Question

Reliable Garoge is completing production of the J2000 kit car. The following data are available for the project ctivityActivi

b. Dctanmine the projects crttical path and durntion The crtical path ABCFGH and the project duration 26 dasi (Enter your res

Reliable Garoge is completing production of the J2000 kit car. The following data are available for the project ctivityActivity Time ldaysl Immediate redecessoris D. b. Dabaina tha projacts ccal path and duration The critical psth is AB-CF-GH ad the project duration is 26 days). Enter your respunse as s whole number)
b. Dctanmine the projects crttical path and durntion The crtical path ABCFGH and the project duration 26 dasi (Enter your respanee aswhove number) c. What is the slack for each activity? days your answer in the edt felds and then cick Check Anewer
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Network Diagram -

media%2F892%2F8924e174-8315-40b4-b9a9-ac

Hence, (d) is the correct answer

Network paths and their duration are -

ABCDH --> 3+4+4+3+4 = 18
ABCEH --> 3+4+4+7+4 = 22
ABCFGH --> 3+4+4+7+4+4 = 26

Hence, critical path is ABCFGH and project duration = 26 days

(c)

Earliest Start (ES) = the earliest time when the activity can begin

Earliest Finish (EF) = ES + Activity Duration

Latest Finish (LF) = the latest time by whenthe activity can be finished without changing the project completion duration

Latest Start (LS) = LF - Activity Duration

Slack = LS-ES = LF-EF

Computing using the above gives us the below -

Activity Precedes Activity Time ES EF LS LF Slack
A - 3 0 3 0 3 0
B A 4 3 7 3 7 0
C B 4 7 11 7 11 0
D C 3 11 14 19 22 8
E C 7 11 18 15 22 4
F C 7 11 18 11 18 0
G F 4 18 22 18 22 0
H D, E, G 4 22 26 22 26 0

Hence, slack for D = 8 and slack for E = 4 days

Slack for all the other activities = 0 days

Slack for activities on critical path is always 0

Add a comment
Know the answer?
Add Answer to:
Reliable Garoge is completing production of the J2000 kit car. The following data are available for the project ctivityActivity Time ldaysl Immediate redecessoris D. b. Dabaina tha projacts ccal pat...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Reliable Garage is completing production of the J2000 kit car. The following data are available for...

    Reliable Garage is completing production of the J2000 kit car. The following data are available for the​ project:                                                                                      Activity Activity Time ​(day​s) Immediate​ Predecessor(s) A 3 − B 4 A C 5 B D 7 C E 6 C F 2 C G 4 F H 4 ​D, E, G Determine the​ project's critical path and duration. The critical path is A-B-C-D-H and the project duration is 23 day​(s). ​(Enter your response as a whole​ number.) c. What is...

  • B. Determine the project’s critical path and duration.(this is number b wuestion) please answer t...

    b. Determine the project’s critical path and duration.(this is number b wuestion) please answer this two b and c questions Reliable Garage is completing production of the J2000 kit car. The following data are available for the project Activity Activity Time (days) Immediate Predecessor(s 10 D, E,G A-B-C-D-H 4 4 A-B-C-F-G-H b. Determine the pr A-B-C-E-H The critical path isand the project duration is I duration. day(s). (Enter your response as a whole number.) c. Calculate the slack for each...

  • Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b....

    Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b. A-B-C-F C. A-B-E-F Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) c. Which of these activities should the project manager track most closely? A. A-B-E-F b. A-D-E-F c. A-B-C-F Problem 15.6 Task Duration Estimate (in Days) Immediate Predecessors None А B A B and D E and C Earliest...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT