Question

Given the following table, construct the network diagram, either AOA or

AON. Times are in days

Path Activity Time Estimates 4-5-6 7-8-10 3-6-9 7-8-10 2-3-4 1-4-6 Top Bottom E

a. Determine the expected duration of the project.

b.Compute the probability that the project will take at least 18 days.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

8.16 8.16 3.83 36 연 each atmy(나)-(부) 6 ti 5 チ 2 16 814 026 - チ 8 10 8.16 o.25 34 30-11 vo ba D Yol e 8 dasdeta.mined by Te- project duatoo 19

Add a comment
Know the answer?
Add Answer to:
Given the following table, construct the network diagram, either AOA or AON. Times are in days a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Complete an AON network diagram based on the scenario below. Make sure you respond to each of the...

    Complete an AON network diagram based on the scenario below. Make sure you respond to each of the following five requirements. Construct an AON diagram using the process described in the videos. Calculate the estimated time for each activity using the three estimates provided. Determine the length of all paths and identify which path is the critical path. During the play, one of the activities on the critical path is delayed by one day. Is this serious? Qualitatively discuss the...

  • For the activities given in the table: Draw the AOA network diagram Find the critical activities...

    For the activities given in the table: Draw the AOA network diagram Find the critical activities Find the critical path Find the project completion time Time (days) Predecessors Activity Description Initial Paperwork A 3 Build Body B A 3 C Build Frame A 2 Finish Body 3 D E Finish Frame C Final Paperwork B,C 3 G Mount Body to Frame D,E 6 Install Skirt on Frame C 2 H A FLO For the activities given in the table: Draw...

  • Activity Duration (week) Predecessors C,E,D a) Draw AOA network diagram (grading will be done only for...

    Activity Duration (week) Predecessors C,E,D a) Draw AOA network diagram (grading will be done only for AOA, not AON] (12 pts) a) When will the project be available (completion of project)? (2 pts) b) What is the effect on the project if activity E takes an extra week? (3 pts)

  • 1. For the following schedule, Draw the AON network diagram for the project and calculate the...

    1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...

  • Here is an Activity on Arrow (AOA) network diagram for a project. The lettered A through...

    Here is an Activity on Arrow (AOA) network diagram for a project. The lettered A through F represents an activity, as shown in the accompanying precedence diagram. The probabilistic time for each activity is as follows Activity Time Activity Time A 4-5-6 D 4-5-6 B 2-5-6 E 2-5-6 C 3-4-5 F 3-4-6 What is the expected time and standard deviation of path A-C-D? What percentage will path A-C-D finish within 13 weeks? Please type your answer and the steps of...

  • AON DIAGRAM

    ACTIVITY   IMMEDIATE PREDECESSORSOPTIMISTIC TIMEMOST LIKELY TIMEPRESSMISTIC TIMEA-124B-33.54C-101212D-457E-245FA678GB245.5HC57.79IC9.91012JC245KD246LE246MF,G,H566.5NJ,K,L11.12OI,M578PN579  Q1.draw an activity network diagram showing es, ef, ls and lm?Q2.calculate estimated time t and variance for each activity?Q3 .calculate the project completion time and project variance?Q4.determine the number of paths associated with the network diagram? Q5.find out the critical path?Q5.you as a manager would like to determine the project completion time, so what is the probability of this project being done in 63 days.?Q6.what date results in a 99% probability of completion? 

  • 2- Consider the AON network illustrated below: B G H A F Activity A B с...

    2- Consider the AON network illustrated below: B G H A F Activity A B с D E F Duration 5 3 7 6 2 3 4 5 H a) Calculate the project completion time b) What is the critical path? c) Calculate the slack time for each activity.

  • The following info is available for drawing a PERT network using AOA. *(More than one answer...

    The following info is available for drawing a PERT network using AOA. *(More than one answer may be selected)* Activity Immediate Predecessors Activity Duration (days) A -- 10 B -- 13 C A 12 D B 15 E A 13 F C 16 G D,E 10 H G,F 5 a. the critical path includes: B, D, G, and H. b. the slack on activity G is not 11 days. c. there is one critical path. d. the total duration to...

  • Q1. a) Draw a project network using (AOA) method, b) and calculate (EST, EFT, LFT, LST)...

    Q1. a) Draw a project network using (AOA) method, b) and calculate (EST, EFT, LFT, LST) for each activity, c) and define the critical path. Activity Symbol A B C Predecessor Activity D E F G Duration (Weeks) Nil Nil Nil 5 9 4 B 7 AC C 8 7 D F

  • 2- Consider the AON network illustrated below: M E H Activity А B с D E...

    2- Consider the AON network illustrated below: M E H Activity А B с D E F Duration 5 3 7 2 3 4 5 H a) Calculate the project completion time b) What is the critical path? c) Calculate the slack time for each activity.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT