1. EXPECTED TIME(ROUNDED)
FORMULA:
(a + (4m) + b) / 6
A = (5 + (4 * 7) + 10) / 6 = 7
B = (3 + (4 * 8) + 12) / 6 = 8
C = (5 + (4 * 6) + 8) / 6 = 6
D = (2 + (4 * 3) + 6) / 6 = 3
E = (3 + (4 * 8) + 10) / 6 = 8
VARIANCE(ROUNDED 4 PLACES)
FORMULA:
((b - a) / 6) ^ 2
A = (10 - 5) / 6) ^ 2 = 0.6944
B = (12 - 3) / 6) ^ 2 = 2.25
C = (8 - 5) / 6) ^ 2 = 0.25
D = (6 - 2) / 6) ^ 2 = 0.4444
E = (10 - 3) / 6) ^ 2 = 1.3611
A. CPM
After forwards and backwards pass, we get the following value based on the precedence relationship.
ACTIVITY |
DURATION |
ES |
EF |
LS |
LF |
SLACK |
A |
7 |
0 |
7 |
3 |
10 |
3 |
B |
8 |
0 |
8 |
0 |
8 |
0 |
C |
6 |
7 |
13 |
10 |
16 |
3 |
D |
3 |
7 |
10 |
13 |
16 |
6 |
E |
8 |
8 |
16 |
8 |
16 |
0 |
CRITICAL PATH = B + E = 16
DURATION = 16
B. VARIANCE OF CRITICAL PATH = B + E = 2.25 + 1.3611 = 3.6111
STDEV = SQRT(CRITICAL VARIANCE) = 1.9003
Z = DUE - EXPECTED / STDEV
PROBABILITY OF COMPLETION IN 22
EXPECTED = 16
DUE = 22
Z = 22 - 16 / 1.9003 = 3.16
Z value that corresponds to 3.16 = 0.9992 or 99.92%
C. PROBABILITY OF COMPLETION IN 18
EXPECTED = 16
DUE = 18
Z = 18 - 16 / 1.9003 = 1.05
Z value that corresponds to 1.05 = 0.8531 or 85.31%
Recently, you were assigned to manage a project for your company. You have constructed a network...
H m Problem 21 Question Help Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: Time Estimates (days) Most Likely Activity Optimistic Pessimistic A 4 8 12 5 12...
Show all Calculations Question 1 (50 points). You were recently assigned to manage a project for your company. You have constructed a network diagram (depicting the various activities in the project, see figure below). In addition, you have asked your team to estimate the amount of time (in days) that they would expect each of the activities to take. Their responses are shown in the table below: Start Finish Table 1 - Estimates Data Time Estimates (Days) Activity OptimisticMost Likely...
Racentty, you wara assignad to manage a projact tor your compary You hav constructed a natwnrk dagram depching the vanous activites in the project (ahown below to the nght In addtion, you have asked your taam to ashmate the amount of time that they would expact each of the actaties to take. Thair esponses are shown in the feliewing table ime Estimatas (days Most Likaly Activity Optimistic Pess 11 Fmah Start C a axpacted completion bme ot the proct a...
It was determined on the following project that the duration for the tasks contained some uncertainty. After more research, the optimistic and pessimistic values were determined. 1. a. Calculate the expected time and variance (using the 95 percent level of confidence) for each activity. b. Determine the critical path and time for completion c. Calculate the probably that the project will finish in 30 days. Calculate the probably of completing the project in 27 days. Other than the critical path,...
If the contracted duration for a project with the following network is 120 days, what is the probability (in percent) of meeting the schedule based on PERT analysis? Then, assume that the owner delays the start by 5 days while keeping the end date as originally scheduled. What is the probability (in percent) that the project will still finish at the originally scheduled completion date? The requested probabilities should be determined based on the entire network and not just one...
2. You are in charge of planning and coordinating next fall's sales management training program ur company. You have never done this before, but you decided to use the lessons from for yo your BUS 190 class to develop a table of tasks to be done, their immediate predecessors, and the most pessimistic, optimistic, and frequent times for each task. The table you developed is below: Task completion time estimate (weeks) Most Immediate Variance Task Predecessor Optimistic probable Pessimistic Mean...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
2. Given the table below (10 pts): A. Draw the project network B. Calculate the expected time to complete each activity as well as the variance (or standard deviation) associated with that time C. Determine the time associated with each potential path and denote the critical path D. Given the calculated data, what is the probability of completing the project in 30 days? 35 days? E. If you were to try to improve your performance (in terms of time), what...
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....