Question

Sox Engineering designs and constructs air conditioning and heating​ (HVAC) systems for hospitals and clinics. Currently...

Sox Engineering designs and constructs air conditioning and heating​ (HVAC) systems for hospitals and clinics. Currently the​ company's staff is overloaded with design work. There is a major design project due in

99

weeks. The penalty for completing the design late is

​$14 comma 00014,000

per​ week, since any delay will cause the facility to open later than​ anticipated, and cost the client significant revenue. If the company uses its inside engineers to complete the​ design, it will have to pay them overtime for all work. Sox has estimated that it will cost

​$11 comma 00011,000

per week​ (wages and​ overhead), including late​ weeks, to have company engineers complete the design. Sox is also considering having an outside engineering firm do the design. A bid of

​$90 comma 00090,000

has been received for the completed design. Yet another option for completing the design is to conduct a joint design by having a third engineering company complete all electromechanical components of the design at a cost of

​$60 comma 00060,000.

Sox would then complete the rest of the design and control systems at an estimated cost of

​$32 comma 00032,000.

Sox has estimated the following probabilities of completing the project within various time frames when using each of the three options. Those estimates are shown in the following​ table:

Probability of Completing the Design

Option

On Time

One Week Late

Two Weeks Late

Three Weeks Late

Internal Engineers

0.30.3

0.40.4

0.30.3

long dash—

External Engineers

0.10.1

0.40.4

0.30.3

0.20.2

Joint Design

0.20.2

0.30.3

0.40.4

0.10.1

The expected monetary value using inside engineers to complete the design is

?????

​(Enter

your response as an

integer.​)

The expected monetary value using an outside engineering firm to complete the design is ???

​(Enter

your response as an

integer.​)

The expected monetary value of conducting a joint design is ??

​(Enter

your response as an

integer.​)

What is the best decision based on an expected monetary value​ criterion?

Joint designJoint design

External engineering firmExternal engineering firm

Internal engineers

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

The penalty for completing design late is $14000 per week. This is common for all the decisions.

The internal design will incur an additional overtime cost of $11000 per week. This makes it $25000 per week effective cost. However, there are no other cost associated with this.

The external design will incur a one-time cost of $90000. In addition if the design is late, the late fee of $14000 is applicable.

The join design will cost $60000 + $32000 = $92000. In addition, if the design is late, there will be the delaying cost of $14000 per week.

Expected monetary value using inside engineers = 0.3*0 + 0.4*25000 + 0.3*25000*2 = 25000

Expected monetary value using external engineers = 0.1*90000 + 0.4*(90000+14000) + 0.3*(90000+14000*2)+0.2*(90000+14000*3) = 112400

Expected monetary value using joint design =0.2*92000 + 0.3*(92000+14000) + 0.4*(92000+14000*2)+0.1*(92000+14000*3) = 111600

According the EMV criterion, the best design is inside engineers (as this is the cheapest option)

Add a comment
Know the answer?
Add Answer to:
Sox Engineering designs and constructs air conditioning and heating​ (HVAC) systems for hospitals and clinics. Currently...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • The product design group of Iyengar Electric​ Supplies, Inc., has determined that it needs to design...

    The product design group of Iyengar Electric​ Supplies, Inc., has determined that it needs to design a new series of switches. It must decide on one of three design strategies. The market forecast is for 300 comma 000300,000 units. The better and more sophisticated the design strategy and the more time spent on value​ engineering, the less will be the variable cost. The chief of engineering​ design, Dr. W. L.​ Berry, has decided that the following costs are a good...

  • Discussion questions 1. What is the link between internal marketing and service quality in the ai...

    Discussion questions 1. What is the link between internal marketing and service quality in the airline industry? 2. What internal marketing programmes could British Airways put into place to avoid further internal unrest? What potential is there to extend auch programmes to external partners? 3. What challenges may BA face in implementing an internal marketing programme to deliver value to its customers? (1981)ǐn the context ofbank marketing ths theme has bon pururd by other, nashri oriented towards the identification of...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT