Consider a project with the following information: Activity Duration Predecessors A 5 -- B 7 A...

Consider a project with the following information:

Activity Duration Predecessors
A 5 --
B 7 A
C 9 B
D 5 B
E 7 C, D
F 6 D
G 4 C
H 7 E, F, G
Activity Duration ES EF LS LF Float
A 5 0 5 0 5
B 7 5 12 5 12
C 9 12 21 12 21
D 5 12 17 16 21
E 7 21 28 21 28
F 6 17 23 22 28
G 4 21 25 24 28
H 7 28 35 28 35
Activity Duration Total Float Resource Hours Needed per Week Total Resources Required
A 5 Weeks 10
B 7 Weeks 8
C 9 Weeks 7
D 5 Weeks 8
E 7 Weeks 4
F 6 Weeks 6
G 4 Weeks 5
H 7 Weeks 8
Total

  

1. Calculate the total resources required for this project, and create a Resource Loading table, highlighting the activity float.

2. Consider that the maximum resource hours available per week are 10. Which weeks are overcommitted?

3. What options are available for you to resource-level the project? Re-create the Resource Loading table.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Float = LF - EF

Activity Duration ES EF LS LF Float
A 5 0 5 0 5 0
B 7 5 12 5 12 0
C 9 12 21 12 21 0
D 5 12 17 16 21 4
E 7 21 28 21 28 0
F 6 17 23 22 28 5
G 4 21 25 24 28 3
H 7 28 35 28 35 0
Activity Duration Total Float Resource Hours Needed per Week Total Resources Required
A 5 Weeks 0 10 50
B 7 Weeks 0 8 56
C 9 Weeks 0 7 63
D 5 Weeks 4 8 40
E 7 Weeks 0 4 28
F 6 Weeks 5 6 36
G 4 Weeks 3 5 20
H 7 Weeks 0 8 56

1.

Resource loading table with resource histogram:

2.

As it is very clear from the resource histogram, weeks starting from week-13 and up to week-23, the resources are overcommitted i.e. more than 10 per week.

3.

The project cannot be completed within 35 weeks' time if the capacity is 10 hours per week. We can use the floats to balance the load but still overshooting happens in-between. This is shown below:

So, the only alternative is to extend the project beyond 35 weeks as shown:

So, the project has to be delayed by 11 more weeks.

Add a comment
Know the answer?
Add Answer to:
Consider a project with the following information: Activity Duration Predecessors A 5 -- B 7 A...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT