Question

5. A competitor of Kozar International, Inc. has begun marketing a new instant developing film project. Kozar has had a simil
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:
Expected time of each activity,

Activity to tm tp te=to+4⋅tm+tp/6 σ2=(tp-to/6)2
A 5 7 8 6.83 0.25
B 6 8 12 8.33 1
C 3 4 5 4 0.11
D 11 17 25 17.33 5.44
E 8 10 12 10 0.44
F 3 4 5 4 0.11
G 4 8 9 7.5 0.69
H 5 7 9 7 0.44

The earliest and latest expected time for each activity is calculated by considering the expected time te

Activity Immediate Predecessors Duration
A - 6.83
B - 8.33
C - 4
D A 17.33
E B 10
F C,E 4
G D,E 7.5
H F 7

Edge and it's preceded and succeeded node

Edge Node1 → Node2
A 1→2
B 1→3
C 1→4
D 2→5
E 3→6
F 4→7
G 5→8
d 6→4
d 6→5
H 7→8

The network diagram for the project, along with activity time, is

2 D(17.33) 5 G(7.5) 8 A(6.83) d(0) H(7) B(8.33) 3 E(10) 6 H(7) C(4) do) H(7) C(4) C(4) 4 F(4) 7

Forward Pass Method
E1=0

E2=E1+t1,2 [t1,2=A=6.83]=0+6.83=6.83

E3=E1+t1,3 [t1,3=B=8.33]=0+8.33=8.33

E4=Max{Ei+ti,4}[i=1,6]

=Max{E1+t1,4;E6+t6,4}

=Max{0+4;18.33+0}

=Max{4;18.33}

=18.33

E5=Max{Ei+ti,5}[i=2,6]

=Max{E2+t2,5;E6+t6,5}

=Max{6.83+17.33;18.33+0}

=Max{24.16;18.33}

=24.16

E6=E3+t3,6 [t3,6=E=10]=8.33+10=18.33

E7=E4+t4,7 [t4,7=F=4]=18.33+4=22.33

E8=Max{Ei+ti,8}[i=5,7]

=Max{E5+t5,8;E7+t7,8}

=Max{24.16+7.5;22.33+7}

=Max{31.66;29.33}

=31.66


Backward Pass Method
L8=E8=31.66

L7=L8-t7,8 [t7,8=H=7]=31.66-7=24.66

L6=Min{Lj-t6,j}[j=5,4]

=Min{L5-t6,5;L4-t6,4}

=Min{24.16-0;20.66-0}

=Min{24.16;20.66}

=20.66

L5=L8-t5,8 [t5,8=G=7.5]=31.66-7.5=24.16

L4=L7-t4,7 [t4,7=F=4]=24.66-4=20.66

L3=L6-t3,6 [t3,6=E=10]=20.66-10=21.66

L2=L5-t2,5 [t2,5=D=17.33]=24.16-17.33=6.83

L1=Min{Lj-t1,j}[j=4,3,2]

=Min{L4-t1,4;L3-t1,3;L2-t1,2}

=Min{20.66-4;21.66-8.33;6.83-6.83}

=Min{16.66;13.33;0}

=0

The critical path in the network diagram has been shown. This has been done by double lines by joining all those events where E-values and L-values are equal.
The critical path of the project is : 1-2-5-8 and critical activities are A,D,G

The total project time is 31.66
The network diagram for the project, along with E-values and L-values, is

G(7.5) 8 Eg = 31.66 Lg = 31.66 2 D(17.33) 5 E2 = 6.83 E5 = 24.16 22 = 6.83 L = 24.16 d(0) A(6.83) H(7) 1 B(8.33) 6 F = 18.33

Please make a note that Revised Chegg Guidelines seriously restrict us in answering only one question! Violating them will get my account suspended. However, I've answered first question so that you would rate this answer positively. So please understand and rate this answer with thumbs up kindly. It is a gesture that shows you support me. Thank you! I PLEASE BEG YOU, DON'T DISLIKE! WE ARE JUST FOLLOWING OUR GUIDELINES

Add a comment
Know the answer?
Add Answer to:
5. A competitor of Kozar International, Inc. has begun marketing a new instant developing film project....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT