Solution :
A : Project Completion time : 55
B : ES of F : 10
C : ES of K : 40
D : LS of E : 22
E : Non - critical activities : ABFHJ
Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15...
Given is a PERT project network diagram as shown below. Start D Activity Start ABCDEFGH End Time 0 1.35 3.65 4.327 .36 8.25 1.394 .68 3.250 a) The Project Completion time = (in 2 decimal places) b) The Earliest Start time, Es, of Activity G- (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C (in 2 decimal places) d) The critical activities are (ex. type in critical activities as ABCD no comma, no space)
Given is a CPM project network diagram as shown below. A F Start E H End B D G Start H Activity day А 6 B 3 с 8 D 7 E 4 F 9 G 4 End 0 0 6 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity - dayy d) The critical activities are (ex. Fill in answer as: ABCD)
Given is a CPM project network diagram as shown below. A וד H End Start التا B D G A F H Activity day Start 0 B 8 с 3 D 5 E 6 وانما | End 0 8 4 a) The Project Completion time = days b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days d) The critical activities are = (ex. Fill in answer as:...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End day 0 5 6 9 6 9 8 5 4 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days.. d) The critical activities are = (ex. Fill in answer as: ABCD) End Start
QUESTION 5 Given is a CPM project network diagram as shown below. A F Start H End B D G B Activity days Start 0 A 2 H D 3 E 4 F 2 G 3 6 8 End 0 2 a) The Project Completion time days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity C- days. d) The critical activities are (ex. Fill in answer as: ABCD)
QUESTION 5 Given is a CPM project network diagram as shown below. A с F Start E H End B D Start A B E H End Activity day с 7 D 3 F 5 G 6 0 2 4 3 0 a) The Project Completion time = days. b) The Earliest Start time, Es, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C - days. d) The critical activities are (ex. Fill in answer...
QUESTION 5 Given is a CPM project network diagram as shown below. А F Start E H End B D G Start A B C D E F G H End Activity day 0 6 زر 8 7 4 9 4 6 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in...
1. Use appropriate nodes and arrows to draw the network diagram. On the netrk dingram, labci the activity t 2. Scan your network diagram in the pdf file format. 3.Submit your assignment by uploading the file. Attach File Browse My Computer QUESTION 2 Given is a PERT project network diagram as shown below Start End Time t-0 321-21 2.31 a) The Project Completion time- b) The Earliest Start time, ES, of Activity G c) The Latest Finish time, LF, of...
QUESTION 5 Given is a CPM project network diagram as shown below. А C F Start E Н. End B D G A B D E F G H Activity day Start 0 с 8 End 0 6 3 7 4 9 4 6 a) The Project Cor etion time = days b) The Earliest Start time, ES, of Activity G- days. c) The Latest Finish time, LF, of Acitivity - days. d) The critical activities are = (ex. Fill...
please show answers clearly 12 points Save Answer QUESTION 5 Given is a CPM project network diagram as shown below. F А H End E Start G B D E F Activity day Start 0 A 5 B 6 Ula G 5 H 4 End 0 ON 9 8 days. a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days.. c) The Latest Finish time, LF, of Acitivity C = d) The critical...