Task |
Date |
Budgeted Amount |
Build forms |
April 1 |
$10,000 |
Pour foundation |
April 1 |
$50,000 |
May 1 |
$100,000 |
|
Frame walls |
May 1 |
$30,000 |
June 1 |
$30,000 |
|
Remaining tasks |
July 1 and beyond |
$500,000 |
As on May 1, the below ratios are calculated:
SV = Earned Value - Planned Value
SPI = Earned value/Planned value
Cost Performance Index = (Earned Value) / (Actual Cost)
Cost Variance = Budgeted cost - Actual cost
Planned value-
% completion as per Budgets = Budgeted cost as on May 1 / Total project cost = 190000/720000 = 0.263889 =~0.26
Budgeted cost * % completion as per Budgets = 190000*0.26 = 50,139
Earned value -
% completion as per Actuals = Actual cost as on May 1 / Total project cost = 160000/720000 = 0.22
Budgeted cost * % completion as per Actuals = 190000*0.22 = 42,222
SV = 42,222 - 50,139 = -7917 (behind schedule)
SPI = 42,222/50,139 = 0.84
CPI = 42,222/1,60,000 = 0.26
Task Date Budgeted Amount Build forms April 1 $10,000 Pour foundation April 1 $50,000 May 1...
Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....
Earned Value Management (EVM) Following is a cost/schedule status report (C/SSR), a document that is generated each month. It demonstrates the cost and schedule status of a project at a given moment in time. Answer the questions associated with the accompanying C/SSR after reading the appropriate sections on earned value in Managing Projects in Organizations, The New Project Management, and A Guide to the Project Management Body of Knowledge (PMBOK). Task Budget Task begun Task ended Actual Cost A 30,000...
2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...
3) You are in charge of the Aurora Project. Given the following project network, baseline, and status information, (40 Points) B DI OA E • Develop status reports for periods 7 and complete the performance indices table. . Calculate the EAC, and VAC. Based on your data, what is the current status of the project? At completion? Rule 1 0% complete 2-50/50 3 - 0/100 ID LF SL Schedule information Total 0 1 2 PV 3 4 30 5 6...
I need help with the attached assignment. I attached the question and completed assigment. I just need help with answering one more question which is which is: Discuss a strategy that you would use to communicate the status of the project to stakeholders? Project Monitoring and Control Assignment Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft...