H m Problem 21 Question Help Recently, you were assigned to manage a project for your...
Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: ơ Time Estimates (days) Optimistic Most Likely Pessimistic Activity ơ ال 7 کره ) | Start Finish 6 ای یا...
Show all Calculations Question 1 (50 points). You were recently assigned to manage a project for your company. You have constructed a network diagram (depicting the various activities in the project, see figure below). In addition, you have asked your team to estimate the amount of time (in days) that they would expect each of the activities to take. Their responses are shown in the table below: Start Finish Table 1 - Estimates Data Time Estimates (Days) Activity OptimisticMost Likely...
It was determined on the following project that the duration for the tasks contained some uncertainty. After more research, the optimistic and pessimistic values were determined. 1. a. Calculate the expected time and variance (using the 95 percent level of confidence) for each activity. b. Determine the critical path and time for completion c. Calculate the probably that the project will finish in 30 days. Calculate the probably of completing the project in 27 days. Other than the critical path,...
Racentty, you wara assignad to manage a projact tor your compary You hav constructed a natwnrk dagram depching the vanous activites in the project (ahown below to the nght In addtion, you have asked your taam to ashmate the amount of time that they would expact each of the actaties to take. Thair esponses are shown in the feliewing table ime Estimatas (days Most Likaly Activity Optimistic Pess 11 Fmah Start C a axpacted completion bme ot the proct a...
5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predecessor of C. The duration estimate for activity A, B and C is shown in the following table. Fill the table with mean duration, standard deviation, and variance for activities and the whole project (critical path). Determine what is the probability of completing this project within 80 days? (10 points) Activity Optimistic Pessimistic Most likely Mean Standard Variance deviation duration...
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
2. You are in charge of planning and coordinating next fall's sales management training program ur company. You have never done this before, but you decided to use the lessons from for yo your BUS 190 class to develop a table of tasks to be done, their immediate predecessors, and the most pessimistic, optimistic, and frequent times for each task. The table you developed is below: Task completion time estimate (weeks) Most Immediate Variance Task Predecessor Optimistic probable Pessimistic Mean...
You are responsible for managing a project with the following activities (all times are given in weeks): Optimistic Most Likely Pessimistic Immediate Time Predecessor(s) Time Activity Time 4 C, D D, E 12 4 8 6 4 What is the expected time of completion of the project? (weeks) (Include 1 decimal place, e.g.,3.1.) abs What is the probability that the project will be completed in 24 weeks or less? (Provide ab 2 decimal places, no 90 sign, e.g., 2.12 for...
A small software development project has eight major activities. The times are estimated and provided in the table below: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 5 -- B 5 7 9 -- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6 10 F Answer the following questions based on above table 1-2...