Question

Need correct and complete solution

Example 5: Using the following information calculate each of three labour variances for each department: Dept. A 25,000 Parti

0 0
Add a comment Improve this question Transcribed image text
Answer #1

LABOUR COST VARIANCE (LCV)= STANDARD COST - ACTUAL COST

LABOUR RATE VARIANCE (LRV) = ACTUAL TIME * [STANDARD RATE - ACTUAL RATE ]

LABOUR EFFICIENCY VARIANCE (LEV) = STANDARD RATE * [ STANDARD TIME - ACTUAL TIME ]

VERIFY USING LCV = LRV + LEV

DEPT A DEPT B
LCV -5000 +10000
LRV -8000 +12000
LEV +3000 -2000

① Dept. A:- Can Values en Currency habour Cost Variance. Standard Cost - Actual cost - (10,000x 2 ) - (850025500) - 20,000 -

Add a comment
Know the answer?
Add Answer to:
Need correct and complete solution Example 5: Using the following information calculate each of three labour...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • CR Company has the following estimated costs for the next year: Direct materials Direct labour Rent...

    CR Company has the following estimated costs for the next year: Direct materials Direct labour Rent on factory building Sales salaries Depreciation on factory equipment Indirect labour Production supervisor's salary $ 4,000 20,000 15,000 25,000 8,000 10,000 12,000 CR Company estimates that 20,000 labour hours will be worked during the year. If overhead is applied on the basis of direct labour hours, the overhead rate per hour will be?

  • 9. Markus Limited produces a specialised machine part used in forklifts. For last year's perations, the following d...

    9. Markus Limited produces a specialised machine part used in forklifts. For last year's perations, the following data were gathered: Units produced: 55,000 Direct labour: 29,000 hours @ $9.00 Actual variable overhead: $135,000 Markus employs a standard costing system. During the year, a variable overhead rate of $5.00 was used. labour standard requires 0.50 hours per unit produced. The variable overhead spending and efficiency variances are, respectively: A. $10,000 U and $7,500 U B. $10,000 F and $7,500 U C....

  • Chancer plc has two departments through which work passes. Costs are related to these departments and...

    Chancer plc has two departments through which work passes. Costs are related to these departments and overheads are charged to jobs on the basis of departmental direct wages percentage. Expenses for the year and other related information are as follows: Budgeted overheads Actual overheads £ £ Rent and rates 40,000 Department 1 92,500 Insurance of plant 12,000 Department 2 70,100 Canteen costs 12,000 Heat and light 3,000 Material handling costs 25,000 Xmas dance 8,000 Actual direct wages Depreciation of plant...

  • using Alternative method as shown in this picture Materials used ? Labour cost ? ? nal...

    using Alternative method as shown in this picture Materials used ? Labour cost ? ? nal Entries (LO2, LO3. L04 PROBLEM 10B-3 Comprehensive Variance Analysis: Journal Entries ILO LOS. LO6, LO9] Haliburton Mills Inc. is a large producer of men's and women's clothing standard costs for all of its products. The standard costs and actual costs for are given below for one of the company's product lines (per unit of product 's clothing. The company uses al costs for a...

  • Variances questions, Introduction To Management Accounting 2 help me in all of them please if possible....

    Variances questions, Introduction To Management Accounting 2 help me in all of them please if possible. thank you. QUESTION -VARIANCES 2 The standard cost card for product Z shows the following details: Standard costs per unit of Z produced: 4 kgs of material A €3.10 per kg 3 litres of material B @ €1.70 per litre 2.5 hours of direct labour €12 per hour Variable production overhead @ €10 per direct labour hour Standard factory cost per unit 12.40 5.10...

  • Question 3 Blue Ltd a manufacturing business with three production departments and one service department and...

    Question 3 Blue Ltd a manufacturing business with three production departments and one service department and has budgeted costs by department as follows: Dept Dept2 Depr3 Stores 320 480 200 Direct labour (£000) 240 280 240 Indirect labour (£000) 320 Production Requisition notes (000's) 120 160 40 Indirect materials (£000) 30,000 30,000 20,000 10,000 Area occupied (sqm) 20 70 10 Use of external maintenance (%) 40 The following additional information is available: • Total external maintenance costs will be £25,000...

  • sol th Question 4 (10 marks) The following is the standard cost card for X Company's...

    sol th Question 4 (10 marks) The following is the standard cost card for X Company's only product: Direct materials, 4 metres at $4.00 Direct labour, 1.5 hours at $10.00 Variable overhead, 1.5 hours at $3.00 Fixed overhead, 1.5 hours at $7.00 Standard cost per unit $16.00 $15.00 $4.50 $10.50 $46.00 The company manufactured and sold 18 000 units of product during the year. A total of 70,200 metres of material was purchased durine the vear at cost of $4.20...

  • Q.1 Amben LTD, makes a product, the Arigato, which has the following unit costs: Direct materials...

    Q.1 Amben LTD, makes a product, the Arigato, which has the following unit costs: Direct materials $8, Direct labour cost $4, variable production cost $2. The company has fixed selling price at $30 per unit. At the beginning of September 2020, there were no opening inventories and production during the month was 20,000 units. Fixed costs for the month were $45,000 (production administration, sales, and distribution). There were no variable marketing costs. Required Calculate the contribution and profit for September...

  • SHOW ALL THE WORK IN GREAT DETAIL The following is the standard cost card for Harper...

    SHOW ALL THE WORK IN GREAT DETAIL The following is the standard cost card for Harper Inc's only product: Direct material, 4 oz. at $3.00/oz. Direct labour, 0.5 hours at $14.70/DLH Variable MOH, 0.5 hours at $20.00/DLH Fixed MOH, 0.5 hours at $28.00/DLH Standard cost per unit $12.00 7.35 10.00 14.00 $41.00 The company manufactured and sold 8,000 units of product during the year. A total of 20,000 oz. of material was purchased during the year at a total cost...

  • fill in the missing numbers Consider the following data provided for each of the following independent...

    fill in the missing numbers Consider the following data provided for each of the following independent cases. For each case assume that the business uses a standard cost system and a flexible budget to control variable and fixed manufacturing overhead, and applies manufacturing overhead on the basis of direct labour hours. Fill in the blanks for each case, and indicate whether the variances are favourable (F) or unfavourable (U). Phi Company Pho Company Number of labour hours budgeted $10,600 hrs...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT