Question

You are the project manager for a power plant project. You have completed project initiation activities...

You are the project manager for a power plant project. You have completed project initiation activities and you are now creating a document that describes processes to document the scope, decompose deliverables into work packages, verify that all work is complete and manage changes to the baseline. What process plan would you choose to perform?

A. Develop project management plan

B. Develop project management life cycle

C. Develop WBS and define scope

D. Develop project charter

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer : A. Develop project management plan

The only plans given in the option is project management plan. Project management plan comprises of other sub plans which cover fhe content for successfully executing the project. The activities given in question comprise of activities for execution of the project.

Develop project charter is carried out in initiation phase. There is no process like Develop project management life cycle.

Develop WBS and define scope doesn't cover management of changes to baseline. Hence, Develop Project management plan is the answer.

Add a comment
Know the answer?
Add Answer to:
You are the project manager for a power plant project. You have completed project initiation activities...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You were offered an opportunity to work as a project manager at one of these institutions:...

    You were offered an opportunity to work as a project manager at one of these institutions: • AUST Hotel Dicu Red Cross • Dar Al Aytam You first task is to come up with the idea of a project that hasn't been already done by your institution Write a SOW or a project charter for your project. This must include but not limited to: Detailed project goals, objectives, requirements, characteristics, project product deliverables, assumptions, and constraints. Assignment Instructions: Work Breakdown...

  • Assignment Details Scenario You have been asked to be the project manager for the development of...

    Assignment Details Scenario You have been asked to be the project manager for the development of an information technology (IT) project. The system to be developed will allow a large company to coordinate and maintain records of the professional development of its employees. The company has over 30,000 employees who are located in four sites: Florida, Colorado, Illinois, and Texas. The system needs to allow employees to locate and schedule professional development activities that are relevant to their positions. Sophisticated...

  • 1) "Once you have identified all of the stakeholders, it is important to determine which group...

    1) "Once you have identified all of the stakeholders, it is important to determine which group of stakeholders holds the most power and which group may have the greatest impact in the overall outcome of the project. " a) true b) false 2) You are leading an international team and you are considering how this might impact your communications and decision making processes as a team. Your goal is to _______________. a) adapt the work processes to cope with the...

  • !!!Only Project 2 need to be answered!!! Project Report 1 Once the business case has been approved, you need to make a...

    !!!Only Project 2 need to be answered!!! Project Report 1 Once the business case has been approved, you need to make a project plan showing each task. Assume you are a project manager to lead your team to acquire an additional delivery van for the company. Please find the details below. The current month is January. Activity (What is to be done?) Objective (Why will we do it?) Resources (Where will it be done?) Procedures (How will it be done?)...

  • Project Description: Student groups will select an industrial project to be developed throughout the semester. Students...

    Project Description: Student groups will select an industrial project to be developed throughout the semester. Students groups will select an appropriate project and define measurable project objectives and requirements. A project plan and schedule will be generated as well as resources allocated to accomplish project objectives. Prepare a group project for the class. Use as your model one of the following Construction project Software development project Events management project ( e.g. Awards banquet) New product development Project Components: Using the...

  • The project team you are working with is doing the work of obtaining formal stakeholders’ acceptance...

    The project team you are working with is doing the work of obtaining formal stakeholders’ acceptance of the completed project and associated deliverables. Each deliverable is reviewed to check that it has been completed satisfactorily. What is this process called? A. Validate Scope B. Define Scope C. Control Scope D. Plan Scope Management

  • Work Breakdown Structure (WBS) Based on your understanding of project planning and budgeting, express your views...

    Work Breakdown Structure (WBS) Based on your understanding of project planning and budgeting, express your views on the following: What is scope planning and scope creeping? What are some of the ways to avoid problems and manage scope correctly? You've been assigned the project of setting up a LAN with a broadband connection in your office. You need to provide internet connectivity for web browsing to all users. All the computers have Microsoft Windows 7 software installed. Based on your...

  • Module Three covers refining your project schedule and fine-tuning resources. Table 1-1: Project ...

    Table 1.1 Module Three covers refining your project schedule and fine-tuning resources. Table 1-1: Project Management Process Group and Knowledge Area Mapping (PMBOK Guide® on page 556) provides you with a very specific guideline concerning what task is due for each knowledge area throughout the five projec management process groups. As you can determine from Table 1-1, a large majority of the tasks are complete during the planning process group Describe and explain how sound industry standards or best practices...

  • 9. A project manager spent some days to create a multi-page document, which he called project...

    9. A project manager spent some days to create a multi-page document, which he called project charter. The document should have been issued by the project sponsor.The sponsor found the document outsized and asked for a condensed document. Which of the following is usually not an element of the project charter? a. The authority level of the project manager b. Detailed control account and work package descriptions C. The business need that the project was undertaken to address d. High-level...

  • A) We require you to describe how you would use project management tools to develop and implement...

    A) We require you to describe how you would use project management tools to develop and implement a project plan. Discuss at least 3 tools from below: project management software Gantt and bar charts critical path method (CPM) Program Evaluation Review Technique charts (PERT) cost schedule control system life cycle cost analysis logistics support analysis spreadsheets technical resources B) Whilst completing your project plan, ensure you include the following: deliverables   work breakdown budget and allocation of resources      timelines risk management...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT