For the following Engineering project, draw the network diagram and calculate ES, EF, LS, LF, TF...
1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...
Question 5 For the project depicted below, a) Compute the ES, EF, LS, and LF times for the network. b) Explain how the ES for Activity 3 is obtained. c) Explain how the LF time for Activity 1 is obtained. d) What is the critical path for the project? e) How long do you expect the project to take to complete? Activity 4 Activity 2 ES= EF= wks LSELF ES= EF T=5 wks LSELF= Activity 1 ES= EF= T=6 wks...
Calculate ES, EF. LS, LF and Float for the network shown below. Highlight the critical path. 5 6
21. Using the CPM method, calculate early start (ES), late start (LS), early finish (EF), late finish (LF) and total float (TF) for each activity in the following network and answer the questions 21-1. The ES of activity His: a) 18 b) 22C) 5 d) 2 21-2. The LF of activity B is: a) 20 b) 22c) 18d) 19 ) 13 d) 59 21-3. The TF of activity A is: a) 5 b ) 17 c) 18 21-4. The project...
3 & 15. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 3 with an imposed finish date of 15 and then 20 days. Activity Duration IPA ES EF LS LF TF FF A 2 - B 4 A C 6 A D 9 A E 5 B F 7 B, C G 3 D, E, F
PLEASE SOLVE FOR ALL :) determine ES, EF, LS, LF, and slack for each Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) E 4 A R 6 5 C A G 10 C, E D 1 A H 6 D.F Dave's...
For the following, draw the node network, perform the CPM calculations, mark the critical Path, and complete the table. IAAB 745 00 ABCDE Make possibility of rejection. Also show procurement activities CHAPTER 4 EXERCISES 1. For the following schedule, draw the node network, perform the CPM tions, mark the critical path, and complete the table. Activity Duration IPA ES EF LS LF TF FF В 8 B, C For the following schedule, draw the node network, perform the CPM tions,...
for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statistics 1. A project is shown by the following network. The durations of activities (in weeks) are indicated on the arrows. a. Identify all of the paths, compute the length of each, identify the critical path and the b. Determine...
10. Explain the following, and their relationships: ES, EF, LS, LF 11. What are the three variables taken into account when using probabilistic activity times? 10. Explain the following, and their relationships: ES, EF, LS, LF 11. What are the three variables taken into account when using probabilistic activity times?
5 & 17. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 5 with an imposed finish date of 26 and then 35 days. Activity Duration IPA ES EF LS LF TF FF A 6 - B 2 - C 9 - D 4 A, B E 7 B F 5 D G 10 D, E H 8 C, F, G I 3 C, G J 2...