02:03:17 Question No: 03 If the indirect costs for each duration are $280 for 27 weeks,...
Assume that Indirect project costs are $75,000 per week Crash the network (one week at a time) until you reach the optimum cost-time point. Document your crashes clearly. d. What is the project length at the optimum point? MGMT 4143 Ch 9 HomeworkDue 3/27, 9pm NOTE due date is changed All work must be done in Excel Put each problem on a separate worksheet tab Label the worksheet tabs, put your name on each worksheet. Note: Crash the networks as...
Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in Table 1. If the indirect costs for each duration is as follows, compute the direct and total cost for each duration. What is the optimum cost-time schedule? Indirect cost 27 weeks – RM 350 26 weeks – RM 270 25 weeks – RM 160 24 weeks – RM 100 12 weeks – RM 70 (12...
You are the project manager for preparing a yacht for the Bond Blue Water Classic yacht race. Based on your experience and the data to hand you have prepared the following WBS with its associated normal and crash costing. Note: Indirect costs are not to be considered in this problem. The project is proposed to commence on 1 August 2018. You can ignore the impact of any public holidays during the project. You are required to: a) Create an AON...