Question

LS Hydrogeology is a water and minerals exploration company. It was recently commissioned by the Zambian...

LS Hydrogeology is a water and minerals exploration company. It was recently commissioned by the Zambian government to make hydro geological maps which would be obtained at different locations around Zambia. The assignment would involve explorations, sample analysis onsite and computer-graphic displays to produce maps. Managing the preparation for the whole assignment was the responsibility of the project engineer, Bill Kalinda. Bill, who had recently graduated from his MSc Project Management course at the University of Lusaka, knew that he would need to keep a tight grip on the arrangements for the explorations to start successfully. The explorations would start at the end of May and the final targeted site would be explored at the end of July. The hydro geological maps are required between early July and late August, so any delay either in exploration or in producing the maps would cause considerable complications. The company had known that it would be commissioned to make the hydro geological maps since December, but Bill had only been allocated the job to start in first week of February! His first act was to list the various jobs which would have to be done before explorations could start. He then discussed each job with the part of the company which would carry it out, to try to understand what decisions would need to be made before they could start on their jobs. The jobs which needed to be done prior to the start of the explorations are listed below together with some details. Note the jobs’ IDs in brackets where arbitrarily allocated. The project engineer’s responsibilities (as well as managing the whole project) included: (a) Scheduling the Sites: would take about two weeks to finalize and could be started straight away. (b) Defining the field work routing: would need discussions with the chief designer and would take about four weeks of considering alternative designs before finalizing the concept, but could be started straight away. (e) Specifying computer-graphic displays: again in consultation with the chief designer, it would take about a week but could not be started until all the detailed planning had been finalized. 2 | P a g e The design department’s responsibility was: (f) Producing designs for field work routing: would take about three weeks but could be started only after completion of the detailed planning. The project planning department’s responsibilities were: (c) Secure exploration sites from the Ministry of Minerals and Water Development: a one-week job which could be started as soon as the sites had been decided by Bill. (d) Detailed planning: the preparation of detailed plans and schedules, a two-week task which could be started once the design concept had been finalized and the sites secured. (g) Printing field work routing charts: an outside printer could be given this job as soon as the designs for field work routing had been prepared by the design department. The printer usually quoted a four-week delivery from receipt of the designs. (h) Printing the display posters: again depended on the preparation of the designs for field work routing but could be delivered within two weeks of the designs being ready. (i) Ordering the exploration vehicles: a trailer truck and ancillary vehicles were needed which could be ordered on completion of the detailed planning; delivery of the vehicles would take about six weeks. (j) Writing the customised graphic display software: contracted out to a software house, it would take about four weeks but could only be started after the computer graphics had been specified by the project engineer and chief designer. (n) Final testing and Kickoff: the project planning department were finally responsible for getting the ‘whole act together’ immediately prior to explorations. Testing could only start once the field work routing charts had been printed, the vehicles fully fitted out and customized and the exploration staff trained. Final tests and kickoff should take around a week but, if things went wrong at any stage, could take longer. The workshop’s responsibility was: (k) Customizing and fitting out the vehicles: after the exploration vehicles are delivered and the designs for field work routing agreed and the computer-graphics software finished, the vehicles could be fitted out and customized for the explorations; this would normally take around two weeks. The personnel department was responsible for: (l) Recruiting the exploration staff: these were the people who did the actual work in the field; they could be recruited as soon as the detailed planning was completed. Usually it took two weeks to recruit all the exploration staff. (m) Training the promo staff: once all exploration staff had been recruited they would need training – a one-week task. Requirements: (a) Prepare an Activity Logic Table for this project. (14 marks) (b) Can Bill get the project together in time to start explorations on schedule? Show workings. (16 marks) (c) Name the jobs which Bill will have to manage particularly closely? Why? (10 marks) (d) What other general advice would you give Bill to help him to manage this project? (10 marks)

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Project Description: LS Hydrogeology is a water and minerals exploration company. It was recently commissioned by the Zambian government to make hydrogeological maps which would be obtained at different locations around Zambia.
Project Engineer-Bill Kalinda
Activity Duration Start Time End Time Dependent Variables
Start of explorations 30-May
A final targeted site would be explored 31-Jul
Hydrological maps are required 31 July-30 Aug
Bill had only been allocated the job 01-Feb
The project engineer’s responsibilities
Scheduling the Sites Two weeks 01-Feb 15-Feb
Defining the fieldwork routing four weeks 01-Feb 28-Feb would need discussions with the chief designer
Specifying computer-graphic displays One week 01-Mar 08-Mar would need discussions with the chief designer
Design Departments Responsibilities
Producing designs for field work routing three weeks 01-Mar 21-Mar start after completion of detailed planning
Secure exploration sites from the Ministry of Minerals and Water Development one week 16-Feb 23-Feb start on finalizing of the site by bill
Detailed planning two weeks 16-Feb 28-Feb start on finalizing the design concept
Printing field work routing charts four weeks 21-Mar 20-Apr dependent on fieldwork routing
Printing the display posters two weeks 21-Mar 07-Apr dependent on fieldwork routing
Ordering the exploration vehicles six weeks 01-Mar 15-Apr ordered on completion of the detailed planning
Writing the customized graphics display software: four weeks 08-Mar 07-Apr could only be started after the computer graphics had been specified by the project engineer and chief designer.
Final testing and Kickoff one week around a week
Customizing and fitting out the vehicles two weeks 16-Apr 30-Apr
The personnel department
Recruiting the exploration staff two weeks 01-Mar 15-Mar they could be recruited as soon as the detailed planning was completed.
Training the promo staff one week 16-Mar 23-Mar

b. According to the activity, tracker bill has a buffer of 30 days for crisis management or unexpected delays, if he follows above schedules to the T.

c. Bill have to closely manage the finalization of design concept, the detailed plan and the field routing based on which the entire activities are based.

d. I would advise Bill to follow above schedule, keep in touch with planning, design and recruiting on a daily basis and analyze the tasks achieved on a daily tracker. He should also advise all teams to report to him in case they see any delay or unexpected failure in meeting the dateline/ deadlines.

Add a comment
Know the answer?
Add Answer to:
LS Hydrogeology is a water and minerals exploration company. It was recently commissioned by the Zambian...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Orleans Construction Company Case (adapted from Meredith and Mantel) The Orleans Construction Company, a small construction...

    Orleans Construction Company Case (adapted from Meredith and Mantel) The Orleans Construction Company, a small construction company in North Carolina, has been awarded a contract for the construction of a new 25,000 soccer stadium at Greensboro. The City is hoping to use this facility to attract a new soccer franchise. The construction cannot start earlier than March 2, 2020 (because of the availability of bond funds) and must be completed within 1 year (52 weeks). A penalty clause of $13,000...

  • 150 words minimum Do you agree or disagree with this post? There is so much that...

    150 words minimum Do you agree or disagree with this post? There is so much that I learned in this class. I never knew about the process that is involved in hiring someone. I always knew that when a friend started the interview process that it was going to take a couple weeks or more before they knew if they got the job or not. It always started with the phone interview, maybe another phone interview, then if they made...

  • Conflict and Negotiation. Paul, 33 years of age graduated with a Master’s degree in Geology from...

    Conflict and Negotiation. Paul, 33 years of age graduated with a Master’s degree in Geology from McGill University in 2002. Since graduation he had worked for a small oil exploration company in Newfoundland. He enjoyed the work, his boss and peers but there was limited opportunity for advancement. He was recently married to a girl from Ontario and just discovered he was about to be a father. Paul decided it was time to explore new employment opportunities. A short time...

  • Apollo Tech Solutions Case Study Part Two The deadline for submitting proposals was 8 April 2012...

    Apollo Tech Solutions Case Study Part Two The deadline for submitting proposals was 8 April 2012 and Arnott was looking forward to receiving three submissions from the consulting firms. He cleared his diary and arranged the meetings for the following two weeks. Ferguson & Co and EuroComms Solutions came back immediately with dates to present their initial proposals to him; however, ITL seemed very reluctant to agree to time. Finally, Arnott was contacted by the Senior Partner in their Strategy...

  • #81: AT&T 6:32 PM week 5 Case Study: Not for IV Use: The Sto… document Background...

    #81: AT&T 6:32 PM week 5 Case Study: Not for IV Use: The Sto… document Background Detail Submission Grade On July 18, 2006, my daughter Robin was admitted to the hospital. She was 24 years old, and she was 35 weeks pregnant. She was admitted for intractable pain, vomiting, and dehydration. It wasn't the first time Robin had been admitted to the hospital. She had had episodes with similar symptoms from the time she was 11 or 12 years old...

  • Write a case study include a summary, background, analysis and insights. Answer questions at the end...

    Write a case study include a summary, background, analysis and insights. Answer questions at the end Video Case Ross Lohr and Nathan Rothstein have built a thriving smallmanufacturers that paid and treated their workers well. The business from the idea of giving old T-shirts new life by hav- new business plan reflects this change in direction. Simply ing them cut into squares and sewn into comfortable fleece put, Project Repat gets the old tees from customers, cuts backed quilts. The...

  • 2. Wendy’s friend Bob worked for the same software company but they didn’t renew his contract....

    2. Wendy’s friend Bob worked for the same software company but they didn’t renew his contract. Now he’s applying for jobs, but can’t collect unemployment benefits because he wasn’t technically an employee. Bob is: Not in the labor force but "marginally attached" Unemployed Not in the labor force and not "marginally attached" 3. Jim works in construction, but his project got shut down for a week because of a snowstorm. As a result, Jim didn’t get paid. He’ll go back...

  • PROBLEM ONE Bill Watkins is a Chartered Professional Accountant. He carried on a professional business as...

    PROBLEM ONE Bill Watkins is a Chartered Professional Accountant. He carried on a professional business as a tax consultant for 12 years. By the end of 2019, the practice had grown very large. Bill was overworked and under pressure to hire additional staff or take a partner. He was interested in education and several years earlier had contracted with a publisher to write a book on taxation for university students. Because of the pressures of his practice, this project made...

  • Case Study: Dante and Tiffany both work for an advertising company and were assigned a new...

    Case Study: Dante and Tiffany both work for an advertising company and were assigned a new account together. Their manager, who was very intimating with a loud, assertive voice, instructed them to create a proposal for the new customer which included a design for a restaurant logo and advertising slogan to be used on several billboards throughout the area. They had one week to create the proposal before it would be presented to the restaurant owners. Their boss raised his...

  • What is the big picture according to best practices in family involvement in early education? Case...

    What is the big picture according to best practices in family involvement in early education? Case 4 Developmentally Appropriate Practices in Head Start The Teacher city. Home-based programs are also a part of the New Rock Head Start. With a population of about variety of communities economically prosperous than others. Also, some neighborhoods are more cultur- ally diverse than others. All of the Head Start pre schools are held in churches and agency buildings in the downtown area. Transportation is...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT