optimistic Most Likely Pessimistic Activity ơ ال 7 کره ) | Start Finish 6 ای یا...

  • You work for a company that makes cell phones and have been made the project manager...

    You work for a company that makes cell phones and have been made the project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning! You have been given the information in Table-1 below. It includes all the...

  • Choose an event or significant task and prepare an activities list following a format similar to...

    Choose an event or significant task and prepare an activities list following a format similar to that used in the text, Table 9.3, Chapter 9, page 391. Be sure to include the immediate predecessors. Then, create a project network similar to that shown in Figure 9.7, Chapter 9, page 392. Do NOT include times for the activities and do NOT attempt to determine the critical path. Examples of events you might consider (there are many others): formal dinner for 5...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT