Activity Duration (week) Predecessors C,E,D a) Draw AOA network diagram (grading will be done only for...
For the activities given in the table: Draw the AOA network diagram Find the critical activities Find the critical path Find the project completion time Time (days) Predecessors Activity Description Initial Paperwork A 3 Build Body B A 3 C Build Frame A 2 Finish Body 3 D E Finish Frame C Final Paperwork B,C 3 G Mount Body to Frame D,E 6 Install Skirt on Frame C 2 H A FLO For the activities given in the table: Draw...
1. Draw the network diagram Precedences and Durations for a Seven Activity Project Activity Description Predecessors Duration Preliminary design Evaluation of design Contract negotiation Preparation of fabrication plantC Final design Fabrication of Product D B, C D, E 12 G Shipment of Product to ownerF
1. Draw the network diagram Precedences and Durations for a Seven Activity Project Activity Description Predecessors Duration Preliminary design Evaluation of design Contract negotiation Preparation of fabrication plantC Final design Fabrication of Product D B, C D, E 12 G Shipment of Product to ownerF
1) Construct an activity on arrow (AOA) network based on the activity description below. Activity Predecessors A - B A C A D A E B, C F E G F H G
Draw the AON and AOA network for a given problem. Activity Predecessor B B C DE DE F, G, H
Given the following table, construct the network diagram, either AOA or AON. Times are in days a. Determine the expected duration of the project. b.Compute the probability that the project will take at least 18 days. Path Activity Time Estimates 4-5-6 7-8-10 3-6-9 7-8-10 2-3-4 1-4-6 Top Bottom E Path Activity Time Estimates 4-5-6 7-8-10 3-6-9 7-8-10 2-3-4 1-4-6 Top Bottom E
Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as shown in the following table. Draw the project network diagram, find the critical path and calculate the corresponding project completion time. Also, find the total float as well as the free float for each activity and the non- critical activities. (10 Marks) ТРА Duration (Weeks) Activity A B نما 4 с 14 D A 10 E F A BD BD с F.H 5 4...
The following info is available for drawing a PERT network using AOA. *(More than one answer may be selected)* Activity Immediate Predecessors Activity Duration (days) A -- 10 B -- 13 C A 12 D B 15 E A 13 F C 16 G D,E 10 H G,F 5 a. the critical path includes: B, D, G, and H. b. the slack on activity G is not 11 days. c. there is one critical path. d. the total duration to...
2- Consider the AON network illustrated below: M E H Activity А B с D E F Duration 5 3 7 2 3 4 5 H a) Calculate the project completion time b) What is the critical path? c) Calculate the slack time for each activity.
Here is an Activity on Arrow (AOA) network diagram for a project. The lettered A through F represents an activity, as shown in the accompanying precedence diagram. The probabilistic time for each activity is as follows Activity Time Activity Time A 4-5-6 D 4-5-6 B 2-5-6 E 2-5-6 C 3-4-5 F 3-4-6 What is the expected time and standard deviation of path A-C-D? What percentage will path A-C-D finish within 13 weeks? Please type your answer and the steps of...