Question

Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15 me 10 13 12 20 a) The Project Comple

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution :

A : Project Completion time : 55

B : ES of F : 10

C : ES of K : 40

D : LS of E : 22

E : Non - critical activities : ABFHJ

Predeces Slack Time ES EF Activit 21 10 4 13 10 4 13 18 18 0 0 13 13 13 B, D 21 28 10 17 4 A, E 28 12 17 35 13 PROJECT DURATI

Add a comment
Know the answer?
Add Answer to:
Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Given is a PERT project network diagram as shown below. Start D Activity Start ABCDEFGH End...

    Given is a PERT project network diagram as shown below. Start D Activity Start ABCDEFGH End Time 0 1.35 3.65 4.327 .36 8.25 1.394 .68 3.250 a) The Project Completion time = (in 2 decimal places) b) The Earliest Start time, Es, of Activity G- (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C (in 2 decimal places) d) The critical activities are (ex. type in critical activities as ABCD no comma, no space)

  • Given is a CPM project network diagram as shown below. A F Start E H End...

    Given is a CPM project network diagram as shown below. A F Start E H End B D G Start H Activity day А 6 B 3 с 8 D 7 E 4 F 9 G 4 End 0 0 6 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity - dayy d) The critical activities are (ex. Fill in answer as: ABCD)

  • Given is a CPM project network diagram as shown below. A וד H End Start التا...

    Given is a CPM project network diagram as shown below. A וד H End Start التا B D G A F H Activity day Start 0 B 8 с 3 D 5 E 6 وانما | End 0 8 4 a) The Project Completion time = days b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days d) The critical activities are = (ex. Fill in answer as:...

  • Given is a CPM project network diagram as shown below. Activity Start A B C D...

    Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End day 0 5 6 9 6 9 8 5 4 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days.. d) The critical activities are = (ex. Fill in answer as: ABCD) End Start

  • QUESTION 5 Given is a CPM project network diagram as shown below. A F Start H...

    QUESTION 5 Given is a CPM project network diagram as shown below. A F Start H End B D G B Activity days Start 0 A 2 H D 3 E 4 F 2 G 3 6 8 End 0 2 a) The Project Completion time days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity C- days. d) The critical activities are (ex. Fill in answer as: ABCD)

  • QUESTION 5 Given is a CPM project network diagram as shown below. A с F Start...

    QUESTION 5 Given is a CPM project network diagram as shown below. A с F Start E H End B D Start A B E H End Activity day с 7 D 3 F 5 G 6 0 2 4 3 0 a) The Project Completion time = days. b) The Earliest Start time, Es, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C - days. d) The critical activities are (ex. Fill in answer...

  • QUESTION 5 Given is a CPM project network diagram as shown below. А F Start E...

    QUESTION 5 Given is a CPM project network diagram as shown below. А F Start E H End B D G Start A B C D E F G H End Activity day 0 6 زر 8 7 4 9 4 6 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in...

  • 1. Use appropriate nodes and arrows to draw the network diagram. On the netrk dingram, labci...

    1. Use appropriate nodes and arrows to draw the network diagram. On the netrk dingram, labci the activity t 2. Scan your network diagram in the pdf file format. 3.Submit your assignment by uploading the file. Attach File Browse My Computer QUESTION 2 Given is a PERT project network diagram as shown below Start End Time t-0 321-21 2.31 a) The Project Completion time- b) The Earliest Start time, ES, of Activity G c) The Latest Finish time, LF, of...

  • QUESTION 5 Given is a CPM project network diagram as shown below. А C F Start...

    QUESTION 5 Given is a CPM project network diagram as shown below. А C F Start E Н. End B D G A B D E F G H Activity day Start 0 с 8 End 0 6 3 7 4 9 4 6 a) The Project Cor etion time = days b) The Earliest Start time, ES, of Activity G- days. c) The Latest Finish time, LF, of Acitivity - days. d) The critical activities are = (ex. Fill...

  • please show answers clearly 12 points Save Answer QUESTION 5 Given is a CPM project network...

    please show answers clearly 12 points Save Answer QUESTION 5 Given is a CPM project network diagram as shown below. F А H End E Start G B D E F Activity day Start 0 A 5 B 6 Ula G 5 H 4 End 0 ON 9 8 days. a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days.. c) The Latest Finish time, LF, of Acitivity C = d) The critical...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT