Before preparing decision evaluation display, we need to check the availability and total cost for all the machines.
Availability
Total no. of weeks in a year = 52 weeks
Downtime of A = 1 week
Availability of A = (52-1) / 52 = 51/52 = 0.9807
Downtime of B = 2 weeks
Availability of B = (52-2) / 52 = 50/52 = 0.9615
Downtime of C = 4 weeks
Availability of C = (52-4) / 52 = 48/52 = 0.9231
Total Life Cycle Cost
1. Acquisition Cost
For Machine A = $110,000.
For Machine B = $75,000
For Machine C = $25,000
2. Interest
Assuming the simple interest for 5 years,
where P = Acquisition Cost, R = Rate of interest = 9%, N = No. of years = 5 years
3. Downtime Cost
Downtime Cost = Total Downtime in a year * No. of years * Cost per downtime
Downtime Cost of A = 1 * 5 * 10,000 = $50,000
Downtime Cost of B = 2 * 5 * 5,000 = $50,000
Downtime Cost of C = 4 * 5 * 5,000 = $100,000
Total Life Cycle Cost = Acquisition Cost + Interest + Downtime Cost
Total Life Cycle Cost of A = 110,000 + 49,500 + 50,000 = $209,500
Total Life Cycle Cost of B = 75,000 + 33,750 + 50,000 = $158,750
Total Life Cycle Cost of C = 25,000 + 11,250 + 100,000 = $136,250
Decision Evaluation Display :
Machine Requirement :
Option | Requirements | Decision Consideration | |
---|---|---|---|
Availability | Acquisition Cost | Total Life Cycle Cost | |
A | 0.9807 | $110,000 | $209,500 |
B | 0.9615 | $75,000 | $158,750 |
C | 0.9231 | $25,000 | $136,250 |
Assumption : Simple Interest method is assumed in calculation of Interest for calculating Total Life Cycle cost.
Comments on options
Option A : Option A satisfies the requirements for both, Availability and Acquisition Cost however Total Life Cycle cost of A is very high compared to rest 2 options.
Option B : Option B satisfies the requirements for both, Availability and Acquisition Cost. Total Life Cycle cost of B is comparable to most economical option C.
Option C : Option C satisfies the requirement for Acquisition Cost however it does not satisfy the requirement of Availability. As it is not satisfying the basic requirement, even after having most economic costs, option C can't be used.
As option C is not valid, we are left with only two options A and B. Both satisfies basic requirements however Total Life Cycle Cost of B is very less as compared to A and hence we should select Option B.
13. A manufacturing company, called "Manufacturing Co", must purchase new equipment for one of its assembly...
Investment Evaluation Analysis Widget Company is considering upgrading its manufacturing equipment. The Vice-President of Production has identified three possible actions Widget could take to accomplish the upgrade, though none is required. One option would upgrade their current equipment and the other two options would replace the existing equipment with purchases of new equipment. The review committee has asked you to review each of the options to identify relevant cost data and to prepare a schedule comparing the three options to...
The table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation, Your company is responsible for the installation project. Indirect costs are $10,000 per week, and a penaity cost of $9,000 per week will be incurred by your company for every week the project is delayed beyond week12. Normal Time Crash Time Normal Cost Crash Cost Activity Immediate Predecessor(s) (weoks) (weeks)(5) long dash- long dash- 7,000 3,000 14,000 3,000 12,00040,000 12,000 22,000 8,000...
ABC Co. is considering its options for managing its IT infrastructure. The cost of each alternative depends on demand for services, a function of the company's growth. The annual cost of each option (in thousands of dollars) is included in the table above. a) If demand probabilities are .4, .4, and .2 for high, medium, and low demand, respectively, which alternative will minimize the expected cost of IT? b) Assuming you choose the option with the lowest expected cost, what...
2 Jackson Hole Manufacturing Jackson Hole Manufacturing is a small manufacturer of plastic products used in the automotive and computer industries. One of its major contracts is with a large computer company and involves the 2 production of plastic printer cases for the computer companys portable printers. The printer cases are produced on two injection molding machines. The M-100 machine has a production capacity of 25 printer cases per hour, and the M-200 machine has a production capacity of 40...
Problem 13-41 A manager is going to purchase new processing equipment and must decide on the number of spare parts to order with the new equipment. The spares cost $182 each, and any unused spares will have an expected salvage value of $52 each. The probability of usage can be described by this distribution: Number 0 Probability .05 1 .40 2 .20 3 .35 If a part fails and a spare is not available, 2 days will be needed to...
B2B Co. is considering the purchase of equipment that would allow the company to add a new product to its line. The equipment is expected to cost $120,000 with a 12-year life and no salvage value. It will be depreciated on a straight-ine basis. The company expects to sell 48,000 units of the equipment's product each year. The expected annual income related to this equipment follows. 75,000 Sales Costs Materials, labor, and overhead (except depreciation on new equipment) Depreciation on...
Suppose Procter and Gamble (P&G) is considering purchasing $ 13 million in new manufacturing equipment. If it purchases the equipment, it will depreciate it on a straight-line basis over the five years, after which the equipment will be worthless. It will also be responsible for maintenance expenses of $ 0.50 million per year. Alternatively, it can lease the equipment for $ 3.0 million per year for the five years, in which case the lessor will provide necessary maintenance. Assume P&G?s...
B2B Co. is considering the purchase of equipment that would allow the company to add a new product to its line. The equipment is expected to cost $374,400 with a 12-year life and no salvage value. It will be depreciated on a straight-line basis. The company expects to sell 149,760 units of the equipment's product each year. The expected annual income related to this equipment follows. $ 234,000 Sales Costs Materials, labor, and overhead (except depreciation on new equipment) Depreciation...
PART III. Rimrock Construction Co. is purchasing a new piece of equipment for $34,000. The unit is expected to produce $21,000 for each of the next 4 years and will be sold at the end of that time for an expected salvage value of $4,000. Maintenance and expenses on the equipment are expected to be $2,000 for the fisrt year and to increase by $500 per year for each successive year of operation. Rimrock is purchasing the equipment by paying...
B2B Co. is considering the purchase of equipment that would allow the company to expected to cost $376,000 with a 12 year life and no salvage value. It will be depreciated on a straight-line basis. The company expects to sell 150,400 units of the equipment's product each year. The expected annual income related to this equipment follows. $ 235,000 Sales Costs Materials, labor, and overhead (except depreciation on new equipment) Depreciation on new equipment Selling and administrative expenses Total costs...