For the following, draw the node network, perform the CPM calculations, mark the critical Path, and complete the table.
1. Network Diagram -
Network Paths and their duration -
ABD --> 3+7+5 = 15
ABE --> 3+7+8 = 18
ACE --> 3+4+8 = 15
Critical path is the path with longest duration i.e A-B-E
Project duration = duration of critical path = 18
Earliest Start (ES) = the earliest time when the activity can begin
Earliest Finish (EF) = ES + Activity Duration
Latest Finish (LF) = the latest time by whenthe activity can be finished without changing the project completion duration
Latest Start (LS) = LF - Activity Duration
Free float (FF) = (ES of next Activity – EF of current Activity)
Total Float (TF) = LS-ES = LF-EF
Computing using the above gives us the below -
Activity | Precedes | Duration | ES | EF | LS | LF | TF | FF |
A | - | 3 | 0 | 3 | 0 | 3 | 0 | 0 |
B | A | 7 | 3 | 10 | 3 | 10 | 0 | 0 |
C | A | 4 | 3 | 7 | 6 | 10 | 3 | 3 |
D | B | 5 | 10 | 15 | 13 | 18 | 3 | 3 |
E | B, C | 8 | 10 | 18 | 10 | 18 | 0 | 0 |
For the following, draw the node network, perform the CPM calculations, mark the critical Path, and...
3 & 15. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 3 with an imposed finish date of 15 and then 20 days. Activity Duration IPA ES EF LS LF TF FF A 2 - B 4 A C 6 A D 9 A E 5 B F 7 B, C G 3 D, E, F
3. For the following schedule, draw the node network, perform the CPM calcula tions, mark the critical path, and complete the table TF FE LS LF ES IPA Duration Activity 2 A - A 4 A 6 C A 5 F B, C D, E, F 7 F 3 G
5 & 17. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 5 with an imposed finish date of 26 and then 35 days. Activity Duration IPA ES EF LS LF TF FF A 6 - B 2 - C 9 - D 4 A, B E 7 B F 5 D G 10 D, E H 8 C, F, G I 3 C, G J 2...
7. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Activity IPA Duration ES EF LS LF TF FF A - 3 0 3 3 6 3 5 B - 5 0 5 5 10 5 2 C A 6 3 9 9 14 5 4 D A, B 9 5 14 14 23 9 9 E A, B 4 5 9 9 12 7 4 F B 6...
1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...
CME403/603 Scheduling and Project Control (10 pts PDM) For the following PDM schedule, manually perform CPM calculation to show items as on legend (key) node - ES, EF, LS, LF, TF, SF and FNF. Highlight critical path(s). 2. 25 8 8 D 11 | 42 46 34 42 3 8 1 3 B 10 C T 16 10 18 29 40 37 Start Finis h 2 0 0 9 12 37 G 24 10 12 4 Legend ES Activity N...
QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration. (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B A 7...
QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B А 7...
Perform the CPM calculations for the following network diagram. Identify the critical path. PE
Draw the following network and calculate all dates (all activities are contiguous): Activity Duration IPA Type Rel Lag ES EF LS LF TF FF A 4 - B 3 - C 8 A D 7 A,B E 6 D SS 3 F 3 D FF G 5 F SS 2 2 F FF please do not copy from others, they are wrong