Perform the CPM calculations for the following network diagram. Identify the critical path. PE

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Critical palt: It is the mounting time which the all project activities are completed. Possib (PS= A> B EF possible ways Crit

Add a comment
Know the answer?
Add Answer to:
Perform the CPM calculations for the following network diagram. Identify the critical path. PE
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • For the following, draw the node network, perform the CPM calculations, mark the critical Path, and...

    For the following, draw the node network, perform the CPM calculations, mark the critical Path, and complete the table. IAAB 745 00 ABCDE Make possibility of rejection. Also show procurement activities CHAPTER 4 EXERCISES 1. For the following schedule, draw the node network, perform the CPM tions, mark the critical path, and complete the table. Activity Duration IPA ES EF LS LF TF FF В 8 B, C For the following schedule, draw the node network, perform the CPM tions,...

  • 3 & 15. For the following schedule, draw the node network, perform the CPM calculations, mark...

    3 & 15. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 3 with an imposed finish date of 15 and then 20 days. Activity Duration IPA ES EF LS LF TF FF A 2 - B 4 A C 6 A D 9 A E 5 B F 7 B, C G 3 D, E, F

  • QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to...

    QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration. (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B A 7...

  • QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to...

    QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B А 7...

  • 5 & 17. For the following schedule, draw the node network, perform the CPM calculations, mark...

    5 & 17. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 5 with an imposed finish date of 26 and then 35 days. Activity Duration IPA ES EF LS LF TF FF A 6 - B 2 - C 9 - D 4 A, B E 7 B F 5 D G 10 D, E H 8 C, F, G I 3 C, G J 2...

  • NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the...

    NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the total project duration. Feel free to verify your answer using MS Project or a similar tool. Activity Dependency Activity Duration (weeks) A B None None AB B F G H 8 9 DE F, G, HI 7 8 5 Draw the Network Diagram using the convention discussed in the class. (If challenged with drawing tools, you can hand draw, take a picture, and paste...

  • 3. For the following schedule, draw the node network, perform the CPM calcula tions, mark the...

    3. For the following schedule, draw the node network, perform the CPM calcula tions, mark the critical path, and complete the table TF FE LS LF ES IPA Duration Activity 2 A - A 4 A 6 C A 5 F B, C D, E, F 7 F 3 G

  • 7. For the following schedule, draw the node network, perform the CPM calculations, mark the critical...

    7. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Activity IPA Duration ES EF LS LF TF FF A - 3 0 3 3 6 3 5 B - 5 0 5 5 10 5 2 C A 6 3 9 9 14 5 4 D A, B 9 5 14 14 23 9 9 E A, B 4 5 9 9 12 7 4 F B 6...

  • 11. In CPM/PERT, an activity that is on the critical path A. has equal values for...

    11. In CPM/PERT, an activity that is on the critical path A. has equal values for "Latest Start" and "Earliest Start" ( LS = ES ) B. has equal values for "Latest Finish" and "Earliest Finish" ( LF = EF ) C. is used in calculating total project duration D. has slack equal to zero E. all of the above 12. In CPM/PERT, the critical path through the network A. will require the most time of any path B. will...

  • Calculate the Critical Path based on the given Network Activity Diagram You have to calculate: Earliest...

    Calculate the Critical Path based on the given Network Activity Diagram You have to calculate: Earliest Start Time Latest Start Time CPM/PERT Breadboard hardware Test Design Release Manufacture hardware hardware hardware hardware Formalize Design Complete Release Specs software software software 2 0 11 Layout manual Finish manual Release manual Print manuals 10 Start project Al specs finalized Hardware design completed Breadboard runing Hardware fully functional PC Board released 10 Manual finalized Manual ready for printer Project complete Critical path 11...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT