Question

Use this info for questions 9 through 13. Chucks Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract

2. What is the cost of the third crash?

3.What is the cost of the fifth crash?

4.What is the total cost of all crashes that should be done to minimize costs?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

diagram Activity On Node te=34 L=34 Ez240 EM Istart 7 7 Il 2240 X Ek=1% 4K=18 EM=22 LM322 0 - 10 u Lsco 6 Eps 27 m5 Lpz2 I CHNow the new path will be JKM P.) asz lo +8+3+ 5+7 +6=39 weeks & another critical path is ) د N داد و 7 د و 10+5+6 + 5 + 7 + 6So, that New tofpath will be JKM porsz= lo + 8 + 2 +5+6+6 = 37 weeks JLAN+ Pa+2 lo +5+5+5+6+6 = {F weeks additional cost dueNext crash to the activity K&L by one week & additional cost is (45+60)=105 JAKAMAP a» 10+6+2 +5+6 +5=34 weeks JLNA PAG-2 toNo. of crashing Crashing without (crashing activity week Gashed Cost 20 total=40 7 39 38 H 70 1 37 H I Man . 3 (20+55)=75 95A thumbs up, pls !!

Add a comment
Know the answer?
Add Answer to:
2. What is the cost of the third crash? 3.What is the cost of the fifth...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Chuck’s Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious...

    Chuck’s Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious New York real estate developer, Mr. T. Relevant data on the project are shown below. The complication is that Mr. T wants delivery in 30 weeks or he will impose a penalty of $250 for each week his yacht is late. Determine the lowest cost plan for crashing this project. Note: All numbers are in thousands, but keep them that way (i.e., don't enter...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • I just need the last two parts of the question answered. PM.66 Real estate developer Russell Call was working with a fe...

    I just need the last two parts of the question answered. PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) $1,050 $2,000 $2,560 $2,600 $1,300 $2,600 $2,200 $1,800 $2,400 4 $4,200 $5,540 $2,050 4...

  • For the following project: Normal Time Crash Time Normal Cost Crash Cost Immediate (weeks 4. Activity...

    For the following project: Normal Time Crash Time Normal Cost Crash Cost Immediate (weeks 4. Activity Predecessor (weeks) $2,600 $2,800 $2,000 $2,200 $500 $2,300 $900 $3,000 $500 $2,600 $1,200 $4,200 $1,400$2,000 4 D, E How long will the project take? What is the total cost to complete the project in normal time? If the project is to be shortened by 1 week, which activity will be reduced and how much will the cost be increased? What is the maximum time...

  • Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None...

    Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None None B Cost Normal Crash 1000 1600 2000 2700 300 300 1300 1600 2 1 С 1 1 D A 7 3 E 6 3 B с 1000 5000 F 2 850 4000 1500 NA G D. E 4 2000 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity should you...

  • Assume that Indirect project costs are $75,000 per week Crash the network (one week at a time) un...

    Assume that Indirect project costs are $75,000 per week Crash the network (one week at a time) until you reach the optimum cost-time point. Document your crashes clearly. d. What is the project length at the optimum point? MGMT 4143 Ch 9 HomeworkDue 3/27, 9pm NOTE due date is changed All work must be done in Excel Put each problem on a separate worksheet tab Label the worksheet tabs, put your name on each worksheet. Note: Crash the networks as...

  • Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3...

    Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3 4 2 1 3 Normal Time (days) 6 8 4 3 7 5 3 6 7 10 10 Dr. John Watage, deputy director of the family planning Research Center in Nigeria's Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new...

  • just need 2 and 3 Southwestern University (A) Southwester Unity Swage wat AL dom ACTIVE Bonde...

    just need 2 and 3 Southwestern University (A) Southwester Unity Swage wat AL dom ACTIVE Bonde . One of a demandej ad With dance w to face the head on Auch cal armwrestling and some seriously Wisme president of Southwestern University, decision to expand the capacity at Adding thods of all, including of boxes, would not please everyone. The argued them for a festa di un tory for his players and a paleta office app the couch of a future...

  • The administration of President Barack Obama has made Patient Protection and Affordable Care Act, often called...

    The administration of President Barack Obama has made Patient Protection and Affordable Care Act, often called “Obamacare”, its chief domestic accomplishment and the centerpiece of Obama’s legacy. Essential to Obama’s health care reform plan is Healthcare.gov, a health insurance exchange Web site that facilitates the sale of private health insurance plans to U.S. residents, assists people eligible to sign up for Medicaid, and has a separate marketplace for small businesses. The site allows users to compare prices on health insurance...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT