CME403/603 Scheduling and Project Control (10 pts PDM) For the following PDM schedule, manually perform CPM...
5 & 17. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 5 with an imposed finish date of 26 and then 35 days. Activity Duration IPA ES EF LS LF TF FF A 6 - B 2 - C 9 - D 4 A, B E 7 B F 5 D G 10 D, E H 8 C, F, G I 3 C, G J 2...
For the following, draw the node network, perform the CPM calculations, mark the critical Path, and complete the table. IAAB 745 00 ABCDE Make possibility of rejection. Also show procurement activities CHAPTER 4 EXERCISES 1. For the following schedule, draw the node network, perform the CPM tions, mark the critical path, and complete the table. Activity Duration IPA ES EF LS LF TF FF В 8 B, C For the following schedule, draw the node network, perform the CPM tions,...
3 & 15. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 3 with an imposed finish date of 15 and then 20 days. Activity Duration IPA ES EF LS LF TF FF A 2 - B 4 A C 6 A D 9 A E 5 B F 7 B, C G 3 D, E, F
3. For the following schedule, draw the node network, perform the CPM calcula tions, mark the critical path, and complete the table TF FE LS LF ES IPA Duration Activity 2 A - A 4 A 6 C A 5 F B, C D, E, F 7 F 3 G
7. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Activity IPA Duration ES EF LS LF TF FF A - 3 0 3 3 6 3 5 B - 5 0 5 5 10 5 2 C A 6 3 9 9 14 5 4 D A, B 9 5 14 14 23 9 9 E A, B 4 5 9 9 12 7 4 F B 6...
Construction Management Assignment on "Critical Path Method (CPM)" Do the following tasks for each of the questions (a) Draw both the activity-on-arrow (AOA) network and the activity-on-node (AON) network. (b) Calculate the early start time (ES), early finish time (EF), late start time (LS), and late finish time (LF) of each activity, and identify the critical path. (c) Compute the total float (TF), free float (FF), interfering float (IF), and independent float (IDF) for each activity (Note: The duration of...
Construction Management Assignment on "Critical Path Method (CPM)" Do the following tasks for each of the questions (a) Draw both the activity-on-arrow (AOA) network and the activity-on-node (AON) network. (b) Calculate the early start time (ES), early finish time (EF), late start time (LS), and late finish time (LF) of each activity, and identify the critical path. (c) Compute the total float (TF), free float (FF), interfering float (IF), and independent float (IDF) for each activity (Note: The duration of...
Given the following information, Construct the PDM network and use the information given in the following table, calculate ES, EF, LS, LF and the critical activities. Project Data: 1-U and R can be performed concurrently and both begin on the start of the project. 2-Activity X is independent of both activities Q and K 3-E must start before work on activity K can begin. 4-Neither activity F nor activity G can start before activity R start. However, activities F and...
Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...
Consider a project with the following information: Activity Duration Predecessors A 5 -- B 7 A C 9 B D 5 B E 7 C, D F 6 D G 4 C H 7 E, F, G Activity Duration ES EF LS LF Float A 5 0 5 0 5 B 7 5 12 5 12 C 9 12 21 12 21 D 5 12 17 16 21 E 7 21 28 21 28 F 6 17 23 22 28...