Question

Assume that Indirect project costs are $75,000 per week Crash the network (one week at a time) until you reach the optimum cost-time point. Document your crashes clearly. d. What is the project length at the optimum point?

MGMT 4143 Ch 9 HomeworkDue 3/27, 9pm NOTE due date is changed All work must be done in Excel Put each problem on a separate w

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Step 1: Network Diagram (Activity on Node) is as follows Step 2: Draw the table listing Max crash time and Crash cost per uni

Step 4: Project Crashing using least cost method 1. Identify and list the various alternative paths through the network and t

a) Under normal conditions, earliest project completion time = 24 weeks

b) Critical path is: A-C-E-F-G-H-J

c) Total direct cost = 745 ($000)

d) Project length at optimum point = 21 weeks

e) Total project cost at the optimum point = 2440 ($000) (this is reduced after crashing from original total project cost of 2545)

Add a comment
Know the answer?
Add Answer to:
Assume that Indirect project costs are $75,000 per week Crash the network (one week at a time) un...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 narl Case Study A Table 1 below contains activities associated with a...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...

  • For the project outlined on the following table, (a) draw a network diagram (arrow or PDM,...

    For the project outlined on the following table, (a) draw a network diagram (arrow or PDM, as you prefer), and (b) identify the critical path and duration. (c) Identify the task(s) you would crash and the incremental cost to reduce project duration by (i) one week; (ii) a second week; (iii) a third week. Duration (Weeks) Cost (Dollars) Task Follows Task(s) Normal Crash Normal Crash (Start) (Start) A, B B C D uun $500 400 600 $600 450 750 550...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • 02:03:17 Question No: 03 If the indirect costs for each duration are $280 for 27 weeks,...

    02:03:17 Question No: 03 If the indirect costs for each duration are $280 for 27 weeks, $240 1or 26 weeks, 5190 tox 25 weeks, 5140 1x 24 weeks 30 ta 7 wees optimum cost-time schedule? The client offers you $10 for every week you shorten the project tom your original network. Wordt you the Crash Time Activity Crush Cost ID (Slopes A 80 B 30 с 40 D 100 F 30 5 11 15 2 50 100 Total Dromid-1300 Time...

  • Q.3. Assume the network and data that follow. Compute the total direct cost for each project...

    Q.3. Assume the network and data that follow. Compute the total direct cost for each project duration. If the indirect costs for each project duration are S410 (19 time units), S360 (18), S310 (17), and $260 (16), compute the total project cost for each duration. What is the optimum cost-time schedule for the project? What is this cost? Activity Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost 20 60 50 60 70 50 100 90 50 S470 10...

  • The table below defines the activities and the normal time duration for each activities within a...

    The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project. Table 1: The time-cost information for the activities Activity Normal Completion Time (weeks) Immediate Predecessor Crash Time (weeks) Normal cost for activities Crash cost for activities/week A 2 - 1 1200 400 B 3 - 1 1400 500 C...

  • Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity...

    Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in Table 1. If the indirect costs for each duration is as follows, compute the direct and total cost for each duration. What is the optimum cost-time schedule? Indirect cost 27 weeks – RM 350 26 weeks – RM 270 25 weeks – RM 160 24 weeks – RM 100 12 weeks – RM 70 (12...

  • HOMEWORK ASSIGNMENT FOR PROJECT MANAGEMENT 13. An automation project has the following activities and related data Time (weeks)Crash Immed. Maximum Activity Prede- Opti- Most Cost/week Crashable...

    HOMEWORK ASSIGNMENT FOR PROJECT MANAGEMENT 13. An automation project has the following activities and related data Time (weeks)Crash Immed. Maximum Activity Prede- Opti- Most Cost/week Crashable Mean Varice cessors mistic (a) Likely (m) mistic (c (S1000) Weeks E(t) V(t) C A 5 D A 4 E B1 F B1 G C,D,E 2 6 6 HF2 12 15 3 13a. (5 points) Compute the mean and variance of each activity and record them on the table above. 13b. (5 points) Develop...

  • Nomal Crash Nomal Crash Predecessors Time Cost cost MCA CC-NC cost/week Successors Start Start 39600 13600 8 7000 7800 6 9300 11300 3600, 6-0 1087009100 45500 7900 1600 3600 5100 7200 12 12 13 A...

    Nomal Crash Nomal Crash Predecessors Time Cost cost MCA CC-NC cost/week Successors Start Start 39600 13600 8 7000 7800 6 9300 11300 3600, 6-0 1087009100 45500 7900 1600 3600 5100 7200 12 12 13 A, B 14 D, F 1310 15 17 18 Start time Actual 20 Activity Crash time duration ES 23 24 26 27 28 29 Completion ime Nomal project cost Cost of crashing - Total cost 34 Sheet1 1. This problem must be done in Excel. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT