1. Draw the network diagram Precedences and Durations for a Seven Activity Project Activity Description Predecessors Du...
1. Draw the network diagram Precedences and Durations for a Seven Activity Project Activity Description Predecessors Duration Preliminary design Evaluation of design Contract negotiation Preparation of fabrication plantC Final design Fabrication of Product D B, C D, E 12 G Shipment of Product to ownerF
Activity Duration (week) Predecessors C,E,D a) Draw AOA network diagram (grading will be done only for AOA, not AON] (12 pts) a) When will the project be available (completion of project)? (2 pts) b) What is the effect on the project if activity E takes an extra week? (3 pts)
The activities,, their durations and predecessor activities for designing, writing and installing a computer database are shown in the table below Predecessor activity Duration (weeks) Activity 1 1. Contract negotiation 1 2. Discussions with main users 1 3. Review of current documentation 2 4. Review of current systems 3, 4 4 5. Systems analysis (a) 5 7 6. Systems analysis (b) 5 12 7. Programming 7 8. Preliminary testing 3, 4 9. Existing system review report 5, 9 10. System...
Concerning the activities the following standards were set: ACTIVITY DESCRIPTION PRECEDING ACTIVITY ACTIVITY DURATION(DAYS) A Feasibility Study None 7 B Internal Specs A 5 C External Specs A 13 D Internal Analysis B 5 E Functional Specs C,D 10 F Hardware Specs E 15 G Hardware Acquisition F 5 H System Installation G 3 I Design material A 45 J System Testing H,I 10 a) Draw a network diagram (Activity-on-None) of the project presented in the case study with all...
1) Construct an activity on arrow (AOA) network based on the activity description below. Activity Predecessors A - B A C A D A E B, C F E G F H G
For the activities given in the table: Draw the AOA network diagram Find the critical activities Find the critical path Find the project completion time Time (days) Predecessors Activity Description Initial Paperwork A 3 Build Body B A 3 C Build Frame A 2 Finish Body 3 D E Finish Frame C Final Paperwork B,C 3 G Mount Body to Frame D,E 6 Install Skirt on Frame C 2 H A FLO For the activities given in the table: Draw...
For the following Engineering project, draw the network diagram and calculate ES, EF, LS, LF, TF Predecessors Durations (Days) A1 3 A2 A1 7 A3 A1 14 A4 A2, A3 3 Activity ES EF LF LS TF A1 A2 A3 A4 Critical Path is
1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...
Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as shown in the following table. Draw the project network diagram, find the critical path and calculate the corresponding project completion time. Also, find the total float as well as the free float for each activity and the non- critical activities. (10 Marks) ТРА Duration (Weeks) Activity A B نما 4 с 14 D A 10 E F A BD BD с F.H 5 4...
A project of seven activities is defined as follows: Activity/ Immediate Predecessors/ Est. Time in wks A / - / 4 / E / - / 9 / F / E / 5 / D / A / 2 / C / A / 6 / G / F,D / 3 / K /C,G / 0 Which of the following statements is correct? Statments not provided please show all work for solving this problem to full potential for Earliest and...