Rizio Co. purchases a machine for $14,300, terms 1/10, n/60, FOB
shipping point. The seller prepaid the $323 freight charges, adding
the amount to the invoice and bringing its total to $14,623. The
machine requires special steel mounting and power connections
costing $989. Another $466 is paid to assemble the machine and get
it into operation. In moving the machine to its steel mounting,
$350 in damages occurred. Materials costing $40 are used in
adjusting the machine to produce a satisfactory product. The
adjustments are normal for this machine and are not the result of
the damages.
Complete the below table to calculate the cost recorded for this
machine. (Rizio pays for this machine within the cash discount
period.)
Rizio Co. purchases a machine for $14,300, terms 1/10, n/60, FOB shipping point. The seller prepaid...
Rizio Co purchases a machine for $13,800, terms 1/10. n/60, FOB shipping point. The seller prepaid the $312 freight charges, adding the amount to the invoice and bringing its total to $14.112. The machine requires speci $954. Another $450 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting. $365 in damages occurred. Materials costing $40 are used in adjusting the machine to produce a satisfactory product. The adjustments are normal...
Rizio Co. purchases a machine for $9,800, terms 1/10, n/60, FOB shipping point. The seller prepaid the $221 freight charges, adding the amount to the invoice and bringing its total to $10,021. The machine requires special steel mounting and power connections costing $677. Another $319 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting, $305 in damages occurred. Materials costing $40 are used in adjusting the machine to produce a...
10 Rizio Co. purchases a machine for $13,600, terms 2/10, n/60, FOB shipping point. The seller prepaid the $307 freight charges, adding the amount to the invoice and bringing its total to $13.907. The machine requires special steel mounting and power connections costing $940. Another $443 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting $260 in damages occurred. Materials costing $40 are used in adjusting the machine to produce...
Rizio Co. purchases a machine for $11,600, terms 2/10, n/60, FOB shipping point. The seller prepaid the $262 freight charges, adding the amount to the invoice and bringing its total to $11,862. The machine requires special steel mounting and power connections costing $802. Another $378 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting, $275 in damages occurred. Materials costing $40 are used in adjusting the machine to produce a...
Exercise 8-1 Cost of plant assets LO C1 Rizio Co. purchases a machine for $11,300, terms 2/10, n/60, FOB shipping point. The seller prepaid the $255 freight charges, adding the amount to the invoice and bringing its total to $11,555. The machine requires special steel mounting and power connections costing $781. Another $368 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting, $360 in damages occurred. Materials costing $40 are...
Rizio Co. purchases a machine for $13,900, terms 1/10, n/60, FOB shipping point. Rizio paid within the discount period and took the $139 discount. Transportation costs of $314 were paid by Rizio. The machine required mounting and power connections costing $961. Another $453 is paid to assemble the machine and $40 of materials are used to get it into operation. During installation, the machine was damaged and $315 worth of repairs were made points Complete the below table to calculate...
Rizio Co. purchases a machine for $10,900, terms 2/10, n/60, FOB shipping point. Rizio paid within the discount period and took the $218 discount. Transportation costs of $246 were paid by Rizio. The machine required mounting and power connections costing $754. Another $355 is paid to assemble the machine and $40 of materials are used to get it into operation. During installation, the machine was damaged and $225 worth of repairs were made. Complete the below table to calculate the...
Rizio Co. purchases a machine for $14,900, terms 2/10, n/60, FOB shipping point. Rizio paid within the discount period and took the $298 discount. Transportation costs of $337 were paid by Rizio. The machine required mounting and power connections costing $1,030. Another $486 is paid to assemble the machine and $40 of materials are used to get it into operation. During installation, the machine was damaged and $375 worth of repairs were made. Complete the below table to calculate the...
Rizio Co. purchases a machine for $11,600, terms 2/10,n/60, FOB shipping point. Rizio paid within the discount period and took the $232 discount. Transportation costs of $262 were paid by Rizio. The machine required mounting and power connections costing $802. Another $378 is paid to assemble the machine and $40 of materials are used to get it into operation. During installation, the machine was damaged and $370 worth of repairs were made. Complete the below table to calculate the cost...
Rizio Co purchases a machine for $12,500, terms 2/10,n/60, FOB shipping point. Rizio paid within the discount period and took the $250 discount. Transportation costs of $360 were paid by Rizio. The machine required mounting and power connections costing $895 Another $475 is paid to assemble the machine and $40 of materials are used to get it into operation. During installation, the machine was damaged and $180 worth of repairs were made. Complete the below table to calculate the cost...