Solution:
Expected time of each activity,
Activity | to | tm | tp | te=to+4⋅tm+tp/6 | σ2=(tp-to/6)2 |
A | 5 | 7 | 8 | 6.83 | 0.25 |
B | 6 | 8 | 12 | 8.33 | 1 |
C | 3 | 4 | 5 | 4 | 0.11 |
D | 11 | 17 | 25 | 17.33 | 5.44 |
E | 8 | 10 | 12 | 10 | 0.44 |
F | 3 | 4 | 5 | 4 | 0.11 |
G | 4 | 8 | 9 | 7.5 | 0.69 |
H | 5 | 7 | 9 | 7 | 0.44 |
The earliest and latest expected time for each activity is calculated by considering the expected time te
Activity | Immediate Predecessors | Duration |
A | - | 6.83 |
B | - | 8.33 |
C | - | 4 |
D | A | 17.33 |
E | B | 10 |
F | C,E | 4 |
G | D,E | 7.5 |
H | F | 7 |
Edge and it's preceded and succeeded node
Edge | Node1 → Node2 |
A | 1→2 |
B | 1→3 |
C | 1→4 |
D | 2→5 |
E | 3→6 |
F | 4→7 |
G | 5→8 |
d | 6→4 |
d | 6→5 |
H | 7→8 |
The network diagram for the project, along with activity time, is
Forward Pass Method
E1=0
E2=E1+t1,2 [t1,2=A=6.83]=0+6.83=6.83
E3=E1+t1,3 [t1,3=B=8.33]=0+8.33=8.33
E4=Max{Ei+ti,4}[i=1,6]
=Max{E1+t1,4;E6+t6,4}
=Max{0+4;18.33+0}
=Max{4;18.33}
=18.33
E5=Max{Ei+ti,5}[i=2,6]
=Max{E2+t2,5;E6+t6,5}
=Max{6.83+17.33;18.33+0}
=Max{24.16;18.33}
=24.16
E6=E3+t3,6 [t3,6=E=10]=8.33+10=18.33
E7=E4+t4,7 [t4,7=F=4]=18.33+4=22.33
E8=Max{Ei+ti,8}[i=5,7]
=Max{E5+t5,8;E7+t7,8}
=Max{24.16+7.5;22.33+7}
=Max{31.66;29.33}
=31.66
Backward Pass Method
L8=E8=31.66
L7=L8-t7,8 [t7,8=H=7]=31.66-7=24.66
L6=Min{Lj-t6,j}[j=5,4]
=Min{L5-t6,5;L4-t6,4}
=Min{24.16-0;20.66-0}
=Min{24.16;20.66}
=20.66
L5=L8-t5,8 [t5,8=G=7.5]=31.66-7.5=24.16
L4=L7-t4,7 [t4,7=F=4]=24.66-4=20.66
L3=L6-t3,6 [t3,6=E=10]=20.66-10=21.66
L2=L5-t2,5 [t2,5=D=17.33]=24.16-17.33=6.83
L1=Min{Lj-t1,j}[j=4,3,2]
=Min{L4-t1,4;L3-t1,3;L2-t1,2}
=Min{20.66-4;21.66-8.33;6.83-6.83}
=Min{16.66;13.33;0}
=0
The critical path in the network diagram has been shown. This has
been done by double lines by joining all those events where
E-values and L-values are equal.
The critical path of the project is : 1-2-5-8 and critical
activities are A,D,G
The total project time is 31.66
The network diagram for the project, along with E-values and
L-values, is
Please make a note that Revised Chegg Guidelines seriously restrict us in answering only one question! Violating them will get my account suspended. However, I've answered first question so that you would rate this answer positively. So please understand and rate this answer with thumbs up kindly. It is a gesture that shows you support me. Thank you! I PLEASE BEG YOU, DON'T DISLIKE! WE ARE JUST FOLLOWING OUR GUIDELINES
5. A competitor of Kozar International, Inc. has begun marketing a new instant developing film project....
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....
Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. Calculate the slack for each activity. Identify all activities on the Critical Path. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score). Activity A 8 с D E...
A small software development project has eight major activities. The times are estimated and provided in the table below: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 5 -- B 5 7 9 -- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6 10 F Answer the following questions based on above table 1-2...
You are responsible for managing a project with the following activities (all times are given in weeks): Optimistic Most Likely Pessimistic Immediate Time Predecessor(s) Time Activity Time 4 C, D D, E 12 4 8 6 4 What is the expected time of completion of the project? (weeks) (Include 1 decimal place, e.g.,3.1.) abs What is the probability that the project will be completed in 24 weeks or less? (Provide ab 2 decimal places, no 90 sign, e.g., 2.12 for...
Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...
(15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7 9 B A 2 4 6 C A 6 9 9 D B, C 5 5 5 E C 2 5 9 F D, E 3 3 6 Use both the longest path method and ES/EF; LS/LF method for the following questions (e) What are the slack values for non-critical activities? (4 points) (f) What is the probability that the project will be...
5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predecessor of C. The duration estimate for activity A, B and C is shown in the following table. Fill the table with mean duration, standard deviation, and variance for activities and the whole project (critical path). Determine what is the probability of completing this project within 80 days? (10 points) Activity Optimistic Pessimistic Most likely Mean Standard Variance deviation duration...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
uction needs to complete construction of Shopping Mall project, which is start in August. They are concerned with the completion time. Some of the ighly unreliable. List of activities and their optimistic, pessimistic, and most ion times in weeks) are given in following table: Optimistic Most Likely Pessimistic E(t) 3 5 9 13 11 0.1111 2.7778 7 Immediate Predecessor(s) None A None None AC D, E D, E F G F DF 2 6 9 5 10 6 5 2...
QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...