You work for a company that makes cell phones and have been made the project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!

You have been given the information in Table-1 below. It includes all the activities required in the project and the duration of each activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started.

Your project is divided into five major subprojects. Subproject P involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject S supplier specifications. These involve engineering details for how the product will perform.

The individual components that make up the product are the focus of the subproject D. Subproject I brings all the components together, and a working prototype is built and tested. Finally, in subproject V, suppliers are selected and contracts are negotiated.

Table-1 MAJOR SUBPROJECTS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION (WEEKS) N P1 P2 P3 P4 + LOLO P4 P4 - Product

  1. Draw a project network that includes all the activities.
  2. Calculate the start and finish times for each activity and determine the minimum number of weeks for completing the project. Find the activities that are on the critical path for completing the project in the shortest time.
  3. Identify slack in the activities that are not on the critical path.

Please help would be appreciated i don't understand the assignment I will give a thumbs up

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Please KINDLY GIVE A THUMBS UP, Thank you!

Draw the Network Diagram as shown below: -D1 si—_D2 12 —> 13 $D4>11 —> 14 Start-P1 P2— P3 P4 S2= V2 FinishCalculation of Earliest and Latest, start and finish schedules of activities: 2 P1 Oluwololololo 7 S2 P4 C D E F G H 1 ActiviThe activities of subproject are done in parallel to complete the duration of each subproject that will be equal to largest d

Add a comment
Know the answer?
Add Answer to:
You work for a company that makes cell phones and have been made the project manager...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT