Hello there,
let us look into the solution directly
Note -; Standard deviation has been denoted by sigma in the table.
the critical path is along START - A - C - E - F -
END and the expected mean time or project duration
is 200 days please ignore the scribblings.
I have committed scribbling,
please ignore them. Please ask any queries you have in the comment
section. Stay at home and safe from coronavirus, Upvote if you
liked the solution. Big thanks.
301247/mod_resource/content/B/Exam%202%20March%202020.pdf - + Fit to page Question 2) Use the table diagram below to answer the...
5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predecessor of C. The duration estimate for activity A, B and C is shown in the following table. Fill the table with mean duration, standard deviation, and variance for activities and the whole project (critical path). Determine what is the probability of completing this project within 80 days? (10 points) Activity Optimistic Pessimistic Most likely Mean Standard Variance deviation duration...
2. Given the table below (10 pts): A. Draw the project network B. Calculate the expected time to complete each activity as well as the variance (or standard deviation) associated with that time C. Determine the time associated with each potential path and denote the critical path D. Given the calculated data, what is the probability of completing the project in 30 days? 35 days? E. If you were to try to improve your performance (in terms of time), what...
If the contracted duration for a project with the following
network is 120 days, what is the probability (in percent) of
meeting the schedule based on PERT analysis? Then, assume that the
owner delays the start by 5 days while keeping the end date as
originally scheduled. What is the probability (in percent) that the
project will still finish at the originally scheduled completion
date? The requested probabilities should be determined based on the
entire network and not just one...
Use the network activity diagram and table below to answer questions 45-53. Activity Optimistic Most Probable Pessimistic A 5 7 B 3 5 7 C 1 2 9 5 E 3 4 2 3 10 G 6 7 14 H 4 12 B G E H. C A. Finish Start F D Using the three time estimate approach, what is the value of uC? O 6 O4 None of the above are correct Use the network activity diagram and table...
Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...
2. Consider the network described in the table below. Immediate Activity Predecessor(s)Pessimistic Probable Optimistic 15 10 8 K 9 8 7 L 10 6 5 M 3 3 3 N KM 9 5 1 O KM 10 7 4 P LN 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path. (c) Calculate the probability that the project will...
Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project duration? ( points) (c) What is the slack time of activity F? ( points)
Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project...
Question 2 (50%): The project information is presented in Table 1. It is known that the critical path of the given project is A - D + G - J. 1) Please fill out the Table 2. (1% * 10-10%) 2) The duration of the project is days (10%) Note: Calculation processes for 1) and 2) are not required. 3) What is the probability of finishing the project in 18 days? (15%) 4) What is the probability of finishing the...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...