4- Consider the (simplified) list of activities and predecessors that are involved in building a house: Description Predecess
0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Network diagram is following: Finish

Three are three paths in the network. These are:

A-B-D 18
A-B-C-G 26
A-B-E-F-G 26

Paths A-B-C-G and A-B-E-F-G have the longest duration. Therefore, these are the critical path.

Draw the table listing ES, LS, EF, LF and Slack time of each activity Earliest Start (ES) is calculated by forward pass metho

Activity Predecessor Normal Time ES LS EF LF Slack
A 5 0 0 5 5 0
B A 8 5 5 13 13 0
C B 10 13 13 23 23 0
D B 5 13 21 18 26 8
E B 4 13 13 17 17 0
F E 6 17 17 23 23 0
G C,F 3 23 23 26 26 0

Critical path can also be identified by 0 slack time in the above table.

Add a comment
Know the answer?
Add Answer to:
Operations Research 4- Consider the (simplified) list of activities and predecessors that are involved in building a house: Description Predecessors Duration (Days) Build foundation Activity Walls...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Activity Predecessors | Duration(days) A B | Description Build foundation Build walls and ceilings Build the...

    Activity Predecessors | Duration(days) A B | Description Build foundation Build walls and ceilings Build the roof Electrical wiring Install windows Put on siding Painting B B Ε CF Ι a) Draw the project diagram, and find the critical path, total duration, and total float and free float for every activity. b) Suppose you are expected to finish the project within 20 days. You find you have to hire more workers in order to shorten the total duration. Please find...

  • Q4. CPM Consider the following list of activities and predecessors. Activity ProcessorsDuration (...

    Q4. CPM Consider the following list of activities and predecessors. Activity ProcessorsDuration (days) Build foundation Build walls&ceilin Build roof Complete electrical wirin Put in windows Put on sidin Paint house C,F a)Draw the network diagram. Write down the LP to determine the completion time. b)Suppose that by hiring additional workers, the duration of each activity can be reduced. The costs per day of reducing the duration of the activities are given in the following table. Write down the LP to...

  • F: The activities in the following table describe the construction of a new house. Activity Predecessor(s)...

    F: The activities in the following table describe the construction of a new house. Activity Predecessor(s) Duration(days) A: Clear site B: Bring utilities to site Excavate D: Pour foundation E: Outside plumbing B, C Frame house D G: Do electric wiring H: Lay floor Lay roof F Inside plumbing E, H K: Shingling Outside sheathing insulation F.J M: Install windows and outside doors F Do brick work L, M 0: Insulate walls and ceiling GJ Cover walls and ceiling 0...

  • Describe the project network to build a house from the data below. Calculate the time and...

    Describe the project network to build a house from the data below. Calculate the time and critical path. Activity Description Predecessor Time (Days) A Clear the location - 1 B Bring the tool to the location - 2 C Conducting excavations A 1 D Pour the foundation C 2 E Plumbing installation from outside B, C 6 F Create a home frame D 10 G Installation of electric wire F 3 H Install the floor G 1 I Installing the...

  • Problem 15-7 Consider the following table of precedence relationships for a portion of a house building...

    Problem 15-7 Consider the following table of precedence relationships for a portion of a house building project: Task Duration Estimates Immediate Predecessor(s) A Prepare Site 3 days None B Install Rough Plumbing 2 days Prepare Site C Pour Concrete Foundation 3 days Install Rough Plumbing D Concrete Curing Time 4 days Pour Concrete Foundation E Preassemble Wall Frames 6 days None F Erect Wall Frames 2 days Preassemble WF, Cure Concrete G Install Roof 1 day Erect Wall Frames H...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT