Question

The product design group of Iyengar Electric​ Supplies, Inc., has determined that it needs to design...

The product design group of Iyengar Electric​ Supplies, Inc., has determined that it needs to design a new series of switches. It must decide on one of three design strategies. The market forecast is for

300 comma 000300,000

units. The better and more sophisticated the design strategy and the more time spent on value​ engineering, the less will be the variable cost. The chief of engineering​ design, Dr. W. L.​ Berry, has decided that the following costs are a good estimate of the initial and variable costs connected with each of the three strategies explained below.

​Low-tech​:

a​ low-technology, low-cost process consisting of hiring several new junior engineers. This option has a fixed cost of

​$55 comma 00055,000

and​ variable-cost probabilities of

0.50.5

for

​$0.620.62​,

0.10.1

for

​$0.590.59​,

and

0.40.4

for

​$0.540.54.

Subcontract​:

a​ medium-cost approach using a good outside design staff. This approach would have a fixed cost of

​$65 comma 00065,000

and​ variable-cost probabilities of

0.70.7

of

​$0.460.46​,

0.20.2

of

​$0.430.43​,

and

0.10.1

of

​$0.420.42.

​High-tech​:

a​ high-technology approach using the very best of the inside staff and the latest​ computer-aided design technology. This approach has a fixed cost of

​$75 comma 00075,000

and​ variable-cost probabilities of

0.80.8

of

​$0.390.39

and

0.20.2

of

​$0.310.31.

What is the best decision based on an expected monetary value​ (EMV) criterion?

​(Note​:

We want the lowest​ EMV, as we are dealing with costs in this​ problem.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Calculation of Expected Monetary Value of the three design options
Low Tech
Given the market forecast is 300000 units
50% probab of variable cost being $.62 prob of 10% of variable cost being $.59 and prob of 40% of variable cost being $.54
Expected Variable Cost
300000*((.50*$.62)+(.10*$.59)+(.40*$.54))
300000*.585
$175,500
Total Cost Fixed Cost +Variable Cost
$55000+$175500
$230,500
The expected monetary value is $230500
Subcontract
Calculation of the expected variable cost with the market forecast of 300000 units
Probab of 70% variable cost being $.46 probab of 20% variable cost $.43 and prob of 10% with variable cost of $.42
Expected Variable Cost
300000*(70%*.46+20%*.43+10%*.42)
Total Cost Fixed Cost +Variable Cost
$65000+$135000
$200,000
The expected monetary value is $200000
High Tech
Calculation of the expected variable cost with the market forecast of 300000 units
Prob of 80% with variable cost of $.39 prob of 20% with variable cost of $.31
Expected Variable Cost 300000*(80%*.39+20%*.31)
$112,200
Total Cost Fixed Cost +Variable Cost
$75000+$112200
$187,200
Based on the lowest EMV we find that the lowest cost is in the case of High Tech which is having $187200
Add a comment
Know the answer?
Add Answer to:
The product design group of Iyengar Electric​ Supplies, Inc., has determined that it needs to design...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The product design group of lyengar Electric Supplies, Inc., has determined that it needs to design...

    The product design group of lyengar Electric Supplies, Inc., has determined that it needs to design a new series of switches. It must decide on one of three design strategies. The market forecast is for 150,000 units. The better and more sophisticated the design strategy and the more time spent on value engineering, the less will be the variable cost. The chief of engineering design, Dr. W. L. Berry, has decided that the following costs are a good estimate of...

  • Sox Engineering designs and constructs air conditioning and heating​ (HVAC) systems for hospitals and clinics. Currently...

    Sox Engineering designs and constructs air conditioning and heating​ (HVAC) systems for hospitals and clinics. Currently the​ company's staff is overloaded with design work. There is a major design project due in 99 weeks. The penalty for completing the design late is ​$14 comma 00014,000 per​ week, since any delay will cause the facility to open later than​ anticipated, and cost the client significant revenue. If the company uses its inside engineers to complete the​ design, it will have to...

  • CHAPTER 5 PRODUCT DESIGN 213 DECISION TREE APPLIED TO PRODUCT DESIGN Silicon, Inc, a semcductor m...

    CHAPTER 5 PRODUCT DESIGN 213 DECISION TREE APPLIED TO PRODUCT DESIGN Silicon, Inc, a semcductor manufacturer, is invessigating the possility of producing and marketing a microprocessor. hiring and training several additional engineers. The mark unfavorable. Silicon, Inc., of course, has the option of not developing the new product at all. king this project will require either purchasing a sophisticated CAD system or et for the product could be either favorable or With favorable acceptance by the market, sales would be...

  • Barstow Manufacturing Company has two service departments — product design and engineering support, and two production...

    Barstow Manufacturing Company has two service departments — product design and engineering support, and two production departments — assembly and finishing. The distribution of each service department's efforts to the other departments is shown below: FROM TO Design Support Assembly Finishing Design 0 % 10 % 30 % 60 % Support 20 % 0 % 45 % 35 % The direct operating costs of the departments (including both variable and fixed costs) were as follows: Design $ 140,000 Engineering Support...

  • Barstow Manufacturing Company has two service departments — product design and engineering support, and two production...

    Barstow Manufacturing Company has two service departments — product design and engineering support, and two production departments — assembly and finishing. The distribution of each service department's efforts to the other departments is shown below: FROM TO Design Support Assembly Finishing Design 0 % 10 % 30 % 60 % Support 20 % 0 % 45 % 35 % The direct operating costs of the departments (including both variable and fixed costs) were as follows: Design $ 330,000 Engineering Support...

  • Barstow Manufacturing Company has two service departments-product design and engineering support, and two production departments -...

    Barstow Manufacturing Company has two service departments-product design and engineering support, and two production departments - assembly and finishing. The distribution of each service department's efforts to the other departments is shown below ort Assembl FROMDesig Design Support 0% 10% 70% 60% 20% 0% 10% 30% The direct operating costs of the departments (including both variable and fixed costs) were as follows $110,000 $490,000 $440,000 $700,000 Design Engineering Support Assembly Finishing The total cost accumulated in the finishing department using...

  • Barstow Manufacturing Company has two service departments-product design and engineering support, and two production departments -assembly...

    Barstow Manufacturing Company has two service departments-product design and engineering support, and two production departments -assembly and finishing. The distribution of each service department's efforts to the other departments is shown below. Design Support 0% 20% sign Support Assembly Finishi 60% 35% 10% 0% 30% 45% The direct operating costs of the departments (including both variable and fixed costs) were as follows: Design Engineering Support Assembly Finishing 250,000 270,000 S 990, 000 $1,500, 000 The total cost accumulated in the...

  • A.)1495813 B.)2730000 C.)1034188 D.)994188 E.)1040854 Barstow Manufacturing Company has two service departments - product design and...

    A.)1495813 B.)2730000 C.)1034188 D.)994188 E.)1040854 Barstow Manufacturing Company has two service departments - product design and engineering support, and two production departments - assembly and finishing. The distribution of each service department's efforts to the other departments is shown below: FROM Design Support TO Design Support Assembly Finishing 0% 10% 30% 60% 20% 0% 45% 35% The direct operating costs of the departments (including both variable and fixed costs) were as follows: Design Engineering Support Assembly Finishing $ 210,000 $...

  • Apply the Concepts Kramer Company currently produces a high-tech medical product with 20 parts. Design engineering has...

    Apply the Concepts Kramer Company currently produces a high-tech medical product with 20 parts. Design engineering has produced a new configuration for the product that requires only eight parts. Current activity capacity and demand (20-part configuration) and expected activity demand (8-part configuration) are provided. Activity Capacity Current Expected Activity Activity Demand Demand Activities Activity Driver Material usage Number of parts 300,000 300,000 15,000 7,500 Assembling parts Direct labor hours 15,000 15,000 Purchasing parts Number of orders 20,000 15,000 9,750 Additionally,...

  • In mid-2005 Gunawan Wiboto (Gunawan), an ethnic Chinese Indonesian entrepreneur and founder of the Ramayana Group,...

    In mid-2005 Gunawan Wiboto (Gunawan), an ethnic Chinese Indonesian entrepreneur and founder of the Ramayana Group, decided to build a steel mill incorporated as a new company: PT Hanuman Steel. His team began the search for an experienced engineering consultant for the project. The company approached several consulting firms reputed for their engineering services. The difficulty, as they quickly discovered, was finding a consultant who believed they could do it their way and be successful. The required services fell into...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT