Question

2. Given the table below (10 pts): A. Draw the project network B. Calculate the expected time to complete each activity as we
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Activity To Tm Tp Te (Var)^0.5 Var
A 3 4 11 5 1.333333 1.777778
B 2 5 8 5 1 1
C 3 6 9 6 1 1
D 8 12 20 12.66667 2 4
E 3 5 12 5.833333 1.5 2.25
F 2 4 7 4.166667 0.833333 0.694444
G 6 9 14 9.333333 1.333333 1.777778
H 1 2 4 2.166667 0.5 0.25

2:Ь ЧТЬ

The possible paths are

ABEH with duration 17.99

ABDFH with duration 28.98

ACDFH with duration 29.98

ACGH with duration 22.49

The critical path is ACDFH with duration 29.98.

Variance of the CP =7,7221

SD of the CP = (7721)^0.5 =2.778

Probability that the project will be completed within 30 days

z = 30-29.98 /2.778 =0.0071

which gives a probability of 50%

Prob. of completing in 35 days

z = 35-29.98 /2.778 =1.807

which gives a probability of 0.9645

Note : As per Chegg policies I can answer the first four questions only. Inconvenience is regretted.

Add a comment
Know the answer?
Add Answer to:
2. Given the table below (10 pts): A. Draw the project network B. Calculate the expected...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT