Question

17-11) Use this network diagram for questions 11 through 17.

1. What is the expected duration of the project? (enter a whole number)

2. What is the critical path for this project?

3. What is the early finish time for activity E?

4. What is the early start time for activity D?

5. What is the late finish time for activity C?

6. What is the late start time for activity B?

7. What is the slack time for activity E?

C.22 D.1 F,4 A,18 G, 15 B,24 E,3

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Expected duration of the project is 61 days with critical path ABFG

2. Critical path is ABFG.

3.

Activity ES EF LS LF Slack
A 0 18 0 18 0
B 18 42 18 42 0
C 18 40 19 41 1
D 40 41 41 42 1
E 42 45 43 46 1
F 42 46 42 46 0
G 46 61 46 61 0

EF for E=45

4.ES for D =40

5.LF for C =41

6.LS for B = 18

7 Slack for E = 1

Add a comment
Know the answer?
Add Answer to:
17-11) Use this network diagram for questions 11 through 17. 1. What is the expected duration...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project manager discovers that his team has neglected tocomplete the network diagram for the...

    A project manager discovers that his team has neglected to complete the network diagram for the project. the network diagram is shown below. however the project manager has some information available, specifically that each activity a-g, has a different duration between one and seven weeks. also the slack time for each of the activity is known as shown belowDuration (weeks): 1,2,3,4,5,6,7 Slack time (weeks): 0,0,0,1,1,3,7 A D E G B FINISH START C F Using the clues provided below, determine...

  • QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to...

    QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration. (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B A 7...

  • QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to...

    QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B А 7...

  • Please help with 1-2!! Network diagram: Exercise # 4 Based on Excercise 3 from Module 6: 1. Perform a Forward...

    Please help with 1-2!! Network diagram: Exercise # 4 Based on Excercise 3 from Module 6: 1. Perform a Forward Pass and a Backward Pass of the network diagram above 2. Which Activities has the same Early Finish as they have Late Finish? Note: The project starts on Day "O" Early Start Duration Early Finsh Task Name Late Start Late Finish Slack A 2. 2 6 4 H Exercise # 4 Based on Excercise 3 from Module 6: 1. Perform...

  • Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...

    Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....

  • Assignment for week 5 Given the following information, draw the project network

    Assignment for week 5Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?ID duration finish to start finish to start additional lag lag predecessor lag Relationship A 2 none 0 none 0B 4 A 0 none 0C 6 A 0 finish-finish C to F 7D 8 A 0 none 0E 18...

  • Please help me with this question (( clear draw Please)) Draw the network diagram, including all...

    Please help me with this question (( clear draw Please)) Draw the network diagram, including all calculations of nodes using the following format: Early Start Duration Early Finish Task Name Late Sta rt Slack Late Finish List the networkpaths below: Determine the criticalpath(s). What is it and what is its duration? Activity Duration Dependency Start 0 A 6 Start B 1 A C 3 A,B D 5 A, B E 12 Start F 4 D, E G 2 C, F...

  • 9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activit...

    9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20 points) Predecessor Duration (Days) Activity A, B C, D F,G 9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20...

  • Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity...

    Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. Calculate the slack for each activity. Identify all activities on the Critical Path. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score). Activity A 8 с D E...

  • (3) Determine the critical path and critical time of the network shown below. Use the critical...

    (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). po Problem . Example a 100 For all starting activities, ES is taken as 0. Activities 1-2, 1-3 gets ES of O. Find EF-ES +time. Activity Time ES E F LS L...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT