Question

Chuck’s Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious...

Chuck’s Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious New York real estate developer, Mr. T. Relevant data on the project are shown below. The complication is that Mr. T wants delivery in 30 weeks or he will impose a penalty of $250 for each week his yacht is late. Determine the lowest cost plan for crashing this project.

Note: All numbers are in thousands, but keep them that way (i.e., don't enter the last three zeros).

1: What is the expected project duration before crashing any activities?

2: What is the cost of the second crash?

3: What is the cost of the seventh crash?

4: What is the total cost of all crashes that should be done to minimize costs?

5: How much should be spent on penalties?

Activity Immediate Predecessor Normal Time (weeks) # Possible Crashes Crash Cost Per Week
J - 10 1 175
K J 8 2 45
L J 5 2 60
M K 4 2 20
N L 6 2 55
P M, N 5 2 265
Q P 7 1 70
Y P 8 2 35
Z Q 6 1 95

Note: If you want a thumbs up, please answer all five questions above. Thanks

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

Initial State 一、 | Critical? 60 | Project paths | |-K-M-P-Y | D-K-M-P-Q-Z | |-L-N-P-Q-Z | J-L-N-P-Ý | Duration 35 40 39 34 .

So, the expected project duration before crashing any activities = 40 weeks

2.

Step-1: Crash M by 1 week Duration Critical? $20 Project paths J-K-M-P-Y J-K-M-P-Q-Z J-L-N-P-Q-Z J-L-N-P-Y Crash cost Penal

Step-2: Crash Q by 1 week Critical? Project paths J-K-M-P-Y J-K-M-P-Q-Z J-L-N-P-Q-Z J-L-N-P-Y Duration 34 38 38 34 Crash co

So, the cost of the second crash = Cost of crashing 'Q' by one week = $70

3.

Step-3: Crash M and N both by 1 week Duration | Critical? Project paths J-K-M-P-Y J-K-M-P-Q-Z J-L-N-P-Q-Z J-L-N-P-Y Crash

Step-4: Crash Z by 1 week Duration Critical? Project paths J-K-M-P-Y J-K-M-P-Q- Z J-L-N-P-Q-Z J-L-N-P-Y Crash cost Penalty

Step-5: Crash K and N both by 1 week Duration | Critical? Project paths J-K-M-P-Y J-K-M-P-Q-Z J-L-N-P-Q-Z J-L-N-P-Y Crash

Step-6: Crash K and L both by 1 week Duration Critical? Project paths J-K-M-P-Y J-K-M-P-Q-Z J-L-N-P-Q-Z J-L-N-P-Y Crash c

Step-7: Crash by 1 week Duration Critical? Project paths J-K-M-P-Y J-K-M-P-Q-Z J-L-N-P-Q-Z J-L-N-P-Y Crash cost Penalty Tot

So, the cost of the seventh crash = cost of crashing 'J' by 1 week = $175

4.

Step-8: Crash P by 1 week 6 x Duration Critical? Project paths J-K-M-P-Y J-K-M-P-Q-Z J-L-N-P-Q-Z J-L-N-P-Y Crash cost Penal

Note that in step-8, the total cost increases from what it was in step-7. So, step-7 is the optimality point.

So, the total cost of all crashes at this point = $640.

5.

At this point (i.e. at step-7), the penalty paid was = $750

Add a comment
Know the answer?
Add Answer to:
Chuck’s Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. What is the cost of the third crash? 3.What is the cost of the fifth...

    2. What is the cost of the third crash? 3.What is the cost of the fifth crash? 4.What is the total cost of all crashes that should be done to minimize costs? Use this info for questions 9 through 13. Chuck's Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious New York real estate developer, Mr. T. Relevant data on the project are shown below. The complication is that Mr. T wants delivery in...

  • Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,000...

    Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,0003,300B...648,0009,000CA114,0004,000      DA543,5004,000EB434,7505,500FC222,0002,000      GD114,0004,000HD,F323,5003,750IE,G323,0004,250JE215,0007,000Since no indirect cost nor penalty cost information is offered, please consider the schedule and crash cost issues only.1. Using Table of Crashing Decision, what is the earliest completion time of this project if normal times are used for all activities?A. fewer than 13 weeks; B. 13 weeks; C. 14 weeks; D. more than 14 weeks2. Using Table of Crashing Decision, what is the minimum time schedule for this project?A. fewer than 8 weeks; B. 8...

  • You are the project manager for preparing a yacht for the Bond Blue Water Classic yacht...

    You are the project manager for preparing a yacht for the Bond Blue Water Classic yacht race. Based on your experience and the data to hand you have prepared the following WBS with its associated normal and crash costing. Note: Indirect costs are not to be considered in this problem. The project is proposed to commence on 1 August 2018. You can ignore the impact of any public holidays during the project. You are required to: a) Create an AON...

  • The administration of President Barack Obama has made Patient Protection and Affordable Care Act, often called...

    The administration of President Barack Obama has made Patient Protection and Affordable Care Act, often called “Obamacare”, its chief domestic accomplishment and the centerpiece of Obama’s legacy. Essential to Obama’s health care reform plan is Healthcare.gov, a health insurance exchange Web site that facilitates the sale of private health insurance plans to U.S. residents, assists people eligible to sign up for Medicaid, and has a separate marketplace for small businesses. The site allows users to compare prices on health insurance...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT