Question

MANG471-002-24185 Operations Management Homework: Chapter 7 Score: 0.89 of 1 pt 2 of 5 (5 complete) % Problem 1 SA b. Calcula
ework: Chapter 7 89 of 1 pt 2 of 5(5 complete) blem 1 te the critical path for this project. al path is A-C-F-H-J and the pro
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Activity Time Predecessor Critical Path LS = LF-Time Calculation Value 1-1 A 7-4 A 7-6 EF = ES + Time Calculation Value 0+1 1Critical path: A-C-F-H-J Project Duration: 26 Days Activity Activity Time On critical Path Slack 3 N. 0 1 L 5 L

Add a comment
Know the answer?
Add Answer to:
MANG471-002-24185 Operations Management Homework: Chapter 7 Score: 0.89 of 1 pt 2 of 5 (5 complete)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Homework: Chapter 14 Material Requirements Planning Save Score: 0 of 1 pt 2 of 20 (1...

    Homework: Chapter 14 Material Requirements Planning Save Score: 0 of 1 pt 2 of 20 (1 complete) HW Score: 5%, 1 of 20 pts Problem 14.1 - Bookmatch Question Help You have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast 200 attendees. Assume that there is no inventory on hand of any of the items. Explode the bill of material. (Subscripts indicate the...

  • B. Determine the project’s critical path and duration.(this is number b wuestion) please answer t...

    b. Determine the project’s critical path and duration.(this is number b wuestion) please answer this two b and c questions Reliable Garage is completing production of the J2000 kit car. The following data are available for the project Activity Activity Time (days) Immediate Predecessor(s 10 D, E,G A-B-C-D-H 4 4 A-B-C-F-G-H b. Determine the pr A-B-C-E-H The critical path isand the project duration is I duration. day(s). (Enter your response as a whole number.) c. Calculate the slack for each...

  • The following is a table of activities associated with a project at Rafay Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what adivities each must precede Activity Duration (weeks) Precedes A (start) Fendi This exercise contains only parts and d. b) The activities on the critical path are c) The total project completion time for Rafay Ishlad's software firm is weeks. (Enter your response as a whole number) d) Determine the slack time for each of the activities. (Enter your...

  • Reliable Garoge is completing production of the J2000 kit car. The following data are available for the project ctivityActivity Time ldaysl Immediate redecessoris D. b. Dabaina tha projacts ccal pat...

    Reliable Garoge is completing production of the J2000 kit car. The following data are available for the project ctivityActivity Time ldaysl Immediate redecessoris D. b. Dabaina tha projacts ccal path and duration The critical psth is AB-CF-GH ad the project duration is 26 days). Enter your respunse as s whole number) b. Dctanmine the projects crttical path and durntion The crtical path ABCFGH and the project duration 26 dasi (Enter your respanee aswhove number) c. What is the slack for...

  • Reliable Garage is completing production of the J2000 kit car. The following data are available for...

    Reliable Garage is completing production of the J2000 kit car. The following data are available for the​ project:                                                                                      Activity Activity Time ​(day​s) Immediate​ Predecessor(s) A 3 − B 4 A C 5 B D 7 C E 6 C F 2 C G 4 F H 4 ​D, E, G Determine the​ project's critical path and duration. The critical path is A-B-C-D-H and the project duration is 23 day​(s). ​(Enter your response as a whole​ number.) c. What is...

  • Problem 5: For the given activity network, if there are 35 days required to complete the...

    Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...

  • Homework: Chapter 1 Homework Save Score: 0 of 1 pt 4 of 5 (3 complete) Score:...

    Homework: Chapter 1 Homework Save Score: 0 of 1 pt 4 of 5 (3 complete) Score: 60%, 3 of 5 pts Question Help 1.2.39 A class has 50 students. Use the second row of digits in the random number table below to select a simple random sample of three students. If the students are numbered 01 to 50, what are the numbers of the three students selected? Line/Column 31212 38862 41008 60689 98156 38417 92478 95304 06322 35843 19182 87025...

  • Activity Duration (days) Preceding activity A 3 - B 5 - C 2 B D 1...

    Activity Duration (days) Preceding activity A 3 - B 5 - C 2 B D 1 A E 6 A F 3 D G 3 C,E a. Construct a network diagram showing the critical path. b. Identify the earliest time the campaign can start. c. Identify the activities where there is float/slack time in the project, and calculate how much float/slack time there is. ** You should show all of your workings and state, clearly, any assumptions made.                                              

  • HomeWork! Chapter 8 Homework (Copy) SUV Score: 0.38 of 1 pt 7 of 9 (9 complete) HW Score: 89.05%, 8.01 of 9 pts S8-...

    HomeWork! Chapter 8 Homework (Copy) SUV Score: 0.38 of 1 pt 7 of 9 (9 complete) HW Score: 89.05%, 8.01 of 9 pts S8-11 (book/static) IE Question Help On December 1, Kyle Corporation accepted a 60-day, 9%, $12,000 note receivable from J. Michael in exchange for his account receivable Read the requirements Date Accounts and Explanation Debit Credit Choose from any list or enter any number in the input fields and then click Check Answer All parts showing Check Answer...

  • 23 of 55 (31 complete) | | Score: 53.67% Score:0 of 1 pt 1.7.33 Question Help...

    23 of 55 (31 complete) | | Score: 53.67% Score:0 of 1 pt 1.7.33 Question Help * The length of a rectangle is 4 meters less than twice the width. If the area of the rectangle is 336 square meters, find the dimensions The width ismeters The length ismeters Enter your answer in the edit fields and then click Check Answer All parts showing Clear All Check An

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT