Question

Given the following information, Construct the PDM network and use the information given in the following...

Given the following information, Construct the PDM network and use the information given in the following table, calculate ES, EF, LS, LF and the critical activities.

Project Data:

1-U and R can be performed concurrently and both begin on the start of the project.

2-Activity X is independent of both activities Q and K

3-E must start before work on activity K can begin.

4-Neither activity F nor activity G can start before activity R start. However, activities F and G can be performed concurrently.

5-Activity U must finish before the completion of activities E and Q.

6-Activity Q must start before the completion ofactivity J.

7-Activity C is independent of both activities Fand G but follows activity K.

8-Activities E and Q can be done concurrently.

9-Activity H can begin only after activates C, K and J are completed.

10-Activity H is the last activity.

11-Activity X is dependent on the start of activates F and G.

12-Activity G cannot be completed until activity F has started.

13-Consider the following lag time

- U and Q (FF) Lag=2, -U and E (FF)Lag =2, -E and K (SS), Lag=2, -R and G (SS)Lag=2, R and F (SS), Lag=3, -F and G (SF), Lag=1, Q and J (SF), Lag=1

14-The project activities are listed below

Activity Number Duration

U

1 1

R

2 3

F

3 5

G

4 4

E

5 2

Q

6 4

K

7 5

X

8 7

J

9 2

C

10 6

H

11 3
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The PDM network is constructed by using the given project data.

Refer the legends to understand the network correctly.

Early Start(ES), Early Finish(EF), Late Start (LS), Late Finish (LF) , Float (F) , critical activities and Critical paths are found.

Critical paths and activities are highlighted in the network diagram.

U>E>K>C>H

R>F>X>H

All the calculated values are tabulated in the last image for quick and easy reference.

(Please give a thumbs up ).

Add a comment
Know the answer?
Add Answer to:
Given the following information, Construct the PDM network and use the information given in the following...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Assignment for week 5 Given the following information, draw the project network

    Assignment for week 5Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?ID duration finish to start finish to start additional lag lag predecessor lag Relationship A 2 none 0 none 0B 4 A 0 none 0C 6 A 0 finish-finish C to F 7D 8 A 0 none 0E 18...

  • Draw the PDM network showing lag factors

    The Planning Manager of ABC (Pvt.) Limited wants you to develop a network plan (a precedence diagram) for a development project which is required to begin In June 2019. Your Supervisor has gathered information from previous projects and formed the Table below (Hint: draw the Finish to Start relationships first) d) (1) Draw the PDM network showing lag factors (2) Calculate the earliest and latest event times (3) Calculate the total float times of each activity (4)Define the critical path State the overall project time

  • CME403/603 Scheduling and Project Control (10 pts PDM) For the following PDM schedule, manually perform CPM...

    CME403/603 Scheduling and Project Control (10 pts PDM) For the following PDM schedule, manually perform CPM calculation to show items as on legend (key) node - ES, EF, LS, LF, TF, SF and FNF. Highlight critical path(s). 2. 25 8 8 D 11 | 42 46 34 42 3 8 1 3 B 10 C T 16 10 18 29 40 37 Start Finis h 2 0 0 9 12 37 G 24 10 12 4 Legend ES Activity N...

  • Draw the Network Diagram (PDM) Identify All the Paths Through the Network

    1) Draw the network diagram (PDM)2) Identify all the paths through the network3) select the critical path and explain why 4) calculate the standard deviation of the critical path ActivityPrecedenceDurationSDANA62BNA10CNA82DNA41EA, B62FC, D62GE62HE, F20JH10KH92LG113MG113NK, L51PM31QK41

  • Draw the following network and calculate all dates (all activities are contiguous): Activity Duration IPA Type...

    Draw the following network and calculate all dates (all activities are contiguous): Activity Duration IPA Type Rel Lag ES EF LS LF TF FF A 4 - B 3 - C 8 A D 7 A,B E 6 D SS 3 F 3 D FF G 5 F SS 2 2 F FF please do not copy from others, they are wrong

  • Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing...

    Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing plant. The client expects the plant to be functional within a year. You are assigned as the Project Manager to ensure that the whole project stays on schedule. The two important conditions as per the client contract are:- ABC construction group will incur a penalty if the work is not completed by the deadline of 47 weeks from now. ABC construction group will be...

  • please answer from a until i with the solving steps CHAPTER 13 / Developing and implementing...

    please answer from a until i with the solving steps CHAPTER 13 / Developing and implementing Effective Accounting Information Systems 431 14 FIGURE 13-11 PERT network diagram for a systems implementation project. 13-19. Do you understand PERT charts? Refer back to Figure 13-11 and answer the following questions: a. Which activity or activities must be completed before activity C can begin? b. Which activity or activities must be completed before activity G can begin? c. Which activity or activities must...

  • CHAPTER 13 / Developing and implementing Effective Accounting Information Systems 431 14 FIGURE 13-11 PERT network...

    CHAPTER 13 / Developing and implementing Effective Accounting Information Systems 431 14 FIGURE 13-11 PERT network diagram for a systems implementation project. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 Activity Prepare the Physical site 3958 Determine functional changes Select and assign personnel Train personnel Acquire and install computer equipment Establish...

  • QUESTION 1 Your company is planning to implement a construction project in a nearby town. You...

    QUESTION 1 Your company is planning to implement a construction project in a nearby town. You have identified ten (10) activities and their relationship to be carried out in order to complete the project. Table 1 and Figure 1 below show the relationship and the critical path diagram for the project. The duration to complete each activity (days) is stated below the activity. The relationship between activities is 'finish-start with no lag except for the following activities. Table 1: Relationship...

  • Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15...

    Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15 me 10 13 12 20 a) The Project Completion time = b) The Earliest Start time, ES, of Activity F- c) The Earliest Start time, ES, of Activity K = d) The Latest Start time, LS, of Activity. E = e) The non-critical activities are comma, no space) (ex. type in critical activities as ABCD, no

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT