Converting each capacity to a process time:
Station 1 = 60min/hr ÷ 20 units/hr = 3 min/unit (for both Machine A and Machine B)
Station 2 = 60min/hr ÷ 3 units/hr = 20 min/unit
Station 3 = 60min/hr ÷ 15 units/hr = 4 min/unit
Bottleneck operation is Station 2, at 20 min per unit
So the answer is :- 20 min/unit
KINDLY RATE THE ANSWER AS THUMBS UP. THANKS A LOT.
AT&T 6:17 PM @ ร 5960 0. + a mathxl.com omework: Chapter S7 Homework HN Score:...
Homework: Chapter 7 Homework Save Score: 0 of 3 pts 6 of 15 (0 complete) HW Score: 0%, 0 of 72 pts S7-6 (similar to) Question Help Ocean Cruiseline offers nightly dinner cruises departing from several cities on the eastern coast of the United States including Charleston, Baltimore, and Alexandria. Dinner cruise tickets sell for $50 per passenger. Ocean Cruiseline's variable cost of providing the dinner is $20 per passenger, and the fixed cost of operating the vessels (depreciation, salaries,...